質問 # 30
Which object is relevant in assembly processing to create an assembly order for the SD document?
- A. Project profile
- B. Item category
- C. Requirement class
- D. Control key
正解:A
質問 # 31
Where do you maintain the length of the project ID?
- A. Special characters
- B. Project profile
- C. Project type
- D. Project coding mask
正解:D
質問 # 32
Which statement is valid regarding networks?
- A. A network can be activity-account-assigned and header-account-assigned
- B. A network activity can be assigned to several WBS elements
- C. Material components can be assigned to activity elements
- D. Relationships can be used to connect activities of different networks
正解:B
質問 # 33
The basic dates of subordinate WBS elements should be extrapolated without taking into account the basic dates of higher-level WBS elements. What planning method for basic dates do you use ?
- A. Strict bottom-up
- B. Free planning
- C. Bottom-up
- D. Top-down
正解:B
解説:
To extrapolate the basic dates of subordinate WBS elements without taking into account the basic dates of higher-level WBS elements, you can use free planning as the planning method for basic dates. Free planning is a type of planning method for basic dates that allows you to plan dates for WBS elements without any restrictions or dependencies on other WBS elements. Free planning does not consider any hierarchical relationships between WBS elements when calculating their dates. Free planning gives you maximum flexibility and control over your date planning for WBS elements. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
質問 # 34
What are valid procurement types for stock items? Note: There are 3 correct answers to this question
- A. Planned order
- B. Third-party order
- C. Purchase requisition and Reservation for WBS element
- D. Reservation for WBS element
- E. Preliminary purchase requisition for WBS element
正解:A、B、C
解説:
Stock items can be procured using planned orders, third-party orders, or purchase requisitions and reservations for WBS elements. Preliminary purchase requisitions are used for non-stock items and reservations are used for stock items that are already available in the warehouse. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
質問 # 35
You are using budgeting and active availability control. How can availability control be activated? Note: There are 2 correct answers to this question
- A. Background activation (CJBV - Activate Availability Control) l
- B. Automatic activation with budget assignment
- C. Automatic activation with the first actual posting
- D. Automatic activation with assignment to an investment program
正解:A、B
質問 # 36
When you create a service activity in your network, what data can be entered? Note: There are 3 correct answers to this question.
- A. Service purchase order number
- B. Material master within service specification
- C. Overall limit (maximum value of all unplanned services)
- D. Service specification
- E. Vendor
正解:C、D、E
解説:
When you create a service activity in your network, you can enter a service specification, an overall limit, and a vendor. The service specification defines the scope and details of the service to be performed. The overall limit sets a maximum value for all unplanned services that can be entered during service entry. The vendor specifies the external service provider who will perform the service. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
質問 # 37
Cost and Budget
What function are available for period end-closing in the project System?
- A. Confirmation
- B. Result analysis
- C. Settl ement
- D. Progress analysis
- E. Milestone trend analysis
正解:B、D、E
質問 # 38
Which report can use user-specific layouts?
- A. Cost element report
- B. Line item report
- C. Enhanced individual overview
- D. Hierarchical report
正解:C
質問 # 39
You want to use subnetworks during the project. Which of the following statements describes subnetworks?
- A. Maintenance orders can be defined as sub-network
- B. Subnetworks must be scheduled separately from the superior network
- C. The scheduling type of a subnetwork is always copied from the superior network
- D. A subnetwork cannot be defined for a superior subnetwork.
正解:C
解説:
One statement that describes subnetworks is that the scheduling type of a subnetwork is always copied from the superior network. A subnetwork is a network that covers only part of a project and is linked in relationships with other subnetworks in the same project. A subnetwork can be used to refine and detail your networks as planning progresses. The scheduling type is a parameter that determines how the dates of activities and networks are calculated based on their dependencies and constraints. The scheduling type of a subnetwork is always copied from the superior network when creating or changing a subnetwork. The scheduling type of a subnetwork cannot be changed independently from the superior network. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/f373bb53707db44ce10000000a174cb4.html
質問 # 40
Cost & Budget.
A customer wants to allocate overhead rates to a WBS element. What must you assign to the WBS element?
- A. Settlement rules
- B. Results analysis key
- C. Costing Sheet
- D. Investment profile.
正解:A
質問 # 41
Which orders or documents can be displayed in Project-Oriented Procurement (ProMan)? Note: There are 2 correct Answers to this question.
- A. Sales order items
- B. Reservations
- C. Internal orders
- D. Purchase order items
正解:B、D
質問 # 42
For which objects can billing plans be created? Note: There are 2 correct Answers to this question.
- A. Project definition
- B. Milestones
- C. Sales order items
- D. WBS elements
正解:C、D
質問 # 43
In your logistics project you want to carry out the internal project work as soon as possible. What do you have to maintain in capacity requirements planning?
- A. Scheduling and distribution key
- B. Control key of an activity
- C. Scheduling and capacity category
- D. Capacity planner group in the network header
正解:A
質問 # 44
Where can you assign the use status profile for WBS elements? Note: There are 3correct answers to this question
- A. In the project profile
- B. In the project version
- C. In the operative WBS element
- D. In the project definition of a standard WBS
- E. In the project type
正解:A、C、D
質問 # 45
To which object can you assign a factory calendar?
- A. Relationship
- B. Milestone
- C. Material component
- D. Network header
正解:D
解説:
To assign a factory calendar, you can use the network header. The network header is a structural element of a network that contains general data and settings for a network, such as its order type, number range, scheduling parameters, and so on. The network header also contains the factory calendar field, which allows you to assign a factory calendar to a network. A factory calendar is a parameter that defines the working days and holidays for a plant or a location. A factory calendar is used to determine the dates and durations of activities and networks based on their workdays and non-workdays. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
質問 # 46
A component is assigned to a network activity. What are the prerequisites to generate project stock reservations? Note: There are 3 correct Answers to this question.
- A. The material master of the component must permit project stock management.
- B. The network activity is assigned to a WBS element.
- C. The network is assigned to a sales order item.
- D. A procurement indicator must be assigned to the activity.
- E. The Project Stock indicator is set in the project definition (non-valuated or valuated).
正解:A、D、E
質問 # 47
You have saved a network and activities with assigned material components. As soon as you release the network, you receive the error message "Business transaction cannot be carried out". What could be the reason for this error message?
- A. Missing budget for material components
- B. Missing material availability
- C. Missing authorizations to release material components
- D. Missing reservations for material components
正解:C
質問 # 48
......