質問 11
In order for a business unit to have its own Idea Portal to retrieve data, what must be configured first?
- A. Idea Portal URL
- B. Idea module
- C. Idea categories
- D. A business unit cannot have its own its own Idea Portal
正解: B
質問 12
An it_pps_admin user is able to update: (Choose two.)
- A. Budget Periods.
- B. Client Scripts.
- C. Business Rules.
- D. Portfolio Targets.
正解: A,D
質問 13
Which roles can modify agile properties? (Choose two.)
- A. it_pps_admin.
- B. scrum_master.
- C. product_owner.
- D. admin.
正解: A,D
質問 14
Plugins may be added to the base platform in one of the following ways: (Choose three.)
- A. Activated by default in the base ServiceNow system.
- B. Requested from ServiceNow.
- C. Activated by an it_portfolio_manager.
- D. Activated by an admin (not by default).
- E. Activated by an it_pps_admin.
正解: A,B,D
質問 15
Which of the following roles can access the project administration application?
- A. timecard_admin.
- B. it_project_manager.
- C. it_pps_admin.
- D. it_project_user.
正解: C
質問 16
The RIDAC workflow can be modified by using which feature?
- A. Flow Designer
- B. Service Catalog
- C. Idea Portal
- D. Project Form
正解: D
質問 17
A project expense line is a cost associated with a specific source. Examples of specific sources could include:
(Choose three.)
- A. Demand.
- B. Configuration Item (CI).
- C. Project.
- D. Fixed Asset.
- E. User.
正解: B,D,E
質問 18
When entering time worked into a time sheet, which feature is recommended to group different types of work (e.g., standard hours and overtime)?
- A. Bill rate
- B. Category
- C. Rate type
- D. Rate model
正解: C
質問 19
When can a user choose from multiple rate types for their work, while logging a time card?
- A. Only if this capability is enabled in the Project Record
- B. Only if the capability is enabled in the Project Preferences
- C. Only if the capability is enabled in the Time Sheet Policies
- D. Only one (1) rate type can apply
正解: C
質問 20
A pps_admin role can configure the parameters that are displayed on a project card. The parameters displayed on a project card are derived from the records in what table?
- A. Project Time Card Exception [project_time_category].
- B. Theme [scrum_theme].
- C. PM Home Page Card [pm_home_page_card].
- D. CMDB Health Scorecard [cmdb_health_scorecard_group].
正解: C
質問 21
Which role can configure the parameters of the demand workbench that is provided with the base system?
- A. business_stakeholder.
- B. it_project_manager
- C. it_pps_admin.
- D. All roles.
正解: C
質問 22
What happens to the expense line after it is processed?
- A. The cost plan closes.
- B. The actual amount incurred becomes part of the cost plan.
- C. Nothing significant results.
- D. The actual cost is recorded at the portfolio level.
正解: B
質問 23
To use the Time Sheet dashboard, what plugin must be installed?
- A. Knowledge Management - Service Portal (com.snc.knowledge_serviceportal)
- B. Employee Service Center (com.sn_hr_service_portal)
- C. Common ITSM Service Portal Application Components (com.snc.app_common.service_portal)
- D. Performance Analytics - Content Pack - PPM Standard plugin (com.snc.pa.pmo_dashboards)
正解: D
質問 24
Which of these tools allow you pinpoint over-allocated resources by viewing their negative availability values? (Choose two.)
- A. Resource Plan Logs
- B. Resource Allocation Workbench
- C. Resource Reports
- D. Project Workbench
正解: B,C
質問 25
What is the demand workbench used for? (Choose two.)
- A. Approving demands.
- B. Comparing demands with portfolios.
- C. Comparing and prioritizing demands against other demands.
- D. Displaying submitted demands to stakeholders.
正解: C,D
質問 26
The PPM Standard plugin enables an it_project_manager to perform the following activities: (Choose three.)
- A. Define target for the portfolio
- B. Establish resource requirements and track costs.
- C. Determine overall project cost requirements
- D. Track actual amount spent compared to an approved budget.
- E. Configure cost type definition
正解: B,C,D
質問 27
What does the project status report allow project managers to do? (Choose two.)
- A. Print as a PDF attachment
- B. View the project Gantt chart
- C. View the WBS
- D. Show historical trend of project KPI's
正解: A,D
質問 28
Which 'Member Preference' automatically finds the most available resource(s) from the group and allocates to a plan using the allocation action?
- A. Specific member.
- B. All members.
- C. Any member and specific member.
- D. Any member.
正解: D
質問 29
At a minimum, which role is required to view the summary of a project in the Details tab of Project Workspace?
- A. it_project_user
- B. it_project_manager
- C. itil
- D. it_portfolio_manager
正解: A
質問 30
Which of the following are true regarding how the My Project Space (Project Workspace) handles dynamic content? (Choose two.)
- A. If the project state is Draft, actual start date and actual end date are displayed.
- B. If the project state is On Hold, actual start date and actual end date are displayed.
- C. If the project state is Work in Progress, actual start date and planned end date are displayed.
- D. If the project state is Pending or Open, planned start date and planned end date are displayed.
正解: C,D
質問 31
Which plugin provides a layer of artificial intelligence that empowers features and capabilities across applications to provide better work experiences?
- A. Scenario Planning for PPM [sn_pw_scenario]
- B. PPM Standard [com.snc.financial_planning_pmo]
- C. Strategic Spend Tracking for PPM [sn_ppm_sst]
- D. Predictive Intelligence for PPM [com.snc.ppm_ml]
正解: D
質問 32
When a time card is approved, the actual time is stored in which two tables? (Choose two.)
- A. Project Time table
- B. Resource Aggregate tables (Daily, Weekly, and Monthly)
- C. Resource Allocation Daily table
- D. Resource Event table
正解: B,C
質問 33
What needs to be configured if a customer wants to change the attributes copied when using copy project or copy partial project?
- A. com.snc.project.copy.additional_attributes.
- B. The copy project UI action
- C. com.snc.project.copy.
- D. The copy project client script.
正解: A