質問 # 29
The RIDAC workflow can be modified by using which feature?
- A. Flow Designer
- B. Project Form
- C. Service Catalog
- D. Idea Portal
正解:B
質問 # 30
In the base system, what is the default number of cards that can be displayed in the project workspace?
- A. 0
- B. 1
- C. 2
- D. 3
正解:D
質問 # 31
When can a user choose from multiple rate types for their work, while logging a time card?
- A. Only if this capability is enabled in the Project Record
- B. Only if the capability is enabled in the Project Preferences
- C. Only if the capability is enabled in the Time Sheet Policies
- D. Only one (1) rate type can apply
正解:C
質問 # 32
A project expense line is a cost associated with a specific source. Examples of specific sources could include:
(Choose three.)
- A. User.
- B. Demand.
- C. Configuration Item (CI).
- D. Fixed Asset.
- E. Project.
正解:A、C、D
質問 # 33
A customer requires five (5) teamspaces to support different departments. What should you do?
- A. Use UI Policies and Business Rules to enable teamspaces.
- B. Enable the teamspace property.
- C. Activate via each teamspace plugin.
- D. Contact the Account Representative to activate the teamspaces.
正解:C
質問 # 34
What role can configure an idea module, map idea categories to the idea module, and add navigation for the Idea Portal?
- A. Project manager [it_project_manager]
- B. Idea admin [idea_admin]
- C. Idea manager [idea_manager]
- D. Demand manager [it_demand_manager]
正解:B
質問 # 35
Demand managers can enhance a demand request by adding the following: (Choose three.)
- A. Change Requests
- B. Decisions
- C. Stakeholders
- D. Problems
- E. Requirements
正解:B、C、E
質問 # 36
Which of the following states appear in the process flow indicator at the top of the Demand form by default?
(Choose three.)
- A. Approved
- B. Updated
- C. Deferred
- D. Draft
- E. Screening
正解:A、D、E
質問 # 37
What does the project status report allow project managers to do? (Choose two.)
- A. View the WBS
- B. View the project Gantt chart
- C. Show historical trend of project KPI's
- D. Print as a PDF attachment
正解:C、D
質問 # 38
An it_project_manager can request resources by which of the following: (Choose two.)
- A. Month.
- B. Person Days.
- C. Day.
- D. Hours.
正解:B、D
質問 # 39
When a time card is approved, the actual time is stored in which two tables? (Choose two.)
- A. Project Time table
- B. Resource Event table
- C. Resource Aggregate tables (Daily, Weekly, and Monthly)
- D. Resource Allocation Daily table
正解:C、D
質問 # 40
Which of the following are true regarding how the My Project Space (Project Workspace) handles dynamic content? (Choose two.)
- A. If the project state is Work in Progress, actual start date and planned end date are displayed.
- B. If the project state is On Hold, actual start date and actual end date are displayed.
- C. If the project state is Pending or Open, planned start date and planned end date are displayed.
- D. If the project state is Draft, actual start date and actual end date are displayed.
正解:A、C
質問 # 41
What happens to the expense line after it is processed?
- A. The cost plan closes.
- B. The actual cost is recorded at the portfolio level.
- C. The actual amount incurred becomes part of the cost plan.
- D. Nothing significant results.
正解:C
質問 # 42
What is the default schedule for a project?
- A. 9-hour workday (from 8 to 12 and from 1 to 5).
- B. 8-hour workday (from 9 to 12 and 1 to 6).
- C. 8-hour workday (from 9 to 5).
- D. 8-hour workday (from 8 to 12 and 1 to 5).
正解:D
質問 # 43
Which role can configure the parameters of the demand workbench that is provided with the base system?
- A. it_pps_admin.
- B. it_project_manager
- C. All roles.
- D. business_stakeholder.
正解:A
質問 # 44
Depending on the execution type selected for a particular project, one of these dashboards will also be available:
- A. PMO Dashboard
- B. Timecard Dashboard
- C. Project Summary - Waterfall Dashboard
- D. User Manager Dashboard
正解:C
質問 # 45
The Project Portfolio Management application supports domain separation at this level:
- A. Data only
- B. Level 2 - Tenant process management
- C. Level 1 - Tenant data management
- D. Level 3 - Tenant self-managed configuration
正解:A
質問 # 46
In which table can you find cost information for a specific fiscal period?
- A. expense_line
- B. cost_plan
- C. pm_project
- D. cost_plan_breakdown
正解:D
質問 # 47
Which of these tools allow you pinpoint over-allocated resources by viewing their negative availability values? (Choose two.)
- A. Resource Allocation Workbench
- B. Project Workbench
- C. Resource Reports
- D. Resource Plan Logs
正解:A、C
質問 # 48
How does a project manager request a change to a resource plan in the requested state?
- A. Request change on resource plan
- B. Email resource user.
- C. Email resource manager
- D. Use notes on resource plan.
正解:A
質問 # 49
What creates calendar entries on a users individual calendar? (Choose two.)
- A. Allocated resource plan.
- B. Approved resource plan.
- C. Confirmed resource plan.
- D. Planned resource plan.
正解:C、D
質問 # 50
Which capability allows users to view variances in a project's schedule?
- A. Project Status Report
- B. Move project
- C. Compare scheduled baselines
- D. Machine-learning algorithms
正解:C
質問 # 51
......
実際にあるCIS-PPM問題集PDFで100%合格率保証付きます:https://jp.fast2test.com/CIS-PPM-premium-file.html