質問 # 29
The RIDAC workflow can be modified by using which feature?

  • A. Flow Designer
  • B. Project Form
  • C. Service Catalog
  • D. Idea Portal

正解:B


質問 # 30
In the base system, what is the default number of cards that can be displayed in the project workspace?

  • A. 0
  • B. 1
  • C. 2
  • D. 3

正解:D


質問 # 31
When can a user choose from multiple rate types for their work, while logging a time card?

  • A. Only if this capability is enabled in the Project Record
  • B. Only if the capability is enabled in the Project Preferences
  • C. Only if the capability is enabled in the Time Sheet Policies
  • D. Only one (1) rate type can apply

正解:C


質問 # 32
A project expense line is a cost associated with a specific source. Examples of specific sources could include:
(Choose three.)

  • A. User.
  • B. Demand.
  • C. Configuration Item (CI).
  • D. Fixed Asset.
  • E. Project.

正解:A、C、D


質問 # 33
A customer requires five (5) teamspaces to support different departments. What should you do?

  • A. Use UI Policies and Business Rules to enable teamspaces.
  • B. Enable the teamspace property.
  • C. Activate via each teamspace plugin.
  • D. Contact the Account Representative to activate the teamspaces.

正解:C


質問 # 34
What role can configure an idea module, map idea categories to the idea module, and add navigation for the Idea Portal?

  • A. Project manager [it_project_manager]
  • B. Idea admin [idea_admin]
  • C. Idea manager [idea_manager]
  • D. Demand manager [it_demand_manager]

正解:B


質問 # 35
Demand managers can enhance a demand request by adding the following: (Choose three.)

  • A. Change Requests
  • B. Decisions
  • C. Stakeholders
  • D. Problems
  • E. Requirements

正解:B、C、E


質問 # 36
Which of the following states appear in the process flow indicator at the top of the Demand form by default?
(Choose three.)

  • A. Approved
  • B. Updated
  • C. Deferred
  • D. Draft
  • E. Screening

正解:A、D、E


質問 # 37
What does the project status report allow project managers to do? (Choose two.)

  • A. View the WBS
  • B. View the project Gantt chart
  • C. Show historical trend of project KPI's
  • D. Print as a PDF attachment

正解:C、D


質問 # 38
An it_project_manager can request resources by which of the following: (Choose two.)

  • A. Month.
  • B. Person Days.
  • C. Day.
  • D. Hours.

正解:B、D


質問 # 39
When a time card is approved, the actual time is stored in which two tables? (Choose two.)

  • A. Project Time table
  • B. Resource Event table
  • C. Resource Aggregate tables (Daily, Weekly, and Monthly)
  • D. Resource Allocation Daily table

正解:C、D


質問 # 40
Which of the following are true regarding how the My Project Space (Project Workspace) handles dynamic content? (Choose two.)

  • A. If the project state is Work in Progress, actual start date and planned end date are displayed.
  • B. If the project state is On Hold, actual start date and actual end date are displayed.
  • C. If the project state is Pending or Open, planned start date and planned end date are displayed.
  • D. If the project state is Draft, actual start date and actual end date are displayed.

正解:A、C


質問 # 41
What happens to the expense line after it is processed?

  • A. The cost plan closes.
  • B. The actual cost is recorded at the portfolio level.
  • C. The actual amount incurred becomes part of the cost plan.
  • D. Nothing significant results.

正解:C


質問 # 42
What is the default schedule for a project?

  • A. 9-hour workday (from 8 to 12 and from 1 to 5).
  • B. 8-hour workday (from 9 to 12 and 1 to 6).
  • C. 8-hour workday (from 9 to 5).
  • D. 8-hour workday (from 8 to 12 and 1 to 5).

正解:D


質問 # 43
Which role can configure the parameters of the demand workbench that is provided with the base system?

  • A. it_pps_admin.
  • B. it_project_manager
  • C. All roles.
  • D. business_stakeholder.

正解:A


質問 # 44
Depending on the execution type selected for a particular project, one of these dashboards will also be available:

  • A. PMO Dashboard
  • B. Timecard Dashboard
  • C. Project Summary - Waterfall Dashboard
  • D. User Manager Dashboard

正解:C


質問 # 45
The Project Portfolio Management application supports domain separation at this level:

  • A. Data only
  • B. Level 2 - Tenant process management
  • C. Level 1 - Tenant data management
  • D. Level 3 - Tenant self-managed configuration

正解:A


質問 # 46
In which table can you find cost information for a specific fiscal period?

  • A. expense_line
  • B. cost_plan
  • C. pm_project
  • D. cost_plan_breakdown

正解:D


質問 # 47
Which of these tools allow you pinpoint over-allocated resources by viewing their negative availability values? (Choose two.)

  • A. Resource Allocation Workbench
  • B. Project Workbench
  • C. Resource Reports
  • D. Resource Plan Logs

正解:A、C


質問 # 48
How does a project manager request a change to a resource plan in the requested state?

  • A. Request change on resource plan
  • B. Email resource user.
  • C. Email resource manager
  • D. Use notes on resource plan.

正解:A


質問 # 49
What creates calendar entries on a users individual calendar? (Choose two.)

  • A. Allocated resource plan.
  • B. Approved resource plan.
  • C. Confirmed resource plan.
  • D. Planned resource plan.

正解:C、D


質問 # 50
Which capability allows users to view variances in a project's schedule?

  • A. Project Status Report
  • B. Move project
  • C. Compare scheduled baselines
  • D. Machine-learning algorithms

正解:C


質問 # 51
......

実際にあるCIS-PPM問題集PDFで100%合格率保証付きます:https://jp.fast2test.com/CIS-PPM-premium-file.html


弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

我々の働いている時間: ( GMT 0:00-15:00 )
月曜日から土曜日まで

サポート: 現在連絡 

English Deutsch 繁体中文 한국어