質問 # 11
A Task List contains two operations:
. Every 3 MON: pump inspection
. Every 24 MON: pump replacement
When replacing the pump, the operation pump inspection will be ignored.
How can you achieve this?
- A. Create a cycle set sequence
- B. Set the lead float
- C. Create a task list hierarchy
- D. Assign different hierarchy levels
正解:D
解説:
Preventive Maintenance
質問 # 12
How can you assign a material BOM to a piece of equipment?
- A. Via creation of an equipment BOM
- B. Via field model number in the equipment master
- C. Via material BOM header in the serialization data
- D. Via field construction type
正解:D
解説:
A material BOM is a list of components that make up a material. It can be used to describe the structure and composition of a product or a spare part. A material BOM can be assigned to one or more technical objects, such as equipment or functional locations, to define the materials required for maintenance activities1.
One way to assign a material BOM to a piece of equipment is via the field construction type in the equipment master. The construction type is a material number that identifies the material BOM for the equipment. By entering the construction type in the equipment master, the system automatically assigns the material BOM to the equipment2.
The other options are incorrect because:
* Via field model number in the equipment master: The model number is a material number that identifies the material of the equipment itself, not the material BOM. It is used to create an equipment BOM, which is a list of components that are installed on the equipment. An equipment BOM can be different from a material BOM, as it can reflect the actual configuration of the equipment2.
* Via material BOM header in the serialization data: The serialization data is a view in the material master that contains information about the serial numbers of the material. It is not related to the material BOM or the equipment assignment3.
* Via creation of an equipment BOM: The creation of an equipment BOM is a different process from the assignment of a material BOM. An equipment BOM can be created from a material BOM, but it does not automatically assign the material BOM to the equipment. An equipment BOM can also be created manually or copied from another equipment2.
References: 1: Using Bills of Materials (BOMs) - SAP Learning 2: SAP PM Bills of Material Tutorial - Free SAP PM Training - ERProof 3: Serialization Data (SAP Library - Material Master (LO-MD-MM))
質問 # 13
Which operations can the responsible person perform after a maintenance order is technically completed?
Note: There are 2 correct answers to this question.
- A. Lock or unlock the order
- B. Change the planned costs
- C. Update the estimated costs
- D. Change the settlement rule
正解:A、D
解説:
Maintenance Processing - Basic Functions
質問 # 14
What is the goal of embedded analytics in SAP S/4HANA?
- A. To integrate BW Data Store Objects
- B. To allow both tactical and strategic analyses within the S/4HANA core
- C. To integrate BW Info Cubes
- D. To combine transactional and analytical processing
正解:D
解説:
The goal of embedded analytics in SAP S/4HANA is to combine transactional and analytical processing in the same system. Embedded analytics enables real-time operational reporting and decision support within the SAP S/4HANA applications, without the need for data replication or separate data warehouses. Embedded analytics uses the SAP HANA platform capabilities, such as in-memory computing, columnar storage, and calculationviews, to provide high-performance and flexible data access. Embedded analytics also leverages the SAP Fiori user interface and the SAP Analytics Cloud to deliver a rich and interactive user experience with predefined and custom analytical apps, dashboards, KPIs, and stories123.
The other options are incorrect because:
* Embedded analytics does not integrate BW Data Store Objects or BW Info Cubes. These are data structures that are used in SAP Business Warehouse, a separate analytical system that can be connected to SAP S/4HANA, but not embedded within it4.
* Embedded analytics does not allow both tactical and strategic analyses within the S/4HANA core.
Tactical and strategic analyses are typically performed on historical and aggregated data that may come from multiple sources, not just the S/4HANA core. For these types of analyses, SAP S/4HANA can be integrated with SAP Analytics Cloud or SAP BW/4HANA, which provide more advanced and comprehensive analytical capabilities.
質問 # 15
The planner adds non-stock material in a released maintenance order.
What are possible options within the maintenance order?
Note: There are 3 correct answers to this question.
- A. A purchase requisition can be created automatically as soon as the order is saved.
- B. A purchase requisition will ALWAYS be created as soon as the order is saved.
- C. A purchase order is created automatically as soon as the order is saved.
- D. The maintenance order can be set to TECO before the invoice is created.
- E. A goods receipt can be posted after the maintenance order is technically completed.
正解:A、B、D
解説:
Maintenance Processing - Basic Functions
質問 # 16
What are characteristics of the Preparation and Scheduling phase within phase-based maintenance?
Note: There are 2 correct answers to this question.
- A. The configuration of the order type decides whether you use Resource Scheduling or not.
- B. If you use the Resource Scheduling apps, you always dispatch orders and operations.
- C. The order moves to the Preparation phase once it is approved and released.
- D. Maintenance Planning Buckets give you a list of non-approved notifications.
正解:B、C
解説:
Maintenance Processing - Advanced Functions
質問 # 17
How does a performance-based maintenance plan calculate the interval between start date and planned date?
- A. Cycle length divided by (monthly performance x 12)
- B. Cycle length divided by ((scheduling period) x (cycle modification factor))
- C. Cycle length divided by (annual performance/365)
- D. Cycle length divided by annual performance
正解:C
質問 # 18
You want to create a single-cycle plan with a cycle of 12 months. You use the scheduling indicator Time - key date.
The orders should be called 3 months before the planned date.
How can you set up the maintenance plan?
Note: There are 2 correct answers to this question.
- A. Set the call horizon to 25%.
- B. Set the call horizon to 75%.
- C. Set the call horizon to 90 days.
- D. Set the offset to 3 months.
正解:A
解説:
Preventive Maintenance
質問 # 19
Which options do you have in SAP S/4HANA Asset Management, Public Cloud Edition? Note: There are 2 correct answers to this question.
- A. You can configure SAP S/4HANA Cloud via the SAP Central Business Configuration (CBC).
- B. You can configure SAP S/4HANA Cloud via the SAP Asset Intelligence Network.
- C. You have access to the SAP S/4HANA back-end system.
- D. You do NOT have access to the SAP S/4HANA back-end system.
正解:A、D
解説:
Organizational Units and Master Data
質問 # 20
Which of the following objects can you directly assign when you define the work center? Note: There are 2 correct answers to this question.
- A. Organizational unit (HR)
- B. Calculation key
- C. Planner group
- D. Capacity category
正解:A、D
質問 # 21
Which parameter in a maintenance strategy do you use to set the start/end date of the maintenance order?
- A. Call horizon
- B. Initial/subsequent buffer
- C. Package offset
- D. Scheduling type
正解:B
質問 # 22
You want to display vehicle-specific data for a piece of equipment. How do you proceed?
- A. Assign a view profile to an equipment category for fleet equipment.
- B. Assign a view profile to the combination of vehicle type and equipment category.
- C. Assign a view profile to the combination of equipment category and vehicle class.
- D. Set the relevant flags in Customizing activity "Define Additional Business Views for Equipment Categories".
正解:B
質問 # 23
The maintenance technician wants to document work steps for a technical object in a notification.
What are the best options to be used in regard to code-based reporting?
Note: There are 2 correct answers to this question.
- A. A task in the notification item
- B. A text in the subject long text screen
- C. An activity in the notification header
- D. An entry in the object list
正解:A、C
解説:
Maintenance Processing - Basic Functions
質問 # 24
How is Phase-based Maintenance Processing activated in the SAP system? Note: There are 2 correct answers to this question
- A. By manually activating the corresponding Business Feature in case Best Practices are not used.
- B. Phase-based maintenance is always active in all S/4HANA 2021 editions and above
- C. Through Best Practices scope items 4HH and 4HI.
- D. By installing the corresponding enhancement pack and activating the related business function
正解:A、C
解説:
Phase-based maintenance processing is a new concept that was introduced in SAP S/4HANA Cloud 2011 and SAP S/4HANA 2021. It allows you to track the life cycle of the maintenance processes using predefined phases and sub-phases, instead of system and user statuses. Phase-based maintenance processing is activated in the SAP system through the following ways:
* Through Best Practices scope items 4HH and 4HI. These are the new scope items for reactive and proactive maintenance that use the phase model for maintenance requests and orders. You can activate these scope items using the SAP Activate methodology and the SAP Best Practices Explorer12.
* By manually activating the corresponding Business Feature in case Best Practices are not used. If you do not use the Best Practices scope items, you can still activate the phase model for maintenance requests and orders by using the Business Feature switch in the Customizing activity Define Settings for Maintenance Processing34.
Phase-based maintenance processing is not always active in all S/4HANA 2021 editions and above, as it depends on the scope items or the Business Feature switch. Therefore, answer B is incorrect. Phase-based maintenance processing is not activated by installing the corresponding enhancement pack and activating the related business function, as this is the old way of activating new features in SAP ERP. Therefore, answer C is also incorrect. References: SAP S/4HANA Cloud release of 2011 - Asset Management (Maintenance
... and Highlights for Asset Management in SAP S/4HANA 2021 | SAP Blogs
質問 # 25
You require stock material to carry out maintenance tasks.
What do you have to consider regarding material planning in the maintenance order? Note: There are 2 correct answers to this question.
- A. For stock material you always need a reservation.
- B. The pick list for materials can be printed before order release.
- C. Material can be assigned at the order header level.
- D. A goods issue can be entered for planned and unplanned material.
正解:A、D
質問 # 26
Which of the following is a prerequisite for external refurbishment?
- A. Assign an external work center to a maintenance order operation.
- B. Select the material group for externally refurbished materials.
- C. Define the order type for external refurbishment.
- D. Activate the subcontracting indicator in an external activity.
正解:D
解説:
Maintenance Processing - Advanced Functions
質問 # 27
What do you have to consider when implementing UI technologies in SAP S/4HANA Asset Management?
Note: There are 2 correct answers to this question.
- A. SAP GUI for HTML can be used in the SAP Fiori launchpad.
- B. Web Dynpro apps can be used in the SAP Fiori launchpad.
- C. The cloud version can also use SAP GUI for Windows.
- D. SAP Fiori launchpad supports only SAPUI5 apps.
正解:A、B
解説:
User Interface and Mobile Maintenance
質問 # 28
How do you map a counter replacement in SAP S/4HANA Asset Management?
- A. Create a new measurement document marked as a counter replacement.
- B. Create a new measurement document and assign a valuation code for counter replacement.
- C. Deactivate the current counter and create a new counter.
- D. Assign a catalogue type for counter replacement to the measuring point category.
正解:A
質問 # 29
Which SAP UI technology is used for the Report and Repair Malfunction app?
- A. Web Dynpro
- B. Business Server Pages
- C. SAP GUI for HTML
- D. SAPUI5
正解:D
解説:
Maintenance Processing - Basic Functions
質問 # 30
You settle a refurbishment order with the batches (valuation types) having price control standard price. What is the effect? Note. There are 2 correct answers to this question.
- A. The goods receipt for the batch refurbished is posted with the value of the moving average price
- B. The goods receipt for the batch refurbished is posted with the value of the standard price.
- C. The effective costs are posted to the respective batch (valuation type).
- D. The effective costs are posted as a credit memo to a price difference account
正解:B、D
解説:
When you settle a refurbishment order with the batches (valuation types) having price control standard price, the following effects occur:
* The effective costs are posted as a credit memo to a price difference account. This means that the difference between the actual costs of the refurbishment and the standard price of the batch is recorded as a variance in the accounting document. This ensures that the inventory value of the batch is not affected by the refurbishment costs1
* The goods receipt for the batch refurbished is posted with the value of the standard price. This means that the inventory value of the batch is updated with the predefined price that is maintained in the material master. This ensures that the inventory value of the batch is consistent and stable1 The other options are incorrect because:
* The effective costs are not posted to the respective batch (valuation type). The batch valuation is based on the standard price, not the actual costs of the refurbishment1
* The goods receipt for the batch refurbished is not posted with the value of the moving average price. The moving average price is only used for batches with price control moving average price, not standard price1 References: 1: Settlement Receiver | SAP Help Portal
質問 # 31
......
SAP試験練習テスト最高得点を獲得しよう:https://jp.fast2test.com/C_S43_2023-premium-file.html