質問 # 59
WBS要素の使用ステータスプロファイルはどこで割り当てられますか? 注: この質問には3つの正解があります
- A. プロジェクトタイプで
- B. プロジェクトプロファイル内
- C. 運用WBS要素内
- D. プロジェクトバージョン
- E. 標準WBSのプロジェクト定義では
正解:A、B、C
解説:
User status profiles are used to define additional statuses for project objects that can control their business processes. You can assign user status profiles for WBS elements in the project profile, which is a template for creating projects with similar characteristics. You can also assign user status profiles for WBS elements in the project type, which is a classification of projects according to their objectives and characteristics. You can also assign user status profiles for WBS elements in the operative WBS element itself, which is a structural element of a project that represents a task or a partial task. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
質問 # 60
プロジェクト内のWBS要素に予算を割り当てました。割り当てられた値を現在の予算と比較するにはどの機能を使用できますか?
- A. 簡単なコスト計画
- B. 可用性制御
- C. 結果分析
- D. コスト予測
正解:B
解説:
Availability control is a function that can be used to check assigned values against the current budget for WBS elements within your project. Availability control is a process that monitors whether budget overruns occur in your project and issues warnings or error messages if predefined tolerance limits are exceeded. You can activate availability control for individual WBS elements or for entire projects and define different tolerance limits for different types of costs or revenues. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
質問 # 61
ネットワークとWBS要素を扱っています。次の記述のうちどれが当てはまりますか?
- A. ネットワークヘッダーを複数のWBS要素に割り当てることができます
- B. アクティビティのある WBS 要素に対して、運用区分勘定割当要素を有効化する必要があります。
- C. プロジェクトプロファイルでネットワークプロファイルを管理する必要があります
- D. アクティビティをあるネットワークから別のネットワークに再割り当てできます
正解:C
解説:
One of the statements that applies to working with networks and WBS elements is that you have to maintain a network profile in the project profile. A network profile is a parameter that defines the basic properties of a network, such as its order type, number range, and scheduling parameters. A project profile is a parameter that defines the basic properties of a project, such as its project type, number range, and budget profile. You have to assign a network profile to a project profile in order to create networks within a project. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
質問 # 62
ネットワーク アクティビティに割り当てられた品目コンポーネントの予約を作成します。
ただし、アクティビティをリリースして保存した後、予約が作成されません。予約が見つからない理由として考えられるものは何ですか?
注: この質問には2つの正解があります
- A. 材料コンポーネントの可用性チェックで、不足している部品が示される
- B. 品目マスタが外部調達に設定されている
- C. 材料は非在庫材料としてアクティビティに割り当てられます
- D. アクティビティに割り当てられた品目コンポーネントの予約/購買依頼インジケータが「なし」に設定されています。
正解:C、D
解説:
Some possible reasons for the missing reservation for a material component assigned to a network activity are: The indicator Reservation/Purchase Requisition indicator for the material component assigned to the activity is set to "never", which means that no reservation or purchase requisition is created for the material component. The material is assigned to the activity as a non-stock material, which means that it does not have a stock record in inventory management and no reservation is created for it. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
質問 # 63
プロジェクト構造
組立処理を使用しています。プロジェクトへの勘定割当を使用して、受注明細の納入日を決定する必要があります。
前提条件は何ですか?
注: この質問には3つの正解があります
- A. 販売ビュー付き部品表
- B. アクティビティを含む標準ネットワーク
- C. 生産オーダー
- D. 販売ビューを備えた品目マスタ
- E. 材料と標準ネットワーク間の割り当て
正解:B、D、E
解説:
According to SAP Press2, "To use assembly processing, you need a material master with sales views, a bill of material (BOM) for the material, a standard network with activities, and an assignment between the material and the standard network." Reference: 2
質問 # 64
ユーザーのステータスに基づいて構造概要を検索するにはどうすればよいでしょうか? 注: この質問には 2 つの正解があります
- A. 個々のステータスを検索することで
- B. ステータスの組み合わせコードで検索する
- C. ステータスプロファイルを検索することで
- D. ステータス選択プロファイルで検索
正解:A、D
解説:
To search in the structure overview based on the user status, you can use either the status selection profile or the individual status as search criteria. The structure overview is a function that allows you to display and analyze various structural elements of a project, such as WBS elements, networks, activities, milestones, and so on. The structure overview also provides various search functions that allow you to find specific project objects based on different criteria, such as number, description, system status, user status, and so on. To search in the structure overview based on the user status, you can use either:
The status selection profile: This is a parameter that allows you to define a set of user statuses that can be used as a filter for searching project objects. You can create and maintain status selection profiles in Customizing for Project System under Structures Status Management Define Status Selection Profiles . You can also assign a default status selection profile to a project profile or a network profile.
The individual status: This is a parameter that allows you to enter a single user status as a search criterion for finding project objects. You can enter an individual status directly in the search dialog box of the structure overview.
質問 # 65
プロジェクトシミュレーションを使用する利点は何ですか? 注: この質問には3つの正解があります
- A. プロジェクトシミュレーションでは購買依頼書を作成できます
- B. プロジェクトシミュレーションでは実際のデータを投稿できます
- C. プロジェクトシミュレーションは構造とコストの計画に使用できます
- D. 運用プロジェクトをテンプレートとして使用せずにプロジェクトシミュレーションを作成できます
- E. 複数のプロジェクトシミュレーションを同時に使用できます
正解:C、D、E
解説:
Project simulations are some of the advantages of using project simulations in SAP Project System. Project simulations are copies of projects that allow you to plan and simulate different scenarios without affecting operational projects. Project simulations can be created without using an operational project as a template, which means you can start from scratch or use a standard structure. Project simulations can be used to plan structures and costs, which means you can create and change WBS elements, networks, activities, and cost elements. Multiple project simulations can be used simultaneously, which means you can compare different alternatives and choose the best one. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
質問 # 66
顧客は内部アクティビティを含むネットワークを作成し、容量要件を生成しました。現在、プロジェクトの容量要件を分析したいと考えています。どのレポートをお勧めしますか?
- A. 個別概要容量要件
- B. 拡張容量評価
- C. キャパシティ負荷作業センタービュー
- D. 構造の概要
正解:B
解説:
To analyze the capacity requirements of their project, you can recommend using the extended capacity evaluation report. The extended capacity evaluation report displays capacity requirements and availability for work centers or resources over a period of time. You can use various selection criteria and display options to customize the report according to your needs. You can also access detailed information on individual capacity requirements or availability situations by choosing drilldown functions. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
質問 # 67
外部コンポーネントがネットワーク アクティビティに割り当てられます。購買依頼の配送日は、ネットワーク アクティビティの日付によって決まります。配送日が最も早い予定日と最も遅い予定日のどちらで定義されるかは、何によって決まりますか。
- A. ネットワークプロファイル
- B. ネットワークのスケジューリングパラメータ
- C. MRPコントローラのテーブル
- D. コントロールキー
正解:B
解説:
To control whether the delivery date for an external component assigned to a network activity is defined by the earliest or latest scheduled dates, you can use the scheduling parameters for the network. An external component is a material component that is required for executing a network activity and that is procured externally from vendors or other plants
質問 # 68
材料
システムはどのようにして要件 (予約や購入依頼など) を有効化できますか?
注: この質問には2つの正解があります
- A. ネットワークまたはアクティビティをリリースする場合
- B. 要求日と補充リードタイムを使用して自動的に
- C. プロジェクトを保存してすぐに
- D. 標準マイルストーンアクティビティを使用する
正解:A、C
解説:
The system can activate requirements (such as reservations or purchase requisitions) in different ways, depending on the settings in customizing and master data. Some of these ways are:
Immediately, by saving the project: This means that the system creates requirements for all materials assigned to WBS elements or activities as soon as you save the project. This option requires that you set the indicator "Requirements immediately" in customizing for your project profile.
When releasing a network or an activity: This means that the system creates requirements for all materials assigned to a network or an activity when you release them. This option requires that you set the indicator "Requirements on release" in customizing for your network type or activity type. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/79ceb65334e6b54ce10000000a174cb4.html?&version=1909.002
質問 # 69
材料
お客様は、ネットワーク コンポーネントの進捗状況追跡を使用して、イベントの日付を手動で管理しています。イベントのスケジュールを実装する必要があります。
イベントのスケジュールを実装するための要件は何ですか?
- A. 資材スケジュールのスケジュールパラメータを設定する必要があります。
- B. イベントは手動でリリースする必要があります。
- C. イベントの優先度を設定する必要があります。
- D. イベント シナリオを定義する必要があります。
正解:D
解説:
To implement scheduling of events, event scenarios must be defined. Event scenarios are predefined sets of events that describe typical sequences of activities in a project. Events are points in time that mark the start or finish of an activity or a milestone. Event scenarios can be used to schedule events automatically based on their dependencies and priorities. Event scenarios can also be used to track and monitor the progress of events in a project. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/0673b65334e6b54ce10000000a174cb4.html
質問 # 70
単一のアクティビティについて、異なる作業センターの作業時間をどのように確認できますか?
- A. 複数の作業センターを割り当てる直接アクティビティ割り当てを入力します。
- B. アクティビティに対して複数の確認を作成し、各確認に適切なワークセンターを使用します。
- C. 1回の確認で複数の作業センターを入力する
- D. アクティビティに複数の作業センターを割り当てる
正解:B
解説:
To confirm the working hours of different work centers for a single activity, you can create multiple confirmations for the activity and use the appropriate work center for each confirmation. A confirmation is a function that allows you to record actual data for activities and activity elements, such as actual dates, actual durations, actual work, and so on. A work center is a parameter that defines where an activity is performed or who performs it. A work center can have various attributes, such as capacity, cost center, formulas, and so on. To confirm the working hours of different work centers for a single activity, you can create multiple confirmations for the activity and use the appropriate work center for each confirmation. This allows you to capture the actual work done by each work center separately and update their capacity requirements and costs accordingly. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/f373bb53707db44ce10000000a174cb4.html
質問 # 71
顧客プロジェクトに請求を使用したいと考えています。どのカスタマイズ オブジェクトが受注明細の請求を制御しますか?
- A. 要件クラス
- B. スケジュール行カテゴリ
- C. アイテムカテゴリ
- D. 要件タイプ
正解:C
解説:
The item category is the customizing object that controls the billing of sales order items for a customer project. The item category is a parameter that defines the basic characteristics and functions of a sales order item, such as whether it is relevant for billing or not, whether it requires a delivery or not, and whether it can be invoiced individually or collectively. The item category also determines which billing plan type can be used for a sales order item. The billing plan type is a parameter that defines how billing dates are determined and how billing amounts are calculated for a sales order item. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
質問 # 72
フロート時間はスケジュール時に計算されます。
浮遊時間に関する次の記述のうち正しいものはどれですか?
注: この質問には3つの正解があります
- A. 時間制約が「開始しなければならない」アクティビティには、常に負の浮動時間があります。
- B. フリーフロートの最大サイズは、アクティビティの合計フロートと同じ大きさです。
- C. 浮動時間は負の値になることがあります
- D. WBS要素の浮動時間は外挿によって計算されます
- E. デフォルトでは、クリティカルアクティビティにはフロート時間があり、これはゼロ以下です。
正解:B、C、D
解説:
Float time is the amount of time that an activity or a WBS element can be delayed without affecting the end date of the project. Float time can be negative if an activity or a WBS element is already behind schedule. The float time of WBS elements is calculated by extrapolating the float times of their subordinate activities. The free float is the amount of time that an activity can be delayed without affecting the start date of its successor activities. The total float is the amount of time that an activity can be delayed without affecting the end date of the project. Therefore, the maximum size of a free float is as large as the total float of an activity. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
質問 # 73
プロジェクト指向調達 (ProMan) ではどのようなビジネストランザクションを使用できますか? 注: この質問には 3 つの正解があります
- A. 購買依頼書を生成する
- B. 配信を生成する
- C. 生産オーダーの確認
- D. 在庫振替転記
- E. 商品の出庫をキャンセルする
正解:A、D、E
解説:
Project-Oriented Procurement (ProMan) supports various business transactions that are related to project procurement. Some of these transactions are:
Stock transfer posting: You can use this transaction to transfer project stock from one storage location to another within the same plant or between different plants.
Generate purchase requisition: You can use this transaction to create a purchase requisition for a material or service that is required for a project.
Cancel goods issue: You can use this transaction to reverse a goods issue posting for a material that was issued from project stock. Reference: https://help.sap.com/saphelp_erp60_sp/helpdata/EN/8e/8bc95360267214e10000000a174cb4/frameset.htm
質問 # 74
コストと予算
プロジェクトのWBS要素に予算を割り当てました
割り当てられた値を現在の予算と比較するには、どのような予算関数を使用できますか?
- A. 簡単なコスト計画
- B. 可用性制御
- C. 結果分析
- D. コスト予測
正解:B
解説:
Availability control is a budget function that can be used to check assigned values against the current budget. Availability control monitors whether the budget for a project is sufficient for planned and actual costs. Availability control compares the assigned values (such as commitments, actual costs, or funds reservations) with the current budget and issues warnings or errors if the tolerance limits are exceeded. Availability control helps you to prevent budget overruns and ensure compliance with budget policies. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/79ceb65334e6b54ce10000000a174cb4.html?&version=1909.002
質問 # 75
新しい作業分解構造 (WBS 要素) の作成に関する次の記述のうち正しいものはどれですか。
注: この質問には 3 つの正解があります。
- A. レベルごとに複数の WBS 要素を作成できます。
- B. WBS構造には複数のレベル1のWBS要素を含めることができます。
- C. 新しいプロジェクトの WBS 要素を別のプロジェクト定義に割り当てることができます。
- D. 新しい作業分解構造には最大 10 レベルを含める必要があります。
- E. WBS 要素は、計画要素、アカウント割り当て要素、および請求要素として同時に使用できます。
正解:A、C、E
解説:
You can create several WBS elements per level." According to SAP Help Portal2, "You can assign a WBS element of the new project to a different project definition." According to SAP Help Portal3, "WBS elements can be planning elements, account assignment elements, and billing elements at the same time." Reference: 123
質問 # 76
......