質問 # 19
at is the difference between a nonconformity and an observation?

  • A. They are different names for the same thing
  • B. They identify different levels of defect, and if either of them are identified during an audit then certification ^ CANNOT be granted
  • C. A nonconformity identifies that a requirement is NOT being correctly met, whereas an observation identifies a recommendation for improvement
  • D. A nonconformity can be identified by both internal and external auditors, but an observation can only be identified by an internal auditor

正解:C


質問 # 20
What is an example of a requirement for the service management objectives?

  • A. They should be easy to realize
  • B. They should be left unchanged, even if services change
  • C. They should be consistent with the service management policy
  • D. They should be shared with the customers

正解:C


質問 # 21
Which statement about the use of technology and tools to achieve and maintain certification is correct?

  • A. The data reported from the tools can be used to provide evidence for audits
  • B. Any tools used shall be listed on the ISO catalogue of approved tools
  • C. The technology and tools used shall be assessed during the audits
  • D. The use of technology is mandatory

正解:A


質問 # 22
What is an audit observation?

  • A. A recommendation that has to be actioned
  • B. A finding against an area which is NOT in the scope of the standard
  • C. A conformity to the standard where there is an opportunity for improvement
  • D. A non-fulfilment of a requirement

正解:C


質問 # 23
What is the intent of the service availability management process?

  • A. To ensure that agreed service availability commitments to providers can be met in all circumstances
  • B. To ensure agreed effective communication towards customers
  • C. To ensure that agreed service availability commitments to customers can be met within agreed targets
  • D. To ensure that agreed levels of service commitments to customers can be met in all circumstances

正解:C


質問 # 24
Which is a reason for the requirement to budget service costs?

  • A. To enable effective financial control for services
  • B. To reduce overall service costs
  • C. To improve the service management processes
  • D. To provide the basis for service provider organization charges

正解:A


質問 # 25
Which event is NOT part of the definition of an incident?

  • A. A reduction in the quality of a service
  • B. An unplanned interruption to a service
  • C. An event that has NOT yet impacted the service to the customer
  • D. A request for access to a service

正解:D


質問 # 26
To which other process is service design and transition most related?

  • A. Change management
  • B. Asset management
  • C. Incident management
  • D. Continual improvement

正解:A


質問 # 27
How should a problem requiring a change to a configuration item be resolved?

  • A. Use a service request
  • B. Update the configuration management database
  • C. Raise a request for change
  • D. Escalate the problem to service level management

正解:C


質問 # 28
ISO/IEC 20000-1 can be applicable to a service provider:

  • A. Only if its suppliers haven't demonstrated conformity to ISO/IEC 20000 requirements
  • B. Only if its customers have demonstrated conformity to ISO/IEC 20000 requirements
  • C. Only if its suppliers have demonstrated conformity to ISO/IEC 20000 requirements
  • D. Even if its customers or suppliers have demonstrated conformity to ISO/IEC 20000 requirements

正解:D


質問 # 29
How many years is an ISO/IEC 20000-1 certificate valid for the Certification scheme?

  • A. One
  • B. Three
  • C. Five
  • D. Two

正解:B


質問 # 30
Which is NOT a specific resource management responsibility within ISO/IEC 20000-1?

  • A. All service management personnel shall be aware of their contribution to service management objectives
  • B. All service management staf shall be qualified to at least ITIL Foundation level
  • C. Appropriate service management staff training records shall be maintained
  • D. The competencies required for service management roles shall be determined

正解:B


質問 # 31
Where an external supplier is using a sub-contracted supplier, who is responsible for ensuring that the sub-contracted supplier meets their contractual obligations?

  • A. The service provider's contract manager
  • B. The service provider's business relationship manager
  • C. The external supplier
  • D. The sub-contracted supplier

正解:C


質問 # 32
Identify the missing words in the following sentence. The definition of the scope of the SMS shall include the services in scope and the [???] managing and delivering the services.

  • A. service management processes used for
  • B. name of the organization
  • C. number of resources required for
  • D. names of suppliers involved in

正解:B


質問 # 33
What is a responsibility of the organization regarding supplier management as defined in ISO/IEC 20000-1?

  • A. To ensure that contracts with external suppliers are accessed for alignment against SLAs of customers
  • B. To ensure that a process exists for the procurement of suppliers
  • C. To ensure that subcontracted suppliers meet contractual requirements in all circumstances
  • D. To ensure that supplier processes and procedures are defined

正解:A


質問 # 34
Who is required to review the service providers SMS and services within the service management system of ISO/IEC 20000-1?

  • A. Any process owner
  • B. The Registered Certification Body
  • C. A consultancy organization
  • D. Top management

正解:D


質問 # 35
Which document defines the scope of services to be delivered by an external supplier who implements and operates some parts of the service management processes?

  • A. A contract agreed with the customers
  • B. A list of service level targets agreed with the customers
  • C. A list of service level targets agreed with the service provider organization
  • D. A contract agreed with the service provider organization

正解:D


質問 # 36
"How do the information security requirements of ISO/IEC 20000-1 and ISO/IEC 27001 relate to each other?"

  • A. The requirements of ISO/IEC 20000-1 are the same as the requirements of ISO/IEC 27001
  • B. The requirements of ISO/IEC 20000-1 are more elaborate than the requirements of ISO/IEC 27001
  • C. They don't relate
  • D. The requirements of ISO/IEC 20000-1 are lighter than the requirements of ISO/IEC 27001

正解:D


質問 # 37
Which is a requirement of incident management for a Major Incident?

  • A. The customer shall be responsible for the definition of a Major Incident
  • B. Opportunities for improvement shall be identified before the incident is resolved
  • C. The root cause of a major incident shall be recorded at the time the incident record is created
  • D. Responsibility shall be assigned for managing a major incident

正解:D


質問 # 38
A transport company with 1500 laptops, received many requests for expansion of the internal memory because its size has proven to be insufficient. Which process should have prevented this from happening?

  • A. Service level management
  • B. Capacity management
  • C. Service availability management
  • D. Configuration management

正解:B


質問 # 39
What is not an input to manage continual improvement?

  • A. Governance of processes operated by other parties
  • B. Relevant directives from top management
  • C. Optimized resource utilization or risk reduction
  • D. Problem records

正解:A


質問 # 40
......


PECB ISO-IEC-20000-Foundation 認定試験の出題範囲:

トピック出題範囲
トピック 1
  • SMS の ISO
  • IEC 20000-1 要件: このドメインでは、SMS を確立、実装、維持、および継続的に改善するための ISO
  • IEC 20000-1 の特定の要件について詳しく説明します。役割と責任の定義、リスク管理、プロセス統合、パフォーマンス測定などが含まれます。
トピック 2
  • このドメインでは、サービス管理の背後にある基本的な考え方と原則、および ISO
  • IEC 20000-1 で説明されているサービス管理システム (SMS) の目的について説明します。ビジネス ニーズと顧客の期待の両方を満たすようにサービスを構築し、品質と継続的な改善を確保することの重要性について説明します。
トピック 3
  • ISO
  • IEC 20000-1 に基づくサービス管理と SMS の基本概念と原則:

 

試験合格保証付きのISO 20000 ISO-IEC-20000-Foundation試験問題集:https://jp.fast2test.com/ISO-IEC-20000-Foundation-premium-file.html


弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

我々の働いている時間: ( GMT 0:00-15:00 )
月曜日から土曜日まで

サポート: 現在連絡 

English Deutsch 繁体中文 한국어