
[2023年更新]C_TS422_2021はSAP Certified Application Associateリアルな無料試験練習テスト
無料SAP Certified Application Associate C_TS422_2021試験問題を提供します
質問 # 21
Your production planners must execute planning only for specific resources. How can you achive this in advanced Planning(PP/DS)
- A. Use a resource group.
- B. Use a planning group.
- C. Use a propagation range.
- D. Use heuristic.
正解:D
質問 # 22
What are the consequences when you assgn a planned order to a production line manually, using the planning table in repetitive manufacturing?
- A. The planed order's component availability is checked.
- B. The planned order's components are copied to the picking list.
- C. The planed order is converted to production order.
- D. The planed order generates capacity requirements
正解:D
質問 # 23
Which of the following questions do you have to answer before you start creating a BOM?
- A. Which Valid To information is necessary?
- B. Is the material type allowed in the BOM?
- C. In which storage location is the BOM required?
- D. What status does the BOM have?
正解:A、B
質問 # 24
What is the purpose of a reporting point confirmation in repetitive manufacturing?
- A. To determine the work in progress along the production line
- B. To reduce the total production lead time for along production line
- C. To provide timely updates of inventory management for the staged components
- D. To stage different components for a production line simultaneously
正解:A、C
質問 # 25
You need to model goods receipt processing time in detailed scheduling. Whic modeling options do you have?
- A. Model a seperate resource in the production data structure.
- B. Model a transportation resorce in the location master.
- C. Model a resource inbound in the location master.
- D. Model a handling resource in the location master and goods receipt time in the material master.
正解:B、D
質問 # 26
Which SAP application can be used for forcasting in Supply Chain Planning?
- A. Integrated Business Planning (IBP)
- B. Material Requirements Planning (MRP)
- C. Supply Chain Management(SCM)
- D. Capacity Requirements Planning (CRP)
正解:A、C
質問 # 27
You want to use capacity availability checks for production orders. Which settings have to be made for this?
- A. An overall profile must be assigned in the checking control.
- B. The PRT Availability Check must be set in the checking control.
- C. The Relevant for Finite Scheduling indicator must be set
- D. A checking rule must be assigned in the checking control
正解:A、C
質問 # 28
What does forecasting in demand planning cycle include?
- A. Market intelligence
- B. Past sales order quantites
- C. One-off events
- D. Past procurment quantities
- E. Past quotation quantities
正解:A、B、C
質問 # 29
You want to reduce planning efforts for B/C materials. Which planning procedure do you recommend?
- A. Consumption-based planning
- B. Forecast planning
- C. Material requirements planning
- D. Manual planning without check
正解:A
質問 # 30
What type of time element can be reduced by strategy settings while dispatching?
- A. Transportation time
- B. Queue time
- C. Wait time
- D. Setup time
正解:B、C
質問 # 31
Advanced Planning uses master data and transaction data from SAP S/4HANA. In which data objects can you set the advanced planning flag?
- A. Plant
- B. Work center
- C. Material
- D. Production version
正解:B、C
質問 # 32
You want to schedule an operation finitely, without moving other operations. Which scheduing strategy do you select?
- A. Find slot
- B. Schedule in working time only
- C. Insert operation
- D. Squeeze in
正解:A
質問 # 33
How can you limit the validity of a bill of material (BOM)?
- A. By material type
- B. By period
- C. By plant
- D. By industry
正解:B、C
質問 # 34
For what production type are production orders used?
- A. Process manufacturing processes
- B. Replenishment controlled by control cycles
- C. Period and quantity-oriented production
- D. Discrete manufacturing processes
正解:D
質問 # 35
In the Capacity Scheduling Table, which settings can you select for the planning strategy? Note: There are 3 correct answers to this question.
- A. Planning mode
- B. Fixed pegging
- C. Scheduling control
- D. Direction
- E. Finiteness level
正解:A、C、D
質問 # 36
What are some uses for the low-level code assigned to each material?
- A. It is used in MRP to determine the sequence in which materials are planned.
- B. It is used by product costing to determine how coast are rolled up.
- C. It is used by engineering to indentify subitems in an engineering bill of material (BOM).
- D. it is used by ATP to determine the priority of alternative components.
正解:A、B
質問 # 37
Which times elements does MRP consider in backward scheduling to determine he order dates for components from dependent requirements?
- A. Planed delivery time
- B. Total replenishment lead time
- C. Operation duration
- D. In-house production time
正解:A、D
質問 # 38
When working with bouth cross-plant and plant-specific material statuses n the material master, which statuses has the higest priority?
- A. The most restrictive status
- B. The cross-plant status
- C. The last restrictive status
- D. The plant-specific status
正解:A
質問 # 39
Your client is asking for your advice on material master numbering in SAP S/4HANA. What do you need to consider?
- A. The display template for material numbers applies to all clients.
- B. The maximum mater all number length is 40 for external numbers and 18 for internal numbers
- C. The number of leading zeros for internal numbers is client-specific.
- D. In Customizing you can decide by material type whether to use the long material number.
正解:A、B
質問 # 40
You have a schedule agreement whit a vendor. You want classic MRP to automatically create schedule lines in case of material shortage.
What must you do?
- A. Add the agreement to the quota arrangement and mark it for MRP revalance.
- B. Add the agreement to the source list and mark it for MRP revalance.
- C. Set the creation indicator for delivery schedule lines on the initial screen of the MRP run.
- D. Set the creation indicator for purchase requisitions on initial screen of MRP run
正解:B、C
質問 # 41
......
SAP C_TS422_2021リアルな問題と知能問題集:https://jp.fast2test.com/C_TS422_2021-premium-file.html
C_TS422_2021問題集でSAP Certified Application Associate高確率練習問題集:https://drive.google.com/open?id=1wxHpS_-OrHiVAPT-6ju1RJXvQSGn83De