完全版C-TS412-1909練習テスト82特別な問題と解答が待ってます! [Q13-Q37]

Share

完全版C-TS412-1909練習テスト82特別な問題と解答が待ってます!

SAP Certified Application Associate問題集でC-TS412-1909試験完全版問題で試験学習ガイド

質問 13
What are some of the advantages of using project simulations? Note: There are 3 correct Answers to this question.

  • A. Project simulations allow posting of actual data.
  • B. Project simulations can be used to plan structures and costs.
  • C. Multiple project simulations can be used simultaneously.
  • D. Project simulations can be created without using an operational project as a template.
  • E. Project simulations can create purchase requisitions.

正解: B,C,D

 

質問 14
When you create a service activity in your network, what data can be entered? Note: There are 3 correct Answers to this question.

  • A. Vendor
  • B. Service specification
  • C. Service purchase order number
  • D. Material master within service specification
  • E. Overall limit (maximum value of all unplanned services)

正解: A,B,E

 

質問 15
Which of the following factors influence the scheduling of internal processing activities? Note: There are
3 correct Answers to this question.

  • A. Whether the work for the internal activity is greater than its duration
  • B. An activated Scheduling indicator in the control key of the internal processing activity
  • C. The factory calendar in the work center used for the internal processing activity
  • D. The relationships between activity elements
  • E. The unit (for example, hour, day) of the field Normal Duration field of the activity

正解: B,C,D

 

質問 16
You want to assign milestones to WBS elements. For what can you use these milestones? Note: There are 2 correct Answers to this question.

  • A. To start workflow tasks
  • B. To set an actual finish date for WBS elements
  • C. For trend analysis
  • D. To transfer the actual date to the billing plan

正解: C,D

 

質問 17
Your customer wants to use requirements grouping in SAP Project System. What are the prerequisites for requirements grouping of materials? Note: There are 2 correct Answers to this question.

  • A. The exact lot size procedure must be used.
  • B. An MRP group must be assigned.
  • C. The procurement type of the material must be internal.
  • D. The materials must allow sales order or project stock.

正解: B,D

 

質問 18
What are some of the possible functions in user status profiles? Note: There are 2 correct Answers to this question.

  • A. Utilize priorities for setting the user status.
  • B. Ensure user status must always be set manually.
  • C. Restrict setting user status for individual users.
  • D. Allow business processes forbidden by SAP system status.

正解: A,C

 

質問 19
For which objects can billing plans be created? Note: There are 2 correct Answers to this question.

  • A. Milestones
  • B. Project definition
  • C. Sales order items
  • D. WBS elements

正解: C,D

 

質問 20
How can you update the degree of processing for an activity?

  • A. By changing the activity
  • B. By scheduling the activity
  • C. By using results analysis
  • D. By confirming the activity

正解: D

 

質問 21
What functionality can you perform with activity elements?

  • A. Schedule WBS elements
  • B. Create relationships
  • C. Assign material
  • D. Assign work centers and capacities

正解: B

 

質問 22
Which organizational structures are required for network activities? Note: There are 3 correct Answers to this question.

  • A. Company code
  • B. Controlling area
  • C. Sales organization
  • D. Plant
  • E. Operating concern

正解: A,B,D

 

質問 23
You want to establish costing for WBS. Costing should be easy to use and should not refer to cost elements. What method for costing do you use?

  • A. Planning of overall values
  • B. Detailed planning for WBS
  • C. Unit costing for WBS
  • D. Easy Cost Planning (ECP) for WBS

正解: A

 

質問 24
How can you grant individual authorization for WBS elements and networks?

  • A. Set the system status to "Lock Master Data".
  • B. Activate access control lists (ACL) for the project profile and the network profile.
  • C. Activate access control lists (ACL) for the user master record.
  • D. Define a user status to lock the business transaction Update Project.

正解: B

 

質問 25
A service company uses project management and they complain that the system does not prevent their project managers from exceeding their budgets. What actions do you have to take to solve the problem?

  • A. Activate availability control for the WBS elements. Define the tolerance limits on each WBS element.
  • B. Activate availability control for projects in the controlling area. Enter the plan data for each WBS element.
  • C. Activate commitment management in the project definition. Enter the budget in the master data of the top WBS element.
  • D. Activate availability control in the assigned budget profile. Define the tolerance limits in customizing.

正解: D

 

質問 26
Which statements describe planned and actual revenue for WBS elements? Note: There are 2 correct Answers to this question.

  • A. Actual revenue is posted via a billing document created from a sales order
  • B. Actual revenue is posted via a billing plan assigned to a WBS element.
  • C. Planned revenue can be transferred from a sales quotation.
  • D. Planned revenue requires a sales order assigned to a WBS element.

正解: A,C

 

質問 27
You have assigned a material to a network activity and want to determine the requirement date related to this activity. What set of dates do you have to maintain?

  • A. Basic dates of the network activity
  • B. Forecast dates of the WBS
  • C. Actual dates of the network activity
  • D. Basic dates of the WBS

正解: A

 

質問 28
What is the reason for assigning billing plans in customer projects?

  • A. Billing plans are copied automatically to the sales order item.
  • B. Billing plans are prerequisites for quotation creation.
  • C. Billing plans enable the billing process to be carried out.
  • D. Billing plans are used for revenue planning.

正解: C

 

質問 29
A customer needs to analyse the capacity requirements of their network activities. Which reports do you recommend? Note: There are 2 correct Answers to this question.

  • A. Structure information system reports
  • B. Resource reports
  • C. Cost element reports
  • D. Hierarchical reports

正解: A

 

質問 30
You are using networks and external activities in your project. The purchase requisition has been created. What is the sequence for the following business transactions and documents?

  • A. Credit limit check -> Acceptance of performed services -> Vendor selection -> Purchase order handling
    -> Purchase order monitoring -> Goods receipt -> Invoice receipt
  • B. Vendor selection -> Purchase order creation -> Service entry sheet creation -> Service entry sheet approval
  • C. Vendor selection -> Purchase order handling -> Purchase order monitoring -> Goods receipt
  • D. Vendor selection -> Purchase order handling -> Invoice receipt -> Purchase order monitoring -> Goods receipt

正解: B

 

質問 31
You are working with networks and WBS elements. Which of the following statements applies?

  • A. You can reassign an activity from one network to another.
  • B. You have to maintain a network profile in the project profile.
  • C. You can assign the network header to multiple WBS elements.
  • D. You have to activate the operative indicator Account Assignment Element for WBS elements with activities.

正解: A,C

 

質問 32
Which of the following data can be maintained in a standard network? Note: There are 3 correct Answers to this question.

  • A. Document information records
  • B. Relationships
  • C. Internally processed activities
  • D. Material components
  • E. Basic dates for activities

正解: B,C,D

 

質問 33
How are earliest dates and latest dates of activities scheduled?

  • A. Earliest dates and latest dates are scheduled by forward scheduling.
  • B. Earliest dates are scheduled by backward scheduling, and latest dates by copying the earliest dates.
  • C. Earliest dates are scheduled by backward scheduling, and latest dates by forward scheduling.
  • D. Earliest dates are scheduled by forward scheduling, and latest dates by backward scheduling.

正解: D

 

質問 34
Which of the following apply to dynamic item processor (DIP)? Note: There are 3 correct Answers to this question.

  • A. Sources can be based on line items.
  • B. Material determination is mandatory.
  • C. DIP is used to create a quotation.
  • D. Usage of cost elements is mandatory.
  • E. Sales prices are maintained in the DIP profile.

正解: A,C,E

 

質問 35
Your customer has created networks with internal activities and generated capacity requirements. Now, they want to analyze the capacity requirements of their project. Which report do you recommend?

  • A. Extended capacity evaluation
  • B. Capacity load work center view
  • C. Structure overview
  • D. None
  • E. Individual overview capacity requirements

正解: E

 

質問 36
Which objects do you have to maintain to enable automatic assignment of material components to the project? Note: There are 2 correct Answers to this question.

  • A. WBS element
  • B. Material master
  • C. Network activity
  • D. BOM item

正解: C,D

 

質問 37
......

C-TS412-1909正真正銘のベスト資料、オンライン練習試験:https://jp.fast2test.com/C-TS412-1909-premium-file.html


弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

我々の働いている時間: ( GMT 0:00-15:00 )
月曜日から土曜日まで

サポート: 現在連絡 

English Deutsch 繁体中文 한국어