質問 36
You want to use subnetworks during the project. Which of the following statements describes subnetworks?

  • A. Subnetworks must be scheduled separately from the superior network.
  • B. The scheduling type of a subnetwork is always copied from the superior network.
  • C. Maintenance orders can be defined as subnetworks.
  • D. A subnetwork cannot be defined for a superior subnetwork.

正解: C

 

質問 37
Project Structures
Which the following statement regarding networks are correct?.
Note : there are 3 correct answers for this question.

  • A. You can assign the same work center to more than one activity on the same network.
  • B. If a network activity requires more capacity than available in a work center, the system automatically proposes an alternative work center.
  • C. During scheduling, the system plans the network activities in such a way that the assigned work center are not overloaded in terms of capacity.
  • D. Capacity requirements of a network activity are reduced when the activity is confirmed.
  • E. You can assign more than one activity element to a network activity.

正解: A,D,E

 

質問 38
Budgeting is implemented for projects. The budget has been adjusted several times. What standard report type provides an overview of adjustments on the budget?

  • A. Hierarchical report on budget updates
  • B. Structure overview for budgets
  • C. Line item report for budgets
  • D. Cost element report on budget updates

正解: A

 

質問 39
Which of the following statements apply to project versions? Note: There are 2 correct Answers to this question.

  • A. Project versions can be changed.
  • B. Project versions can be created automatically based on user status.
  • C. Manually created project versions always require a project version profile.
  • D. Project versions are mandatory for Milestone Trend Analysis (MTA).

正解: A,D

 

質問 40
You want to determine the planned costs for an internally processed activity. Which data do you need Note: There are 2 correct answers to this question

  • A. Duration
  • B. Profit center
  • C. Activity type
  • D. Work

正解: A,D

 

質問 41
Your customer wants to use requirements grouping in SAP Project System. What are the prerequisites for requirements grouping of materials? Note: There are 2 correct Answers to this question.

  • A. The materials must allow sales order or project stock.
  • B. The procurement type of the material must be internal.
  • C. An MRP group must be assigned.
  • D. The exact lot size procedure must be used.

正解: A,C

 

質問 42
You want to use billing for a customer project. Which customizing object controls the billing of sales order items?

  • A. Schedule line category
  • B. Requirements type
  • C. Item category
  • D. Requirements class

正解: C

 

質問 43
Dates
How are earliest dates and latest dates of activities schedule?

  • A. Earliest dates and latest dates are scheduled by forward scheduling.
  • B. Earliest dates are scheduled by forward scheduling , and the latest dates by backward scheduling.
  • C. Earliest dates are scheduled by backward scheduling, and the lates dates by copying the earliest dates.
  • D. Earliest dates are scheduled by backward scheduling, and the latest dates by forward scheduling.

正解: B

 

質問 44
You use networks and internal activities in your project. You have activated capacity requirements and notice that one work center is overloaded. You have no authorization to change the work center. How can you reduce the overload of the work center? Note: There are 2 correct answers to this question

  • A. Increase the capacities of the work center in the project planning board.
  • B. Maintain subordinate internal activity elements assigned to other work centres
  • C. Trigger automatic capacity leveling inside the project planning board
  • D. Shift activities backward or forward on the time axis where more capacities are available

正解: B,D

 

質問 45
You use networks and internal activities in your project. You have activated capacity requirements and notice that one work center is overloaded. You have no authorization to change the work center. How can you reduce the overload of the work center? Note: There are 2 correct Answers to this question.

  • A. Increase the capacities of the work center in the project planning board.
  • B. Trigger automatic capacity leveling inside the project planning board.
  • C. Maintain subordinate internal activity elements assigned to other work centers.
  • D. Shift activities backward or forward on the time axis where more capacities are available.

正解: B,D

 

質問 46
You are working with predefined project coding masks to create projects. Which of the following statements apply? Note: There are 2 correct Answers to this question.

  • A. You can use the same coding mask for standard projects and operative projects.
  • B. You can only use numbers for a project coding mask definition.
  • C. You can use an indicator to determine that only coded project numbers may be used within SAP Project System.
  • D. You can shorten the project mask even when there are existing projects.

正解: A,C

 

質問 47
Which statement is valid regarding networks?

  • A. Material components can be assigned to activity elements
  • B. A network activity can be assigned to several WBS elements
  • C. Relationships can be used to connect activities of different networks
  • D. A network can be activity-account-assigned and header-account-assigned

正解: B

 

質問 48
Materials
Your customer want to use scheduling for network to specify planned dates of task. In the SAP project system there are different set of dates that can be scheduled.
Which set of dates can be used for scheduled for network?
Note : there are 2 correct answer for this question.

  • A. Basic dates
  • B. Baseline dates
  • C. Planned dates
  • D. Fundamental dates
  • E. Forecast dates

正解: A,E

 

質問 49
You have created an internally-processed network activity, and assigned a work center and the work.
After saving, you discover that no planned costs are displayed in the cost element report for the activity.
What could be the reason? Note: There are 3 correct Answers to this question.

  • A. The formula for costing in the work center is incorrect.
  • B. The activity output price for the activity type and cost center assigned to the work center is not maintained.
  • C. Integrated planning for the network is active.
  • D. The duration is missing in the activity.
  • E. The Determine Costs indicator in the network header rules out planned cost calculation.

正解: B,D,E

 

質問 50
Materials
Your customer use a tight (estrecha) integration between sales order and WBS with network to deliver finished and semi-finish product.
What benefit do they have when using delivery from project (CNSO).

  • A. With delivery from projects you can generate purchase requisitions for sub-contractors.
  • B. With delivery from projects You can generate goods issues for project without creating delivery documents.
  • C. With the delivery from project you can deliver material component assigned to your network.
  • D. With delivery from projects good receipt are automatically posted while saving.

正解: B

 

質問 51
Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20.
The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day.
What do you recommend to set up the requirement date for the component ?

  • A. Set up the requirement date aligned with the activity start date and a negative offset of 5 days
  • B. Set up the requirement date aligned with the activity start date and an offset of 5 days
  • C. Set up the requirement date manually as February 5.
  • D. Set up the requirement date aligned with the activity finish date and an offset of 15 days.

正解: A

 

質問 52
......

C-TS412-1909問題集はSAP Certified Application Associate認証済み試験問題と解答:https://jp.fast2test.com/C-TS412-1909-premium-file.html


弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

我々の働いている時間: ( GMT 0:00-15:00 )
月曜日から土曜日まで

サポート: 現在連絡 

English Deutsch 繁体中文 한국어