質問 # 51
結果分析の評価方法でエキスパート モードを使用する理由は何でしょうか?
- A. 異なる行IDの使用
- B. 異なる通貨での評価
- C. 財務会計への転記のための異なる勘定の割り当て
- D. 異なる会社コードに属する請求WBS要素
正解:A
解説:
One reason to use expert mode in the valuation method for results analysis is usage of different line ID. Results analysis is a function that allows you to calculate and post values for work in process (WIP), reserves for unrealized costs (RUC), profit from sales order stock (PSOS), and so on. Results analysis uses valuation methods to determine how these values are calculated based on various criteria, such as cost of sales method, percentage of completion method, revenue-based method, and so on. Expert mode is a type of valuation method that allows you to define your own logic and rules for results analysis by using formulas and conditions. One reason to use expert mode in the valuation method for results analysis is usage of different line ID. A line ID is a parameter that identifies a line item in results analysis data. A line ID can have various attributes, such as cost element group, value category, posting indicator, and so on. By using expert mode in the valuation method for results analysis, you can use different line ID for different scenarios or requirements that are not covered by the standard valuation methods. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
質問 # 52
顧客はSAPプロジェクトシステムで要件グループ化を使用したいと考えています。品目の要件グループ化の前提条件は何ですか? 注: この質問には2つの正解があります
- A. 品目の調達タイプは内部調達である必要があります
- B. MRPグループを割り当てる必要があります
- C. 正確なロットサイズの手順を使用する必要があります
- D. 材料は販売注文またはプロジェクト在庫を許可する必要があります
正解:B、D
解説:
Requirements grouping of materials is a process that allows you to plan and procure materials jointly for several WBS elements within a project or across projects. To use requirements grouping of materials, the materials must allow sales order or project stock, which means they must have a special procurement type of E or Q in the material master. An MRP group must also be assigned to the materials, which defines the parameters for material requirements planning, such as lot size and planning strategy. Reference: https://help.sap.com/doc/78f5c353b677b44ce10000000a174cb4/700_SFIN20%20006/en-US/0814c353b677b44ce10000000a174cb4.html
質問 # 53
プロジェクト計画ボードに表示されるのは次のうちどれですか? 注: この質問には 2 つの正解があります。
- A. アクティビティに割り当てられたメンテナンスオーダー
- B. WBS要素に割り当てられた生産オーダー
- C. プロジェクト関連の発注書
- D. 容量要件
正解:A、D
解説:
The project planning board is a graphical tool that allows you to plan and monitor projects in a Gantt chart view. You can use the project planning board to display capacity requirements and maintenance orders that are related to project activities. You can also display other objects such as WBS elements, networks, activities, milestones, production orders, sales orders, purchase orders, and so on. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/1ad4b65334e6b54ce10000000a174cb4.html?locale=en-US&state=PRODUCTION&version=2020.002
質問 # 54
顧客プロジェクトで請求プランを割り当てる理由は何ですか?
- A. 見積作成には請求プランが前提条件となります
- B. 請求計画は販売注文明細に自動的にコピーされます。
- C. 課金プランは収益計画に使用されます
- D. 課金プランにより、課金プロセスを実行できます。
正解:C
解説:
Billing plans are used for revenue planning in customer projects because they allow you to define billing dates and billing amounts for each project phase or milestone. Billing plans can also be used to create billing requests or invoices automatically based on the billing dates and amounts. Billing plans help you to plan and monitor the cash flow and profitability of your customer projects. Reference: https://help.sap.com/viewer/0c9a2f8f9c1b4a2e8b3f7d0c9b6e1d8a/2020.000/en-US/4c5f7a3e6b571014e10000000a174cb4.html
質問 # 55
顧客は、販売注文と WBS をネットワークと緊密に統合して、完成品と半完成品を納品します。
プロジェクトからの配信 (CNSO) を使用するとどのような利点がありますか。
- A. プロジェクトからの配送により、ネットワークに割り当てられた品目コンポーネントを配送できます。
- B. プロジェクトからの配送により、保存時に受領証が自動的に転記されます。
- C. プロジェクトからの出荷では、出荷伝票を作成せずにプロジェクトの出庫を生成できます。
- D. プロジェクトからの配送により、下請業者向けの購買依頼を生成できます。
正解:A
解説:
Delivery from project (CNSO) is a function that allows you to deliver material components that are assigned to network activities in a project. You can use this function to generate goods issues for project stock without creating delivery documents. You can also use this function to create delivery documents for sales order stock or plant stock that are assigned to network activities. Delivery from project helps you to reduce the effort and time required for delivering materials in a project. Reference: https://help.sap.com/saphelp_erp60_sp/helpdata/EN/8e/8bc95360267214e10000000a174cb4/frameset.htm
質問 # 56
次のアクションのうち、外部処理の実際のコストを転送できるのはどれですか? 注: この質問には2つの正解があります。
- A. 商品の受領書を保存する
- B. 注文書の保存
- C. 仕入先請求書の保存
- D. サービスエントリシートの保存
正解:C、D
解説:
Saving a supplier invoice and saving a service entry sheet are some of the actions that can transfer actual costs for external processing. External processing is a process that involves procuring services from external vendors for project activities. Saving a supplier invoice is an action that records the payment request from a vendor for the services performed and posts actual costs to the project. Saving a service entry sheet is an action that records the delivery of services from a vendor and posts actual costs to the project. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
質問 # 57
プロジェクト計画ボードに表示されるのは次のうちどれですか? 注: この質問には 2 つの正解があります。
- A. アクティビティに割り当てられたメンテナンスオーダー
- B. WBS要素に割り当てられた生産オーダー
- C. プロジェクト関連の発注書
- D. 容量要件
正解:A、D
解説:
The project planning board is a graphical tool that allows you to plan and monitor projects in a Gantt chart view. You can use the project planning board to display capacity requirements and maintenance orders that are related to project activities. You can also display other objects such as WBS elements, networks, activities, milestones, production orders, sales orders, purchase orders, and so on. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/1ad4b65334e6b54ce10000000a174cb4.html?locale=en-US&state=PRODUCTION&version=2020.002
質問 # 58
SD ドキュメントの組立オーダーを作成するために、組立処理に関連するオブジェクトはどれですか?
- A. コントロールキー
- B. プロジェクトプロファイル
- C. アイテムカテゴリ
- D. 要件クラス
正解:D
解説:
Requirement class is an object that is relevant in assembly processing to create an assembly order for the SD document. Requirement class defines whether an assembly order is created automatically or manually for a sales order item, and whether it is relevant for availability check, costing, or settlement. Requirement class also controls the assignment of requirements type and account assignment category to the sales order item. Reference: https://help.sap.com/viewer/0c9a2f8f9c1b4a2e8b3f7d0c9b6e1d8a/2020.000/en-US/4c5f7a3e6b571014e10000000a174cb4.html
質問 # 59
日付
活動の最も早い日付と最も遅い日付はどのようにスケジュールされますか?
- A. 最早日付と最遅日付はフォワードスケジュールによってスケジュールされます。
- B. 最も早い日付は順方向スケジュールでスケジュールされ、最も遅い日付は逆方向スケジュールでスケジュールされます。
- C. 最も早い日付は逆方向スケジュールでスケジュールされ、最も遅い日付は順方向スケジュールでスケジュールされます。
- D. 最も早い日付は逆順にスケジュールされ、最も遅い日付は最も早い日付をコピーしてスケジュールされます。
正解:B
解説:
This is how earliest dates and latest dates of activities are scheduled in the SAP Project System. Earliest dates are scheduled by forward scheduling, and latest dates by backward scheduling. Forward scheduling is a method of scheduling activities from the start date of the project to the end date. Backward scheduling is a method of scheduling activities from the end date of the project to the start date. The earliest dates are determined by forward scheduling and the latest dates are determined by backward scheduling. This ensures that the activities are scheduled within the project duration and that any slack time is distributed evenly
質問 # 60
フロート時間はスケジュール時に計算されます。
浮遊時間に関する次の記述のうち正しいものはどれですか?
注: この質問には3つの正解があります
- A. デフォルトでは、クリティカルアクティビティにはフロート時間があり、これはゼロ以下です。
- B. フリーフロートの最大サイズは、アクティビティの合計フロートと同じ大きさです。
- C. 浮動時間は負の値になることがあります
- D. WBS要素の浮動時間は外挿によって計算されます
- E. 時間制約が「開始しなければならない」アクティビティには、常に負の浮動時間があります。
正解:B、C、D
解説:
Float time is the amount of time that an activity or a WBS element can be delayed without affecting the end date of the project. Float time can be negative if an activity or a WBS element is already behind schedule. The float time of WBS elements is calculated by extrapolating the float times of their subordinate activities. The free float is the amount of time that an activity can be delayed without affecting the start date of its successor activities. The total float is the amount of time that an activity can be delayed without affecting the end date of the project. Therefore, the maximum size of a free float is as large as the total float of an activity. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
質問 # 61
どのオブジェクトに対して課金プランを作成できますか? 注: この質問には 2 つの正解があります
- A. 販売注文品目
- B. マイルストーン
- C. WBS要素
- D. プロジェクト定義
正解:A、C
解説:
Billing plans can be created for WBS elements and sales order items. Billing plans are used to define billing dates and billing amounts for periodic or milestone billing. WBS elements can be assigned to billing plans if they are assigned to a sales document item or if they have a billing element indicator set. Sales order items can be assigned to billing plans if they have a relevant item category and billing relevance. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
質問 # 62
プロジェクト定義を作成するときに指定する__________________は、プロジェクト全体に対して一意です。正しい回答を選択してください。
- A. 制御エリア
- B. 会社コード
- C. 企画部
- D. 植物
正解:A
解説:
"The controlling area that you specify when you create a project definition is unique for the entire project. You specify the controlling area just once when you create the project." Reference: 2
質問 # 63
ネットワークを保存し、割り当てられた品目コンポーネントで有効化しました。ネットワークをリリースするとすぐに、「ビジネストランザクションを実行できません」というエラー メッセージが表示されます。このエラー メッセージの原因は何でしょうか。
- A. 材料コンポーネントの予算が不足しています
- B. 材料コンポーネントの予約がありません
- C. 材料の入手先がありません
- D. 材料コンポーネントをリリースするための承認がありません
正解:D
解説:
One possible reason for the error message "Business transaction cannot be carried out" when releasing a network is missing authorizations to release material components. Material components are materials that are required for executing a network activity. To release material components, you need to have the authorization object C_AFKO_ATY with the activity 02 (change) for the order type of the network. Reference: https://answers.sap.com/questions/7530952/the-business-transaction-cannot-be-carried-out-mes.html
質問 # 64
間接費率を WBS 要素に割り当てたい場合、WBS 要素に何を割り当てる必要がありますか?
- A. 決済ルール
- B. 原価計算シート
- C. 投資プロファイル
- D. 結果分析キー
正解:B
解説:
To allocate overhead rates to a WBS element, you must assign a costing sheet to the WBS element. A costing sheet is a tool that allows you to define and calculate overhead costs based on various criteria, such as plant, company code, material origin, or order type. You can assign a costing sheet to a WBS element in the Control Data tab of the WBS element master data. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/df72bb53707db44ce10000000a174cb4.html
質問 # 65
ユーザーのステータスに基づいて構造概要を検索するにはどうすればよいでしょうか? 注: この質問には 2 つの正解があります
- A. ステータス選択プロファイルで検索
- B. 個々のステータスを検索することで
- C. ステータスの組み合わせコードで検索する
- D. ステータスプロファイルを検索することで
正解:A、B
解説:
To search in the structure overview based on the user status, you can use either the status selection profile or the individual status as search criteria. The structure overview is a function that allows you to display and analyze various structural elements of a project, such as WBS elements, networks, activities, milestones, and so on. The structure overview also provides various search functions that allow you to find specific project objects based on different criteria, such as number, description, system status, user status, and so on. To search in the structure overview based on the user status, you can use either:
The status selection profile: This is a parameter that allows you to define a set of user statuses that can be used as a filter for searching project objects. You can create and maintain status selection profiles in Customizing for Project System under Structures Status Management Define Status Selection Profiles . You can also assign a default status selection profile to a project profile or a network profile.
The individual status: This is a parameter that allows you to enter a single user status as a search criterion for finding project objects. You can enter an individual status directly in the search dialog box of the structure overview.
質問 # 66
ネットワーク、マテリアル、マイルストーンを含むプロジェクトがあります。先行アクティビティの 2 日後にアクティビティを開始するように計画します。どうすればよいでしょうか。
注: この質問には 2 つの正解があります。
- A. 品目コンポーネントの所要日には2日間のオフセットを使用します。
- B. マイルストーンの日付に 2 日間のオフセットを使用します。
- C. アクティビティの開始日を計算し、それに応じて「開始する必要がある日」という制約を設定します。
- D. 両方のアクティビティの関係に 2 日間のオフセットを使用します。
正解:C、D
解説:
"You can use an offset to specify a time interval between two activities. For example, you can specify that an activity should start two days after its predecessor activity has finished." According to SAP Help Portal2, "You can use constraints to specify fixed dates for activities. For example, you can use the constraint 'Must start on' to fix the start date of an activity." Reference: 12
質問 # 67
......