
SAP C-S43-2022試験情報と無料練習テストはこちら
合格させるSAP C-S43-2022プレミアムお試しセットテストエンジンPDFで無料問題集セット
SAP C-S43-2022 認定試験の出題範囲:
| トピック | 出題範囲 |
|---|---|
| トピック 1 |
|
| トピック 2 |
|
| トピック 3 |
|
| トピック 4 |
|
| トピック 5 |
|
質問 # 33
In which maintenance object can you use an activity type? Note: There are 2 correct answers to this question.
- A. Maintenance order header
- B. Work center
- C. Notification activity
- D. Maintenance order operation
正解:B、D
質問 # 34
Which parameter in a maintenance strategy do you use to set the start/end date of the maintenance order?
- A. Initial/subsequent buffer
- B. Call horizon
- C. Scheduling type
- D. Package offset
正解:B
解説:
Explanation
The call horizon is the parameter in a maintenance strategy that determines the start/end date of the maintenance order. The call horizon defines the percentage of the maintenance cycle that must be expired before the system generates a call object, such as a maintenance order or notification. The start date of the call object is calculated by adding the callhorizon to the last completion date of the maintenance plan. The end date of the call object is calculated by adding the maintenance cycle to the last completion date of the maintenance plan. The call horizon can be used to control the scheduling of preventive maintenance activities and ensure that they are performed within the planned time frame. References:
Preventive Maintenance in SAP S/4HANA, Lesson 2: Using Cycle Set Sequences, page 13-14 Highlights for Asset Management in SAP S/4HANA 2021, New Scope Items, Fig. 2: Standardized end-to-end process Proactive Maintenance (4HH)
質問 # 35
Which options do you have in SAP S/4HANA Asset Management, Public Cloud Edition? Note: There are 2 correct answers to this question
- A. You have access to the SAP S/4HANA back-end system
- B. You do NOT have access to the SAP S/4HANA back-end system.
- C. You can configure SAP S/4HANA Cloud via the SAP Asset Intelligence Network
- D. You can configure SAP S/4HANA Cloud via the self-service configuration UI.
正解:B、D
解説:
Explanation
SAP S/4HANA Asset Management, Public Cloud Edition is a cloud-based solution that offers a simplified and standardized configuration of the system via the self-service configuration UI. You can use this UI to adjust the system settings according to your business needs. You do not have access to the SAP S/4HANA back-end system, as it is managed by SAP. SAP Asset Intelligence Network is a separate cloud-based solution that connects manufacturers, operators, and service providers of physical assets. You can use SAP Asset Intelligence Network to share and exchange asset information, but you cannot use it to configure SAP S/4HANA Cloud. References:
SAP S/4HANA Cloud, Public Edition - SAP Learning
SAP S/4HANA Cloud for Asset Management, Public Edition
質問 # 36
Which operations can the responsible person perform after a maintenance order is technically completed? Note: There are 2 correct answers to this question
- A. Update the estimated costs
- B. Change the planned costs
- C. Lock or unlock the order
- D. Change the settlement rule
正解:C、D
解説:
After a maintenance order is technically completed, the responsible person can perform the following operations1:
Lock or unlock the order: This prevents or allows further changes to the order data, such as actual costs, settlement rule, or confirmation data.
Change the settlement rule: This allows the responsible person to adjust the distribution of costs to the relevant receivers, such as cost centers, assets, or orders.
Post goods movements: This allows the responsible person to record the consumption or return of materials that were used for the maintenance work.
Enter measurement documents: This allows the responsible person to record the measurement readings of the technical objects that were maintained.
The responsible person cannot perform the following operations after a maintenance order is technically completed1:
Update the estimated costs: This is only possible before the order is released or during the execution phase.
Change the planned costs: This is only possible before the order is released or during the execution phase.
Change the order type: This is only possible before the order is released.
Change the order status: This is only possible before the order is technically completed or after it is reversed.
Therefore, the correct answers are A and C. References: 1: Maintenance Order Types | SAP Help Portal
質問 # 37
Which of these are necessary steps of the Inspection Checklist process? Note: There are 2 correct answers to this question
- A. Generate Inspection Lols within the checklists view.
- B. Record the usage decision for an Inspection Lot
- C. Generate Inspection Lots assigned to maintenance order headers.
- D. Link PM task list with assigned inspection point type to a maintenance item.
正解:A、B
解説:
The inspection checklist process is an end-to-end process from the creation of inspection plans to results recording and follow-up actions in Plant Maintenance. The necessary steps of the inspection checklist process are:
Generate object lists for the maintenance order, which contain the technical objects to be inspected.
Generate inspection checklists for the maintenance order, which contain the inspection lots based on the inspection plans assigned to the technical objects.
Record the inspection results for the inspection characteristics in the inspection lots.
Record the usage decision for the inspection lots, which determines whether the technical objects are accepted or rejected.
Therefore, option A (Generate Inspection Lots within the checklists view) and option C (Record the usage decision for an Inspection Lot) are correct, while option B (Link PM task list with assigned inspection point type to a maintenance item) and option D (Generate Inspection Lots assigned to maintenance order headers) are not part of the inspection checklist process.
Reference:
Explaining Inspection Checklists
Set up your SAP S/4HANA system for EAM Inspection Checklists
質問 # 38
Which steps support the maintenance technician in the Report and Repair Malfunction app (3 tiles)? Note:
There are 3 correct answers to this question
- A. Verify planned and actual costs
- B. Assign a production resource tool (PRT) to the operation
- C. Plan repair work for the responsible work center
- D. Complete the malfunction report
- E. Find malfunction records already created in a list
正解:C、D、E
解説:
Explanation
The Report and Repair Malfunction app supports the maintenance technician in the following steps:
Plan repair work for the responsible work center: The app allows the technician to assign the work items to the work center that is responsible for the repair work. The work center can be a person, a group of persons
質問 # 39
What do you need to configure to enable entries in the action log of a piece of equipment?
- A. Define the corresponding history related field for the equipment reference category.
- B. Activate the change documents for the equipment reference category.
- C. Activate the change documents for the equipment category.
- D. Define history related fields in the usage period customizing.
正解:C
解説:
Explanation
The action log is a function that allows you to view the changes that were made to fields during the processing of an order or a piece of equipment. The action log shows you the date, time, user, sub-object, field name, old value, and new value of each change. To enable entries in the action log of a piece of equipment, you need to activate the change documents for the equipment category. The equipment category is a classification of equipment that determines the data that can be maintained for the equipment. The change documents are records of the changes that are made to the data of the equipment. You can activate the change documents for the equipment category in the Customizing for Technical Objects under Equipment Define Equipment Categories . You do not need to define history related fields in the usage period customizing, as this is only relevant for the equipment history. The equipment history is a function that allows you to view the usage periods of the equipment, such as the installation, removal, or transfer dates. The history related fields are fields that are relevant for the equipment history, such as the functional location, the maintenance plant, or the cost center. You can define the history related fields in the Customizing for Technical Objects under Equipment Define History-Related Fields for Usage Periods . You do not need to define or activate the change documents for the equipment reference category, as this is only relevant for the equipment reference. The equipment reference is a function that allows you to link a piece of equipment to another object, such as a material, a serial number, or a document. The equipment reference category is a classification of equipment references that determines the data that can be maintained for the equipment reference. You can define the equipment reference category in the Customizing for Technical Objects under Equipment Define Equipment Reference Categories . You can activate the change documents for the equipment reference category in the Customizing for Technical Objects under Equipment Define Change Documents for Equipment Reference Categories . References:
Display of the Action Log, section "Use"
Equipment Categories, section "Change Documents"
History-Related Fields for Usage Periods, section "History-Related Fields" Equipment Reference Categories, section "Change Documents"
質問 # 40
You settle a refurbishment order with the batches (valuation types) having price control standard price. What is the effect? Note. There are 2 correct answers to this question.
- A. The effective costs are posted as a credit memo to a price difference account
- B. The goods receipt for the batch refurbished is posted with the value of the standard price.
- C. The goods receipt for the batch refurbished is posted with the value of the moving average price
- D. The effective costs are posted to the respective batch (valuation type).
正解:A、B
解説:
When you settle a refurbishment order with the batches (valuation types) having price control standard price, the following effects occur:
The effective costs are posted as a credit memo to a price difference account. This means that the difference between the actual costs of the refurbishment and the standard price of the batch is recorded as a variance in the accounting document. This ensures that the inventory value of the batch is not affected by the refurbishment costs1 The goods receipt for the batch refurbished is posted with the value of the standard price. This means that the inventory value of the batch is updated with the predefined price that is maintained in the material master. This ensures that the inventory value of the batch is consistent and stable1 The other options are incorrect because:
The effective costs are not posted to the respective batch (valuation type). The batch valuation is based on the standard price, not the actual costs of the refurbishment1 The goods receipt for the batch refurbished is not posted with the value of the moving average price. The moving average price is only used for batches with price control moving average price, not standard price1 References: 1: Settlement Receiver | SAP Help Portal
質問 # 41
Which functions are available in the Resource Scheduling for Maintenance Planners app? Note: There are 2 correct answers to this question.
- A. Monitor maintenance order operations due in the next 4 weeks
- B. Print job papers from a maintenance order.
- C. Dispatch maintenance order operations
- D. Schedule and dispatch maintenance operations by shifts.
正解:A、C
質問 # 42
Where can the maintenance planner perform a material availability check? Note: There are 2 correct answers to this question?
- A. Via the SAP Fiori app "Maintenance Scheduling Board"
- B. Within the SAP Fion-based background job
- C. Via the SAP Fiori app "Manage Maintenance Order List"
- D. Via the SAP Fiori epp "Manage Maintenance Planning Buckets"
正解:A、C
質問 # 43
Which functionalities are available in the SAP Service and Asset Manager (SAP Asset Manager) for a maintenance worker? Note: There are 2 correct answers to this question
- A. Schedule resources
* Change task list - B. Change BOM
* Create a work order on the ESRI map - C. Display maps
* Display and maintain technical objects - D. Confirm time sheets
* Attach documents
正解:C、D
質問 # 44
To which objects can a personnel number be directly assigned? Note: There are 2 correct answers to this question?
- A. Work center
- B. Planner group
- C. Maintenance plan
- D. Business partner
正解:A、D
解説:
A personnel number is a unique identifier for an employee in the SAP system. A personnel number can be directly assigned to the following objects:
C . Work center. A work center is a location where maintenance activities are performed. A work center can have one or more personnel numbers assigned to it, which represent the employees who work at that location. The personnel numbers can be used for capacity planning, scheduling, and confirmation of maintenance orders1.
D . Business partner. A business partner is a person or an organization that has a business relationship with the company. A business partner can have one or more roles, such as customer, vendor, or contact person. A personnel number can be assigned to a business partner role, which allows the system to identify the employee who is responsible for the business partner or who acts as a contact person for the business partner2.
A personnel number cannot be directly assigned to the following objects:
A . Planner group. A planner group is a group of employees who are responsible for planning and processing maintenance orders. A planner group is assigned to a maintenance order header, but not to a personnel number. A planner group can have one or more work centers assigned to it, which in turn can have personnel numbers assigned to them3.
B . Maintenance plan. A maintenance plan is a document that defines the frequency and scope of preventive maintenance activities for technical objects. A maintenance plan is assigned to a maintenance item, which contains the technical object and the task list for the maintenance activities. A maintenance plan does not have a direct assignment to a personnel number, but it can have a planner group assigned to it, which can have work centers and personnel numbers assigned to it. References: 1: Work Center 2: Business Partner 3: Planner Group : [Maintenance Plan]
質問 # 45
What do you have to consider regarding a cross-plant planning scenario?
- A. Multiple maintenance plants are assigned to a planning plant (n: 1).
- B. Only a maximum number of five maintenance plants can be assigned to a planning plant.
- C. Multiple planning plants are assigned to a maintenance plant (m: 1).
- D. It is only possible within the same company code.
正解:A、C
解説:
Explanation
A cross-plant planning scenario is a special planning process that allows you to carry out material requirements planning for various plants centrally. This facilitates the production of a product in another plant and it also guarantees a smooth flow of materials between different plants. In a cross-plant planning scenario, you can assign multiple maintenance plants to a planning plant (n: 1) or multiple planning plants to a maintenance plant (m: 1). This means that you can plan and execute maintenance orders in different plants using a common planning plant or a common maintenance plant. There is no limit on the number of maintenance plants that can be assigned to a planning plant, so answer B is incorrect. A cross-plant planning scenario is also possible across different company codes, as long as the plants belong to the same controlling area. Therefore, answer D is also incorrect. References: Cross-Plant Planning | SAP Help Portal and SAP S/4HANA Asset Management: Plants from a Maintenance ... - SAP PRESS
質問 # 46
How is Phase-based Maintenance Processing activated in the SAP system? Note: There are 2 correct answers to this question
- A. By manually activating the corresponding Business Feature in case Best Practices are not used.
- B. By installing the corresponding enhancement pack and activating the related business function
- C. Phase-based maintenance is always active in all S/4HANA 2021 editions and above
- D. Through Best Practices scope items 4HH and 4HI.
正解:A、D
解説:
Phase-based maintenance processing is a new concept that was introduced in SAP S/4HANA Cloud 2011 and SAP S/4HANA 2021. It allows you to track the life cycle of the maintenance processes using predefined phases and sub-phases, instead of system and user statuses. Phase-based maintenance processing is activated in the SAP system through the following ways:
Through Best Practices scope items 4HH and 4HI. These are the new scope items for reactive and proactive maintenance that use the phase model for maintenance requests and orders. You can activate these scope items using the SAP Activate methodology and the SAP Best Practices Explorer12.
By manually activating the corresponding Business Feature in case Best Practices are not used. If you do not use the Best Practices scope items, you can still activate the phase model for maintenance requests and orders by using the Business Feature switch in the Customizing activity Define Settings for Maintenance Processing34.
Phase-based maintenance processing is not always active in all S/4HANA 2021 editions and above, as it depends on the scope items or the Business Feature switch. Therefore, answer B is incorrect. Phase-based maintenance processing is not activated by installing the corresponding enhancement pack and activating the related business function, as this is the old way of activating new features in SAP ERP. Therefore, answer C is also incorrect. References: SAP S/4HANA Cloud release of 2011 - Asset Management (Maintenance ... and Highlights for Asset Management in SAP S/4HANA 2021 | SAP Blogs
質問 # 47
Which views can you assign to an equipment category via a view profile? Note: There are 2 correct answers to this question?
- A. Manufacturer data
- B. Serial data
- C. Warranty
- D. Configuration
正解:A、C
解説:
Explanation
An equipment category defines the technical characteristics of an equipment and the views that are available for it. A view profile is a set of views that can be assigned to an equipment category. The views that can be assigned to an equipment category via a view profile are:
Basic data
Classification
Location
Organization
Partner
Status
Structure
Warranty
Manufacturer data
Measurement document
History
Permits
Documents
User fields
Serial data
Configuration
Object links
Time-dependent data
Linear data
Geographical data
Maintenance plan
Maintenance item
Maintenance task list
Maintenance order
Maintenance notification
Service order
Service notification
Service contract
Service confirmation
Service quotation
Service request
Service plan
Service item
Service task list
Service product
Service product allocation
Service product structure
Service product location
Service product partner
Service product status
Service product classification
Service product documents
Service product permits
Service product user fields
Service product serial data
Service product configuration
Service product object links
Service product time-dependent data
Service product linear data
Service product geographical data
Among these views, the ones that match the options given in the question are Warranty and Manufacturer data.
Therefore, the correct answers are A and D.
References:
SAP Help Portal - Equipment Category
SAP Help Portal - View Profile
質問 # 48
You want to create a new functional location. Which selling is part of the Customizing for the functional location category? Note: There are 3 correct answers to this question
- A. Object information
- B. Measuring point category
- C. Usage period
- D. Warranty category
- E. Status profile
正解:A、B、E
解説:
The Customizing for the functional location category includes the following settings: usage period, object information, and status profile.
The usage period defines the start and end dates of the functional location's usage. It can be used to control the validity of maintenance plans and orders, and to calculate the age of the functional location. You can define the usage period in the Customizing activity Define Functional Location Categories1.
The object information defines the additional data that can be entered for the functional location, such as manufacturer, construction type, serial number, and equipment number. You can define the object information in the Customizing activity Define Functional Location Categories1.
The status profile defines the user statuses that can be assigned to the functional location. The user statuses can be used to control the business transactions that are allowed for the functional location, such as creating orders, notifications, or measuring documents. You can define the status profile in the Customizing activity Define Status Profile2.
質問 # 49
Which component is used to display data in the Technical Object Breakdowns and Technical Object Damages app?
- A. SAP Asset Strategy and Performance Management
- B. SAP Lumira Designer
- C. SAP S/4HANA Core Data Services
- D. SAP Predictive Analysis
正解:B
解説:
The Technical Object Breakdowns and Technical Object Damages app use SAP Lumira Designer to display data in a user-friendly and interactive way. SAP Lumira Designer is a tool that allows you to create analytical applications and dashboards based on SAP S/4HANA Core Data Services (CDS) views. SAP Asset Strategy and Performance Management and SAP Predictive Analysis are not components used to display data in this app, but they are other solutions that can help you optimize your asset management strategy and performance. References:
Technical Object Breakdowns
Technical Object Damages
[SAP Lumira Designer]
質問 # 50
Which scheduling parameters are used in a multiple-counter plan? Note: There are 2 correct answers to this question.
- A. Factory calendar
- B. Scheduling indicator
- C. Start date
- D. Scheduling period
正解:B、D
解説:
Explanation
A multiple-counter plan is a maintenance plan that contains multiple maintenance cycles based on different counters. The scheduling parameters are used to define the scheduling rules for each maintenance cycle in the plan. The scheduling parameters are:
Scheduling period: This is the interval between two maintenance calls, expressed in the unit of the counter. For example, if the counter is measured in kilometers, the scheduling period could be 10,000 km. This means that a maintenance call is due every 10,000 km. This parameter is mandatory for each maintenance cycle in a multiple-counter plan1.
Scheduling indicator: This is the indicator that determines how the system calculates the next due date for the maintenance call, based on the counter reading and the scheduling period. There are three possible values for the scheduling indicator1:
Fixed: The system calculates the next due date by adding the scheduling period to the counter reading at the time of the last maintenance call. For example, if the last maintenance call was at
20,000 km and the scheduling period is 10,000 km, the next due date is 30,000 km.
Shifted: The system calculates the next due date by adding the scheduling period to the counter reading at the time of the actual maintenance execution. For example, if the actual maintenance execution was at 21,500 km and the scheduling period is 10,000 km, the next due date is 31,500 km.
Proportional: The system calculates the next due date by adding the scheduling period to the counter reading at the time of the planned maintenance execution. For example, if the planned maintenance execution was at 20,500 km and the scheduling period is 10,000 km, the next due date is 30,500 km.
Start date: This is the date when the first maintenance call is due, based on the counter reading and the scheduling period. This parameter is optional for each maintenance cycle in a multiple-counter plan1. If it is not specified, the system uses the current date as the start date.
Factory calendar: This is the calendar that defines the working days and holidays for the maintenance plan. This parameter is optional for each maintenance cycle in a multiple-counter plan1. If it is not specified, the system uses the factory calendar of the maintenance planning plant.
Therefore, option A (Scheduling period) and option C (Scheduling indicator) are correct, while option B (Start date) and option D (Factory calendar) are not mandatory for a multiple-counter plan.
References:
Multiple-Counter Plans
質問 # 51
How do you set up the visible tiles for a specific user in SAP Fiori Launchpad? Note: There are 2 correct answers to this question
- A. By assigning a portal role with an SAP Fiori catalog
- B. By assigning a PFCG role with an SAP Fiori tile group
- C. By assigning the tiles directly
- D. By assigning a PFCG role with an SAP Fiori catalog
正解:B、D
解説:
The visible tiles for a specific user in SAP Fiori Launchpad are determined by the PFCG roles that are assigned to the user. The PFCG roles contain the SAP Fiori catalogs and tile groups that define the available and visible tiles for the user.
The steps to set up the visible tiles for a specific user are:
Create or use an existing PFCG role in the backend system that contains the SAP Fiori catalogs and tile groups that are relevant for the user. The catalogs and tile groups can be created or copied from the SAP Fiori Launchpad Designer app. The catalogs contain the tiles and target mappings that represent the apps that can be launched from the launchpad. The tile groups are collections of tiles that are displayed on the launchpad home page.
Assign the PFCG role to the user in the backend system. The user can have multiple PFCG roles assigned, depending on their business needs and authorizations.
Log on to the SAP Fiori Launchpad with the user credentials. The user will see the tiles that are assigned to them through the PFCG roles on the launchpad home page. The user can also personalize the launchpad by adding, removing, or rearranging the tiles and groups.
The other options are incorrect because:
Portal roles are not used to assign SAP Fiori catalogs and tile groups. Portal roles are used to assign portal content, such as iViews and pages, to users in the SAP Enterprise Portal.
Assigning the tiles directly to the user is not possible. The tiles are part of the catalogs and tile groups that are assigned to the user through the PFCG roles.
References:
Setting Up Launchpad Content | SAP Help Portal
Creating and Configuring Tiles | SAP Help Portal
SAP Fiori Launchpad Tiles Setup - Go Coding
How to create Fiori Catalog, Group and custom Fiori tiles
質問 # 52
Which default object type do you use to settle a refurbishment order?
- A. The material
- B. The cost center
- C. The fixed asset
- D. The WBS element
正解:C
解説:
Explanation
A refurbishment order is a type of maintenance order that is used to repair or restore a damaged or defective material. The material is usually a fixed asset, such as a machine or a vehicle, that belongs to the company.
The refurbishment order allows you to track the costs and activities involved in the refurbishment process, and to settle the costs to the fixed asset. The fixed asset is the default object type for the settlement of a refurbishment order, but you can also use other object types, such as the cost center or the WBS element, depending on your business requirements. References: Alibaba Cloud Academy - ACP Cloud Computing Certification Course - Chapter 9: Maintenance Management - Section 9.2: Refurbishment Order
質問 # 53
Which objects can you assign to a Maintenance Service Order Item? Note: There are 2 correct answers to this question.
- A. Service Product
- B. Service Work Center
- C. Service Master Record
- D. DIP Profile
正解:A、D
質問 # 54
Where can you see the results of the material availability check for maintenance orders? Note: There are 2 correct answers to this question
- A. In the report Material: Where-Used List
- B. In the list editing (single-level) for maintenance orders
- C. Within a maintenance order
- D. In the material reservation list in inventory management
正解:A、C
質問 # 55
Which activities can the technician perform with the Report and Repair Malfunction SAPUI5 app? Note: There are 2 correct answers to this question
- A. Release
* Print - B. Complete
* Close Report - C. Release
* Start Work - D. Schedule
* Dispatch
正解:B、C
解説:
The Report and Repair Malfunction SAPUI5 app is a Fiori app that allows the technician to easily report that a technical object has a malfunction, plan the required repair work, as well as document and confirm the maintenance work when it's done1. With this app, the technician can perform the following activities:
C . Complete and Close Report. This is true because the technician can provide information about the malfunction and the job, confirm the job, and close the malfunction report. The technician can also attach pictures or descriptions of the damage, as well as a URL to provide further information about the technical object or the damage1.
D . Release and Start Work. This is true because the technician can release the malfunction report and start working on the job assigned to them. The technician can also view the details of the technical object, the history of recent repair work, the required spare parts, and the work centers involved1.
The technician cannot perform the following activities with this app:
A . Schedule and Dispatch. This is false because these activities are performed by the planner or the dispatcher, not the technician. The planner or the dispatcher can use the Resource Scheduling app to schedule and dispatch the maintenance orders and operations2.
B . Release and Print. This is false because the technician can only release the malfunction report, not print it. The technician can use the Repair Malfunctions - My Job List app to view the list of all work items assigned to them and their current status, but not to print them1. Reference: 1: Report and Repair Malfunction 2: Resource Scheduling
質問 # 56
......
更新された公式認定はC-S43-2022認証済みのC-S43-2022問題集でPDF:https://jp.fast2test.com/C-S43-2022-premium-file.html