Who determines the tasks that are required to complete the committed backlog items in a Sprint?
- A. Product owner
- B. Scrum master
- C. Scrum team
- D. Project manager
正解:C
解説:
A is correct because the Scrum team is the one that determines the tasks that are required to complete the committed backlog items in a Sprint. The Scrum team is a self-organizing and cross-functional group of people who work together to deliver a potentially releasable increment of the product at the end of each Sprint. The Scrum team breaks down the user stories into smaller and manageable tasks, and assigns them to the team members based on their skills and availability.
質問 # 28
According to the definition of done, which activity must be completed for each sprint?
- A. Functionality must be released to the business
- B. End-user training must be delivered
- C. Functionality must be tested in the quality system (QAS)
- D. The solution must be built and configured in the development system (DEV)
正解:D
質問 # 29
In which phase should you create a data migration strategy (LO) during a selective data transition?
- A. Explore
- B. Deploy
- C. Discover
- D. Realise
正解:C
質問 # 30
What does the Side-by-Side extensibility option mean?
- A. There are two SAP S/4HANA instances: one for standard code and another for custom developments.
- B. SAP S/4HANA extensions are context-aware and focused on tight integration.
- C. Extensibility is based on the SAP Business Transformation Platform (BTP) and published APIs.
- D. Reporting is transferred to an enterprise data warehoused based on SAP BW/4HANA
正解:C
解説:
C is correct because extensibility based on the SAP Business Technology Platform (BTP) and published APIs is what the Side-by-Side extensibility option means. Side-by-Side extensibility is a type of extensibility that allows customers to create custom applications or extensions that run on a separate platform, such as SAP BTP, and communicate with the SAP S/4HANA system via published APIs. Side-by-Side extensibility enables customers to enhance their SAP S/4HANA solution without modifying the core code or configuration, and to leverage the capabilities of SAP BTP, such as cloud services, development tools, or integration options. Verified :
質問 # 31
How do you achieve frequent checkpoints with the end user in an Agile delivery approach?
There are 2 correct answers to this question.
- A. User acceptance test
- B. Solution demo for sprints
- C. Demo the SAP model company
- D. Solution review for waves
正解:B、D
質問 # 32
What tool provides sizing estimations for the "System Conversion" transition path?
- A. Scope and Effort Analyzer
- B. SAP Readiness Check
- C. SAP Best Practices Explorer
- D. SAP Transformation Navigator
正解:B
質問 # 33
What tool would you use for managing project tasks and Solution Documentation when implementing SAP S/4HANA Cloud, public edition?
- A. SAP Roadmap Viewer
- B. SAP Cloud ALM
- C. SAP Support Portal
- D. SAP Transformation Navigator
正解:B
質問 # 34
Which of the following are used to perform configuration in SAP S/4HANA Cloud, private edition?
- A. Self Service Configuration Uls (SSCUIs)
- B. SAP Central Business Configuration
- C. IMG (Implementation Guide)
- D. SAP Solution Manager
正解:A
質問 # 35
Which of the following tools are considered enablers for digital transformation? Note: There are 3 correct answers to this question.
- A. Software Logistics Toolset
- B. SAP Activate Community
- C. SAP Roadmap Viewer
- D. SAP Best Practices Explorer
- E. SAP Product Availability Matrix
正解:B、C、D
質問 # 36
You are transitioning to SAP S/4HANA.In which phase do you adjust custom code?
- A. Explore
- B. Discover
- C. Deploy
- D. Realize
正解:D
解説:
A is correct because in the Realize phase, you adjust custom code when transitioning to SAP S/4HANA. Custom code is the code that was developed by the customer or a partner to extend or modify the standard SAP functionality. Custom code needs to be adjusted to ensure compatibility and performance with SAP S/4HANA, as well as compliance with the simplification items and coding guidelines. Verified :
質問 # 37
What is the objective of a sprint retrospective meeting?
- A. Review and prioritize the backlog.
- B. Improve the Scrum process.
- C. Define the stakeholder management approach
- D. Provide formal feedback to the Project Manager.
正解:B
解説:
A is correct because improving the Scrum process is the objective of a sprint retrospective meeting. The sprint retrospective meeting is a time for the Scrum Team to reflect on how they worked together in the last sprint and identify ways to enhance their effectiveness and efficiency. Verified :
質問 # 38
In which of the following do you use a work item in Focused Build?
- A. Releases
- B. Sprints
- C. Waves
- D. Epics
正解:B
質問 # 39
Which statement are part of the 5 golden rules for SAP S/4HANA Cloud single tenant edition?
There are 2 correct answers to this question.
- A. Use SAP solution manager 7.2 with focused build
- B. Stick to the security standard of the customer organisation
- C. Foster cloud mindset and adherence to the fit to standard approach
- D. Document deviations from golden rules for transparency and future use in upgrade
正解:C、D
質問 # 40
In which of the following do you use a work item in Focused Build?
- A. Releases
- B. Sprints
- C. Waves
- D. Epics
正解:B
解説:
C is correct because in Focused Build, you use a work item in sprints. A work item is a document that describes a configuration requirement or gap for a scope item. A work item is assigned to a sprint, which is a time-boxed iteration where the work item is implemented and tested by the Scrum team. Verified :
: Managing Work Items
質問 # 41
Which of the following are SAP Activate workstreams?Note: There are 2 correct answers to this question.
- A. Data Migration
- B. Change Management
- C. Extensibility
- D. Project Management
正解:A、D
質問 # 42
Which of the following are capabilities of the test automation tool for SAP S/4HANA Cloud, public edition?Note: There are 2 correct answers to this question.
- A. Supports recording of transaction-based processes
- B. Captures test results with screenshots
- C. Raises test defects automatically
- D. Supports the creation of custom test automates
正解:A、B
質問 # 43
What is the best target deployment option of SAP S/4HANA for the "system conversion" transition path?
- A. SAP S/4HANA
- B. SAP C/4HANA
- C. Hybrid of SAP S/4HANA cloud and SAP S/4HANA
- D. SAP S/4HANA Cloud
正解:B
質問 # 44
Where can you find the integration content? There are 3 correct answers
- A. SAP API business hub
- B. SAP Solution manger
- C. SAP Best practices explorer
- D. SAP cloud appliance library
- E. Cloud integration automatic service
正解:A、C、D
質問 # 45
When conducting an upgrade of an SAP S/4HANA Cloud, public edition three system landscape, in which phase are the Business Roles updated?
- A. Deploy
- B. Explore
- C. Realize
- D. Discover
正解:A
質問 # 46
Which collaboration features are available in the SAP Community? Note: There are 2 correct answers to this question.
- A. Update Key Deliverable wikis
- B. Ask questions
- C. Comment on Key Deliverables
- D. Tweet questions
正解:B、C
解説:
B is correct because asking questions is one of the collaboration features that are available in the SAP Community. The SAP Community allows users to post questions on various topics and get answers from other users, experts, or moderators.
C is correct because commenting on key deliverables is one of the collaboration features that are available in the SAP Community. The SAP Community allows users to comment on the key deliverables that are published by SAP or other users, such as blog posts, articles, videos, podcasts, or webinars. Verified :
: SAP Community Home
質問 # 47
Which task should you include in your procedure while preparing for a fit-to-standard analysis in an SAP Data Warehouse Cloud project?Note: There are 2 correct answers to this question.
- A. Review SAP S/4HANA best practices availability for your country.
- B. Review all the necessary leading practice process diagrams.
- C. Review available SAP S/4HANA accelerators for the Data Management workstream
- D. Review all the necessary Implementation Design Principles (IDPs).
正解:B、D
解説:
B is correct because Implementation Design Principles (IDPs) are documents that provide guidance on how to configure and extend SAP Data Warehouse Cloud to meet customer-specific requirements1.
D is correct because leading practice process diagrams are graphical representations of the business processes that are supported by SAP Data Warehouse Cloud and can be used as a reference for the fit-to-standard analysis2. Verified :