質問 # 67
How many change projects can be active at a time?
- A. 0
- B. 1
- C. 2
- D. 3
正解:A
質問 # 68
What are the responsibilities of the Project Team on level 4 in the picture below? There are 2 answers to this question.
- A. Set business priorities, goals and objectives
- B. Identify and resolve issues and risks
- C. Perform status reporting and communication
- D. Set Project policy, standards and oversight
正解:B、C
質問 # 69
What are some activities the project team will perform in executing project work during the Explore Phase?
- A. Manage Background Jobs, Input and Output
- B. Establish and manage internal and external communications
- C. Manage risks and implement risk response activities
- D. Collect project data and report on progress and performance
- E. Deal with user authorization requests
正解:B、C、D
質問 # 70
Where can you find Integration Content? 3 correct answers
- A. SAP API Business Hub
- B. SAP Solution Manager
- C. SAP Best Practice Explorer
- D. Cloud Integration Automation service
- E. SAP Cloud Appliance Library
正解:A、C、D
質問 # 71
In SAP Activate, what tool is used in the during the Realize phase to make forecasts based on actual data?
- A. Release Plan
- B. Project Plan
- C. Burndown Chart
- D. Product Increment
正解:C
質問 # 72
Via which media does SAP provide ready-to-run systems for SAP S/4HANA deployment? There are 2 answers to this question.
- A. SAP Solution Builder tool
- B. SAP cloud appliance library
- C. SAP App centre
- D. Blu-ray disks
正解:B、D
質問 # 73
In which phase do you run the user acceptance test?
- A. Realize
- B. Deploy
- C. Final Preparation
- D. Build and Test
正解:A
質問 # 74
The hypercare period is part of which phase?
- A. Go-Live
- B. Explore
- C. Realize
- D. Deploy
正解:D
質問 # 75
What tool do you use to configure an SAP Business Suite on-premise solution? Please choose the answer.
- A. ABAP Workbench
- B. Expert Configuration
- C. Configuration Composer
- D. SAP Implementation Guide
正解:D
質問 # 76
What are some of the benefits that apply to SAP Cloud ALM as a cloud product? Note: There are 2 answers to this question.
- A. User management is provided.
- B. The solution is always up to date.
- C. The solution is always available.
- D. Different customer landscapes are all managed by SAP.
正解:B、C
質問 # 77
Working in an Agile approach, what should your planning look like at the beginning of the Realize phase?
- A. User Stories are in Ready state for only the first 2 to 3 sprints.
- B. Timelines of the sprint may differ due to the workload.
- C. Go-Live scope is fixed on the first of January the following year.
- D. Project scope and planning are completed and final.
正解:A
質問 # 78
Which end-to-end turn-key application lifecycle management (ALM) solution can support You in managing requirements and software development for large Agile project.
- A. Requirement management
- B. Focused build
- C. Change request management
- D. Solution manager test suite
正解:B
質問 # 79
In the "new implementation of SAP S/4HANA" transition path, which systems are part of the project system landscape?
There are 2 answers to this question.
- A. P-system
- B. Starter system
- C. QAS
- D. DEV
正解:C、D
質問 # 80
What is the minimum number of quality gates mandated by the SAP Activate methodology?
- A. 0
- B. 1
- C. 2
- D. 3
正解:D
質問 # 81
What do you do during post cutover?
- A. Perform Technical System Test
- B. Conduct Organizational Readiness Check
- C. Setup Operational Support
- D. Perform the Verification Session of the SAP Going Live Check
正解:D
質問 # 82
In what respect is SAP Activate Methodology different from the ASAP Methodology? Please choose the answer.
- A. Leverages iterative incremental build
- B. Supports only new implementations
- C. Supports cloud deployments
- D. Includes Fit/Gap analysis instead of Blueprint
正解:D
質問 # 83
Which new project roles are introduced with the SAP Activate methodology for the Agile delivery approach, compared to waterfall? Note: There are 2 correct answers to this question.
- A. Scrum master
- B. Product owner
- C. Design thinking coach
- D. Integration lead
正解:A、B
質問 # 84
What are the substreams in the Data Management Workstream?
- A. Data aging
- B. Data volume management
- C. Master data management
- D. Data migration
正解:B、C、D
質問 # 85
Where can you check for the current roadmap of SAP Cloud ALM?
- A. SAP ONE Support Launchpad
- B. SAP Support Portal
- C. SAP Help Portal
- D. SAP Community
正解:B
質問 # 86
What are some responsibilities of the Configuration Expert project team role in an SAP S/4HANA Cloud implementation?
- A. Manages interactions with the SAP Service Center
- B. Prepares and leads the Fit-to-Standard analysis process
- C. Serves as the central contact for SAP
- D. Resolution of business process issues
正解:B、D
質問 # 87
What structure level do you see when you access the Roadmap Viewer and chose work stream navigation?
Please choose the correct answer.
- A. Task
- B. Deliverable
- C. Scope Item
- D. Scenario
正解:B
質問 # 88
In which tools can the project team across the SAP Activate Methodology content including accelerators?
There are 2 answers to this question.
- A. SAP Jam
- B. Roadmap Viewer
- C. SAP Service Marketplace
- D. SAP Community Network
正解:A、B
質問 # 89
What are some of the values of SAP Cloud ALM for implementation? Note: There are 3 correct answers to this question.
- A. Comprehensive document repository
- B. Pre-loaded SAP Activate tasks
- C. Central cost and effort management
- D. Accelerated time to market
- E. NO additional cost of product
正解:B、D、E