質問 # 22
In which of the following project phases is it important to plan and schedule data loads followed by load validation activities?
Please choose the correct answer.
Response:
- A. Deploy
- B. Prepare
- C. Explore
- D. Realize
正解:C
質問 # 23
What is the difference between the "new implementation of SAP S/4HANA Cloud" And the "new implementation of SAP S/4HANA transition path?
There are 2 correct answers to this question.
- A. Upgrade of SAP S/4HANA cloud are managed by SAP, and upgrades of SAP S/4HANA are managed by the customer
- B. SAP S/4HANA uses the implementation guide (IMG) and the in-app extensibility option for Configuration and development, L-1 and SAP S/4HANA Cloud uses SSCUs and the side-by-side Extensibility option
- C. There are different roles in the application design and configuration workstream
- D. Different sets of workstreams are used for these transition paths
正解:A、B
質問 # 24
In which phase do you create a prioritized list of user requirements?
Please choose the correct answer.
Response:
- A. Deploy
- B. Prepare
- C. Explore
- D. Realize
正解:C
質問 # 25
What is a Strategy Level 0 (LO) artifact?
Please choose the correct answer.
Response:
- A. Approach document that is developed by a united Project Team (partner + customer)
- B. Optional information that is NOT important for project activities
- C. Project result that is developed solely by the partner
- D. Preliminary strategy developed by the customer to approach the project in a specific work stream
正解:D
質問 # 26
What tool would you use for managing project tasks and solution documentation Who implementing SAP S/4HANA
- A. SAP roadmap viewer
- B. SAP transformation Navigator
- C. Implementation portal for SAP S/4HANA cloud
- D. SAP support marketplace
正解:C
質問 # 27
In which phase should you first run the SAP Readiness Check for SAP S/4HANA in a "Selective Data Transition" transition path, in a System Consolidation scenario that includes conversion from SAP ERP?
Please choose the correct answer.
Response:
- A. Discover
- B. Prepare
- C. Explore
- D. Realize
正解:A
質問 # 28
What does the Content element of SAP Activate provide?
There are 3 correct answers to this question.
Response:
- A. Functional Specifications for WRICEF development
- B. Business Processes Content
- C. Migration Content
- D. Integration Content
- E. End-User guides
正解:B、C、D
質問 # 29
What are some of the key topics covered in the customer team enablement workshops? There are 3 correct answers to this question.
- A. Planning skills
- B. Project sourcing approach
- C. Solution expertise
- D. Technical expertise
- E. Project management
正解:C、D、E
質問 # 30
What are the three pillars of SAP Activate?
There are 3 correct answers to this question.
Response:
- A. SAP Best Practices
- B. SAP Solution Manager
- C. Guided Configuration
- D. SAP S/4HANA in-memory database
- E. SAP Activate Methodology
正解:A、C、E
質問 # 31
How does the provisioning of SAP S/4HANA cloud differ from the setup of SAP S/4HANA Note: There are 2 correct answers to this question There is a Preset phase for Q-system. which is unique for SAP S/4HANA Cloud.
- A. In SAP S/4HANA Cloud, decommissioning/shutdown of the Starter system is initiated automatically after the P-system is requested through the Manage Your Solution app, whereas in an SAP S/4HANA system, the DEV system persists.
- B. To start a Solution Validation workshop, a DEV system is available for SAP S/4HANA, while a Starter system is required for Fit-to-standard for SAP S/4HANA Cloud.
- C. SAP S/4HANA systems take less time to provision than SAP S/4HANA Cloud systems.
正解:A、B
質問 # 32
Which tools does SAP Activate provide to support Guided Configuration?
There are 3 correct answers to this question.
Response:
- A. Solution Builder
- B. Model Company
- C. Self Service Configuration
- D. Expert Configuration
- E. SAP Solution Composer
正解:A、C、D
質問 # 33
Which of the following are part of the 10 SAP Quality Principles?
There are 2 correct answers to this question.
Response:
- A. Achieve production readiness.
- B. Use standard functionality optionally.
- C. Start scoping early.
- D. Plan one phase at a time.
正解:A、C
質問 # 34
Where can you find the Integration Content?
There are 3 correct answers to this question.
Response:
- A. SAP Solution Manager
- B. SAP Cloud Appliance library
- C. Cloud Integration Automation Service
- D. SAP Best Practices Explorer
- E. SAP API Business Hub
正解:C、D、E
質問 # 35
Which accelerator can help you document the detailed design of solution extensions?
Please choose the correct answer.
Response:
- A. Sprint Backlog Template
- B. Product Backlog Template
- C. Change Request Template
- D. RICEF Specification Template
正解:D
質問 # 36
What is the most granular level of the methodology you can view in the SAP roadmap viewer?
- A. Deliverables
- B. Scenario
- C. Phase
- D. Task
正解:D
質問 # 37
Which activity helps the project team add user stories to the product backing?
- A. Planning the user acceptance test
- B. Conducting the solution validation workshop
- C. Preparing a project schedule
- D. Assessing project risks
正解:B
質問 # 38
Which activity helps the Project Team add User Stories to the Product Backlog?
Please choose the correct answer.
Response:
- A. Conducting the Solution Validation workshop
- B. Preparing a Project Schedule
- C. Planning the User Acceptance Test
- D. Assessing Project Risks
正解:A
質問 # 39
Which of the following statements about Scrum is correct?
Please choose the correct answer.
Response:
- A. Scrum Master defines and prioritizes features and gathers requirements.
- B. In Scrum, as best practices, we have three main roles, and three artifacts or three ceremonies.
- C. The three ceremonies are sprint planning, daily scrum, sprint review (retrospective).
- D. In Scrum, the team is Self-organized, define all task necessary for all project life cycle.
正解:C
質問 # 40
......