質問 # 22
In which of the following project phases is it important to plan and schedule data loads followed by load validation activities?
Please choose the correct answer.
Response:

  • A. Deploy
  • B. Prepare
  • C. Explore
  • D. Realize

正解:C


質問 # 23
What is the difference between the "new implementation of SAP S/4HANA Cloud" And the "new implementation of SAP S/4HANA transition path?
There are 2 correct answers to this question.

  • A. Upgrade of SAP S/4HANA cloud are managed by SAP, and upgrades of SAP S/4HANA are managed by the customer
  • B. SAP S/4HANA uses the implementation guide (IMG) and the in-app extensibility option for Configuration and development, L-1 and SAP S/4HANA Cloud uses SSCUs and the side-by-side Extensibility option
  • C. There are different roles in the application design and configuration workstream
  • D. Different sets of workstreams are used for these transition paths

正解:A、B


質問 # 24
In which phase do you create a prioritized list of user requirements?
Please choose the correct answer.
Response:

  • A. Deploy
  • B. Prepare
  • C. Explore
  • D. Realize

正解:C


質問 # 25
What is a Strategy Level 0 (LO) artifact?
Please choose the correct answer.
Response:

  • A. Approach document that is developed by a united Project Team (partner + customer)
  • B. Optional information that is NOT important for project activities
  • C. Project result that is developed solely by the partner
  • D. Preliminary strategy developed by the customer to approach the project in a specific work stream

正解:D


質問 # 26
What tool would you use for managing project tasks and solution documentation Who implementing SAP S/4HANA

  • A. SAP roadmap viewer
  • B. SAP transformation Navigator
  • C. Implementation portal for SAP S/4HANA cloud
  • D. SAP support marketplace

正解:C


質問 # 27
In which phase should you first run the SAP Readiness Check for SAP S/4HANA in a "Selective Data Transition" transition path, in a System Consolidation scenario that includes conversion from SAP ERP?
Please choose the correct answer.
Response:

  • A. Discover
  • B. Prepare
  • C. Explore
  • D. Realize

正解:A


質問 # 28
What does the Content element of SAP Activate provide?
There are 3 correct answers to this question.
Response:

  • A. Functional Specifications for WRICEF development
  • B. Business Processes Content
  • C. Migration Content
  • D. Integration Content
  • E. End-User guides

正解:B、C、D


質問 # 29
What are some of the key topics covered in the customer team enablement workshops? There are 3 correct answers to this question.

  • A. Planning skills
  • B. Project sourcing approach
  • C. Solution expertise
  • D. Technical expertise
  • E. Project management

正解:C、D、E


質問 # 30
What are the three pillars of SAP Activate?
There are 3 correct answers to this question.
Response:

  • A. SAP Best Practices
  • B. SAP Solution Manager
  • C. Guided Configuration
  • D. SAP S/4HANA in-memory database
  • E. SAP Activate Methodology

正解:A、C、E


質問 # 31
How does the provisioning of SAP S/4HANA cloud differ from the setup of SAP S/4HANA Note: There are 2 correct answers to this question There is a Preset phase for Q-system. which is unique for SAP S/4HANA Cloud.

  • A. In SAP S/4HANA Cloud, decommissioning/shutdown of the Starter system is initiated automatically after the P-system is requested through the Manage Your Solution app, whereas in an SAP S/4HANA system, the DEV system persists.
  • B. To start a Solution Validation workshop, a DEV system is available for SAP S/4HANA, while a Starter system is required for Fit-to-standard for SAP S/4HANA Cloud.
  • C. SAP S/4HANA systems take less time to provision than SAP S/4HANA Cloud systems.

正解:A、B


質問 # 32
Which tools does SAP Activate provide to support Guided Configuration?
There are 3 correct answers to this question.
Response:

  • A. Solution Builder
  • B. Model Company
  • C. Self Service Configuration
  • D. Expert Configuration
  • E. SAP Solution Composer

正解:A、C、D


質問 # 33
Which of the following are part of the 10 SAP Quality Principles?
There are 2 correct answers to this question.
Response:

  • A. Achieve production readiness.
  • B. Use standard functionality optionally.
  • C. Start scoping early.
  • D. Plan one phase at a time.

正解:A、C


質問 # 34
Where can you find the Integration Content?
There are 3 correct answers to this question.
Response:

  • A. SAP Solution Manager
  • B. SAP Cloud Appliance library
  • C. Cloud Integration Automation Service
  • D. SAP Best Practices Explorer
  • E. SAP API Business Hub

正解:C、D、E


質問 # 35
Which accelerator can help you document the detailed design of solution extensions?
Please choose the correct answer.
Response:

  • A. Sprint Backlog Template
  • B. Product Backlog Template
  • C. Change Request Template
  • D. RICEF Specification Template

正解:D


質問 # 36
What is the most granular level of the methodology you can view in the SAP roadmap viewer?

  • A. Deliverables
  • B. Scenario
  • C. Phase
  • D. Task

正解:D


質問 # 37
Which activity helps the project team add user stories to the product backing?

  • A. Planning the user acceptance test
  • B. Conducting the solution validation workshop
  • C. Preparing a project schedule
  • D. Assessing project risks

正解:B


質問 # 38
Which activity helps the Project Team add User Stories to the Product Backlog?
Please choose the correct answer.
Response:

  • A. Conducting the Solution Validation workshop
  • B. Preparing a Project Schedule
  • C. Planning the User Acceptance Test
  • D. Assessing Project Risks

正解:A


質問 # 39
Which of the following statements about Scrum is correct?
Please choose the correct answer.
Response:

  • A. Scrum Master defines and prioritizes features and gathers requirements.
  • B. In Scrum, as best practices, we have three main roles, and three artifacts or three ceremonies.
  • C. The three ceremonies are sprint planning, daily scrum, sprint review (retrospective).
  • D. In Scrum, the team is Self-organized, define all task necessary for all project life cycle.

正解:C


質問 # 40
......

最新のC_ACTIVATE13学習ガイド2023年最新の- 提供するのはテストエンジンとPDF:https://jp.fast2test.com/C_ACTIVATE13-premium-file.html

最新版を今すぐ試そうC_ACTIVATE13練習テスト問題解答:https://drive.google.com/open?id=1tsKfjmg6L1HnFXDDPqpQCY_qH7q_azZI


弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

我々の働いている時間: ( GMT 0:00-15:00 )
月曜日から土曜日まで

サポート: 現在連絡 

English Deutsch 繁体中文 한국어