質問 21
Planned orders are scheduled in SNP with just one PDS for a product. How is the duration and end date of the order derived, if you plan in weekly buckets?
Note: There are 2 correct answers to this question.
- A. Usage Decision
- B. Defect Recording
- C. Results Recording
- D. Results History
- E. Control Charts
正解: C,D,E
質問 22
Which statements are true? more than one answers are true.
- A. Specifications are copied from the inspection lot to the inspection plan.
- B. Change master records are identified by the change number.
- C. If you work without a change number, the old values in the task list are overwritten by new values.
- D. Specifications are copied from the inspection plan to the inspection lot.
正解: C,D
質問 23
Which statements are correct? (More than one answer is true.)
- A. Details for the QM specific procurement processes as plant level are determined using the QM control key.
- B. Results recording cannot be carried out after the sample size has been determined.
- C. When the indicator "QM procurement active" is set, quality management in procurement is activated for all plants of a client.
- D. An inspection lot can be created automatically or manually.
正解: A,D
質問 24
Sampling procedures are procedures that determine the sample group for an inspection.
- A. Correct
- B. Incorrect
正解: B
質問 25
In the usage decision transactions, it is standard that quantities for the stock transfer can only be specified in the base unit of measure of the material.
- A. Correct
- B. Incorrect
正解: B
質問 26
When creating a process order , what type of task list is primary used for inspection ? Correct 3
- A. Master recipe
- B. Equipment
- C. Routings
- D. Reference rate routing
正解: A,C,D
質問 27
The maintenance strategy can be time-based or but can not be performance-based.
- A. Correct
- B. Incorrect
正解: B
質問 28
Which statements are correct? Sampling plan dependent on ________. (More than one answer is true.)
- A. Variable
- B. severities/AQL value
- C. Lot size intervals
- D. Inspection
正解: B,C,D
質問 29
An enterprise portal must provide access to information respective of its storage location.
- A. Correct
- B. Incorrect
正解: A
質問 30
Which Status allows you to make a usage decision without using the force inspection competition function for all mandatory characteristic results ?
- A. 0
- B. 1
- C. 2
- D. 3
正解: B
質問 31
If the usage decision has been made for an inspection lot, an additional inspection lot cannot be created for a production version.
- A. Correct
- B. Incorrect
正解: B
質問 32
Details for the QM specific procurement processes at plant lever are determined using the Q control key.
- A. Correct
- B. Incorrect
正解: A
質問 33
You want to print a certificate for an outbound delivery, at which level is a certificate printed?
- A. Material level
- B. Delivery header level
- C. Shipping point level
- D. Delivery Item level
正解: D
質問 34
If there are inspection specifications from both the variant configuration and the task list or material specification that are relevant for the characteristic, the specifications from the variant configuration take precedence over those from the material specification.
- A. Correct
- B. Incorrect
正解: A
質問 35
An activity consists of the following elements: (More than one answers are true)
- A. Processing deadlines
- B. Processing quality factor
- C. Short test
- D. Catalog entry
- E. Long text
正解: A,B,E
質問 36
You can use the action box functions to process the wrong delivery.
- A. Correct
- B. Incorrect
正解: A
質問 37
Inspection results recording must always be carried out for each in section lot
- A. Correct
- B. Incorrect
正解: B
質問 38
Which statements are correct? (More than one answers are true)
- A. A document may be assigned to every audit data object.
- B. Several question lists can be assigned to one audit.
- C. None
- D. A valuation may be in recorded for every question in the question list.
正解: A,D
質問 39
When you post a good receipt, where does the system check the current inspection stage for a material/vendor combination for upcoming inspection.
- A. Quality level
- B. Sampling scheme
- C. Inspection Plan
- D. Characteristic
正解: A
質問 40
QM cannot be used to set a payment block for the goods receipt invoice.
- A. Correct
- B. Incorrect
正解: B
質問 41
You can assign follow-up actions to the codes in the code groups of the task catalog.
- A. Correct
- B. Incorrect
正解: A
解説:
Explanation
質問 42
You can create a maintenance plan with or without a maintenance strategy.
- A. Correct
- B. Incorrect
正解: A
質問 43
......
正真正銘で最適な資料C-TPLM40-65オンライン練習試験:https://jp.fast2test.com/C-TPLM40-65-premium-file.html