質問 90
Which of the following statements about lines of authority and reporting are true?
1. The Project Manager has day-to-day control for a management stage within the limits laid down by the Project Board.
2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager.
- A. Neither 1 or 2 are true
- B. Only 1 is true
- C. Only 2 is true
- D. Both 1 and 2 are true
正解: D
解説:
Section: Volume B
質問 91
What takes place during the Closing a Project process?
- A. An End Stage Report is prepared for the final stage
- B. The post-project benefits reviews are performed
- C. The project closure notification is reviewed and approved
- D. Ownership of the project's products is transferred to the customer
正解: D
質問 92
Which product records any project outcomes perceived as negative by stakeholders?
- A. Project Plan
- B. Business Case
- C. Communication Management Strategy
- D. Project Product Description
正解: B
質問 93
Which describes a risk event?
- A. The area of uncertainty in terms of the threat or opportunity
- B. The sequence of events and actions that will be put in place if a risk occurs
- C. The achievement of a milestone on the project plan
- D. The derivation or sources of a potential risk to the project
正解: A
解説:
Explanation
Reference http://prince2.wiki/Risk
質問 94
Which of the following refers to the actions identified to bring a situation to a level where exposure to a risk is acceptable?
- A. Risk category
- B. Risk status
- C. Risk response
- D. Risk description
正解: C
質問 95
Which are purposes of the quality theme?
1. To implement continuous improvement during the project
2. To establish how the project will ensure that products created will be acceptable to key stakeholders
3. To ensure that the project is desirable and achievable
4. To identify, assess and control uncertainty
- A. 2 and 3
- B. 3 and 4
- C. 1 and 2
- D. 1 and 4
正解: A
解説:
Section: Volume B
Explanation/Reference:
Reference https://www.whatisprince2.net/prince2-theme-quality.php
質問 96
Which is an objective of the Directing a Project process?
- A. Ensure corporate or programme management has an interface to the project
- B. Define how risks, issues and changes will be managed
- C. Review and approve a project mandate
- D. Obtain approval for completed products
正解: A
質問 97
What should influence the Project Board's decision whether to delegate its Project Assurance responsibilities?
- A. The need to involve key stakeholders on the project management team
- B. Having insufficient time to perform the role
- C. The preference of the Project Manager
- D. Having insufficient authority to perform the role
正解: B
質問 98
Which is an objective of the Managing Product Delivery process?
- A. Sign-off completed Work Packages
- B. Ensure that work on products is authorized and agreed with the team
- C. Report progress to the Project Board
- D. Ensure the Business Case is kept under review
正解: B
質問 99
Which product is used by the Project Manager to authorize work?
- A. Product Description
- B. Team Plan
- C. Stage Plan
- D. Work Package
正解: D
質問 100
What is an advantage of applying the 'manage by stages' principle?
- A. The PRINCE2 method can be used for any type of project
- B. The project has decision points so that it does not run on in an uncontrolled manner
- C. The project delivers benefits that are aligned with strategic objectives
- D. Tolerances can be defined for delegated authority
正解: B
質問 101
Which role is responsible for appointing the senior user in a project that is independent from a program?
- A. Project assurance
- B. Corporate, program management or the customer
- C. The executive
- D. The project manager
正解: B
解説:
Reference https://www.prince2primer.com/prince2-roles-and-responsibilities/
質問 102
Identify the missing word in the following sentence relating to one of the principles:
A PRINCE2 project should have [?] defined for each project objective.
- A. principles
- B. themes
- C. processes
- D. tolerances
正解: D
解説:
Section: Volume B
Explanation
質問 103
How many tasks does the product-based planning technique describe?
- A. Two
- B. Three
- C. Four
- D. One
正解: C
質問 104
What action is taken as part of the 'controlling a stage' process?
1. Create an exception plan
2. Authorize work to be done
3. Take corrective action
4. Obtain approvals for completed products
- A. 2 and 3
- B. 3 and 4
- C. 1 and 2
- D. 1 and 4
正解: A
解説:
Reference https://www.greycampus.com/opencampus/prince-2-foundation/introduction-on-controlling-a-stage-process-in-prince2
質問 105
Which process ensures focus on the delivery of a stage's products and avoids uncontrolled change?
- A. Controlling a stage
- B. Directing a project
- C. Managing a stage boundary
- D. Starting up a project
正解: A
解説:
Section: Volume B
Explanation/Reference:
Reference https://www.greycampus.com/opencampus/prince-2-foundation/introduction-on-controlling-a-stage- process-in-prince2
質問 106
......
PRINCE2Foundation別格な問題集で最上級の成績にさせるPRINCE2Foundation問題:https://jp.fast2test.com/PRINCE2Foundation-premium-file.html
手に入れよう!最新PRINCE2Foundation認定の有効な試験問題集解答:https://drive.google.com/open?id=18lZZ-6h-TPoD9eM1tznx2jZ2Wxfahu0I