C_TS413_2020試験問題集、C_TS413_2020練習テスト問題 [Q32-Q55]

Share

C_TS413_2020試験問題集、C_TS413_2020練習テスト問題

PDF問題(2022年最新)実際のSAP C_TS413_2020試験問題

質問 32
Which of the following is a prerequisite for external refurbishment?

  • A. Define the order type for external refurbishment.
  • B. Select the material group for externally refurbished materials.
  • C. Create the purchasing info record for the external provider.
  • D. Activate the subcontracting indicator in an external activity.

正解: D

 

質問 33
You want to have several plan dates calculated in a maintenance plan. Which scheduling parameter do you use?

  • A. Offset
  • B. Scheduling indicator
  • C. Scheduling period
  • D. Call horizon

正解: C

 

質問 34
You want to set up a scenario for regular maintenance. The first event should take place after 1 year; after that, it is a regular cycle of 6 months. Which parameter do you have to use to map this in the system?

  • A. Maintenance package offset
  • B. Scheduling indicator
  • C. Shift factor
  • D. Maintenance plan category

正解: A

 

質問 35
Which functionalities are available in the SAP Asset Manager for a maintenance worker? Note: There are
2 correct Answers to this question.

  • A. Change BOM. Create a work order on the ESRI map
  • B. Schedule resources. Change task list
  • C. Display maps. Display and maintain technical objects
  • D. Confirm time sheets. Attach documents

正解: C,D

 

質問 36
Which statements about the structure indicator are correct? Note: There are 2 correct Answers to this question.

  • A. It defines which data is transferred to the lower levels of the hierarchy.
  • B. It defines the allowed characters for a functional location.
  • C. It can have a maximum length of 50 characters.
  • D. It defines hierarchy levels of the functional location structure.

正解: B,D

 

質問 37
In which cases are projects (PS) used in the area of SAP S/4HANA Asset Management? Note: There are 2 correct Answers to this question.

  • A. Condition-based maintenance
  • B. Investments
  • C. External refurbishment
  • D. Shutdowns and overhaul

正解: B,D

 

質問 38
You create a revision for a Maintenance Event Builder (MEB) scenario. Which of the following statements are correct? Note: There are 2 correct Answers to this question.

  • A. You must assign maintenance notifications to the revision.
  • B. You must use hierarchical task lists for the MEB scenario.
  • C. You can assign a network to a revision.
  • D. You can assign a hierarchical task list to the revision.

正解: A,D

 

質問 39
Where can the maintenance planner perform a material availability check? Note: There are 2 correct Answers to this question.

  • A. Via the SAP Fiori app "Maintenance Scheduling Board"
  • B. Via the multi-level order list (SAP GUI)
  • C. Within the SAP Fiori-based background job
  • D. Via the SAP Fiori app "Manage Maintenance Order List"

正解: B,C

 

質問 40
Which statement is correct when planning maintenance work that is to be carried out by an external company?

  • A. In the control key assigned to the order operation, the "Service" indicator must always be activated.
  • B. If you assign a control key with indicator "Service" for an external service, you have to enter the actual values via the service entry sheet.
  • C. If you assign a control key for an external order operation, the actual values must always be entered as a goods receipt in the system.
  • D. A service master record must always be assigned to the external order operation.

正解: B

 

質問 41
In which component do you have to perform most of the configuration to set up SAP Asset Manager?

  • A. SAP ERP on HANA
  • B. SAP BTP (formerly Cloud Platform)
  • C. SAP Mobile Platform
  • D. SAP S/4HANA

正解: B

 

質問 42
Which of the following statements about orders with operation account assignment (OAA) are correct?
Note: There are 3 correct Answers to this question.

  • A. The settlement rule is maintained on the header level.
  • B. A technical object must be assigned to an order operation.
  • C. Overall costs are dynamically summed up on the header level.
  • D. Purchase requisitions have the operation as account assignment.
  • E. Costs are stored only for the operation object.

正解: B,C,E

 

質問 43
Which parameter in a maintenance strategy do you use to set the start/end date of the maintenance order?

  • A. Package offset
  • B. Scheduling type
  • C. Initial/subsequent buffer
  • D. Call horizon

正解: C

 

質問 44
Which operations can the responsible person perform after a maintenance order is technically completed? Note: There are 3 correct Answers to this question.

  • A. Lock or unlock the order.
  • B. Change the settlement rule.
  • C. Update the estimated costs.
  • D. Create an invoice receipt for delivered materials.
  • E. Change the planned costs.

正解: A,B,D

 

質問 45
Which statements related to the creation of maintenance orders are correct? Note: There are 2 correct Answers to this question.

  • A. The long text of the reference notification can be automatically copied as the long text of the order.
  • B. The document within the document management system can be assigned only at operational level.
  • C. The assignment of the header notification to an order CANNOT be deleted.
  • D. When an order is created based on a single notification, this notification becomes the header notification.

正解: A,D

 

質問 46
You require stock material to carry out maintenance tasks. Which of the following statements regarding material planning in the maintenance order are correct? Note: There are 3 correct Answers to this question.

  • A. Material can be assigned at the order operation level.
  • B. A control key for internal workforce is required when assigning stock material to an order operation.
  • C. A goods receipt can be entered for a technically completed maintenance order.
  • D. The pick list for materials can be printed before order release.
  • E. Material can be assigned at the order header level.

正解: A,B,C

 

質問 47
How do you map a counter replacement in SAP S/4HANA Asset Management?

  • A. Deactivate the current counter and create a new counter.
  • B. Create a new measurement document marked as a counter replacement.
  • C. Create a new measurement document and assign a valuation code for counter replacement.
  • D. Replace the defective piece of equipment to which a counter is assigned.

正解: B

 

質問 48
Which SAP UI technology is used for the Report and Repair Malfunction app?

  • A. SAP GUI for Windows
  • B. Web Dynpro
  • C. SAPUI5
  • D. SAP GUI for HTML

正解: B

 

質問 49
You want to create a new functional location. Which configuration steps are required? Note: There are 2 correct Answers to this question.

  • A. Define the number range for the functional location category.
  • B. Define the reference functional location.
  • C. Define the functional location category.
  • D. Define the structure indicator.

正解: C,D

 

質問 50
You need to create a new functional location. Which actions can you perform with the SAP Fiori app
"Create Technical Object"? Note: There are 3 correct Answers to this question.

  • A. Assign a subordinate piece of equipment.
  • B. Edit classification data and characteristics.
  • C. Assign documents.
  • D. Change a reference location.
  • E. Create a task list for functional location.

正解: B,C,D

 

質問 51
In which maintenance object can you use an activity type? Note: There are 2 correct Answers to this question.

  • A. Maintenance order header
  • B. Notification activity
  • C. Maintenance order operation
  • D. Work center

正解: C,D

 

質問 52
Which steps are available for the maintenance technician when using the Report Malfunction tile? Note:
There are 3 correct Answers to this question.

  • A. View details of the technical object by navigating to the Asset Viewer.
  • B. Input estimated costs for repair malfunction.
  • C. Select and print the maintenance order shop papers.
  • D. Display the current location of the technical object.
  • E. Add a URL to provide further information.

正解: A,D,E

 

質問 53
Which scheduling parameters are used in a multiple-counter plan? Note: There are 2 correct Answers to this question.

  • A. Factory calendar
  • B. Scheduling indicator
  • C. Start date
  • D. Scheduling period

正解: C,D

 

質問 54
Which of the following statements are correct regarding a cross-plant planning scenario?

  • A. Multiple planning plants are assigned to a maintenance plant (m:1).
  • B. It is not supported in SAP S/4HANA.
  • C. Multiple maintenance plants are assigned to a planning plant (n:1).
  • D. An n:m relationship between maintenance plant and planning plant can be maintained in SAP S/4HANA.

正解: A

 

質問 55
......

更新された2022年03月合格させるC_TS413_2020試験リアル練習テスト問題:https://jp.fast2test.com/C_TS413_2020-premium-file.html

問題集返金保証付きのC_TS413_2020問題集には90%オフ:https://drive.google.com/open?id=1iCG63mVyjFNxszYFcS6mibiifbrf1mmK


弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

我々の働いている時間: ( GMT 0:00-15:00 )
月曜日から土曜日まで

サポート: 現在連絡 

English Deutsch 繁体中文 한국어