C_S4CAM_2308試験問題集合格させるのは2024年最新の認証済み試験問題
C_S4CAM_2308試験問題でリアルに更新された問題PDF
質問 # 64
Your customer requires a regular maintenance for a printer with the following maintenance steps expected:
* Inspection after 1.000 copies
* Exchanging spare parts after 5.000 copies What is required to set up this process?
Note: There are 2 correct answers to this question.
- A. Maintenance strategy
- B. User status profile
- C. Cycle set
- D. Task list
正解:A、D
解説:
According to the SAP document "Asset Management in SAP S/4HANA Cloud" , a task list is required to define the maintenance steps for a printer, and a maintenance strategy is required to define the cycle length and counter-based scheduling. A user status profile is not required for this process. A cycle set is not a term used in the SAP document.
質問 # 65
You define a maintenance strategy with two maintenance packages. Which parameter influences the selection of both maintenance packages, if they are due at the same time?
- A. Cycle length
- B. Hierarchy
- C. Offset
- D. Initial buffer
正解:B
質問 # 66
What tasks can you perform from the Display Technical Users app?
- A. Change the username and password of a print user
- B. Lock and unlock the initial user account that is delivered with the new system
- C. Upload a certificate for a communication user
- D. Assign and unassign users to user groups
正解:B、D
質問 # 67
Which of the following are outcomes of the Fit-to-Standard workshop? Note: There are 3 correct answers to this question.
- A. Expert configuration definition
- B. Identification of source code changes
- C. Extensibility solutions to close gaps
- D. Finalized scope and integration requirements
- E. Solution impact on business processes
正解:C、D、E
解説:
According to the SAP S/4HANA Cloud, public edition Learning Journey1, some of the outcomes of the Fit-to-Standard workshop are finalized scope and integration requirements, expert configuration definition, and extensibility solutions to close gaps. The Fit-to-Standard workshop is a process that compares the customer's business requirements with the standard processes and functionalities provided by SAP S/4HANA Cloud. The outcomes of the workshop are a finalized scope that defines the selected business processes and scenarios, integration requirements that define the data and system connections needed, expert configuration definition that defines the settings and parameters for the selected scope, and extensibility solutions that define the additional functionalities or customizations required to close any gaps.
質問 # 68
How does an implementation consultant support customer experts during Fit-to-Standard workshops?
- A. Determine set up instructions for customer-driven integrations
- B. Demonstrate SAP Best Practices in the Starter system
- C. Conduct end-user training on active scope items
- D. Highligt areas that require configuration or extensibility decisions
正解:B、D
質問 # 69
When scheduling the maintenance plan, which call objects can be generated automatically?
Note: There are 2 correct answers to this question.
- A. Task lists
- B. Measurement documents
- C. Notifications
- D. Service entry sheets
正解:C、D
質問 # 70
How does an implementation consultant support customer experts during Fit-to-Standard workshops?
- A. Determine set up instructions for customer-driven integrations
- B. Demonstrate SAP Best Practices in the Starter system
- C. Conduct end-user training on active scope items
- D. Highligt areas that require configuration or extensibility decisions
正解:B、D
解説:
According to the SAP document "SAP Activate Methodology for SAP S/4HANA Cloud" , an implementation consultant supports customer experts during Fit-to-Standard workshops by highlighting areas that require configuration or extensibility decisions, and demonstrating SAP Best Practices in the Starter system. Conducting end-user training and determining set up instructions for customer-driven integrations are not part of the Fit-to-Standard workshops.
質問 # 71
How is the productive system configured?
Note: There are 2 correct answers to this question.
- A. Via the Cloud Application Lifecycle Management (CALM) Implementation Portal
- B. Through the Solution Documentation component of the SAP Solution Manager
- C. Through transports from the quality system
- D. Through Central Business Configuration (CBC) in SAP Business Technology Platform
正解:C、D
質問 # 72
You want to migrate asset management business objects to SAP S/4HANA cloud. Which business role must be assigned to your user?
- A. Administrator
- B. Transportation Manager
- C. Maintenance Planner
- D. Maintenance Supervisor
正解:C
質問 # 73
Which steps are required for data load preparation? There are 3 correct answers to this question.
- A. Design programs or reports required to extract data and initiate data cleansing
- B. Perform full data load to determine the required loading times
- C. Determine if public or private cloud is required for data migration
- D. Determine data requirements based on scenario reviews
- E. Review data load templates and determine data mapping
正解:A、D、E
解説:
According to the Asset Management in SAP S/4HANA Cloud, public edition Learning Journey2, some steps that are required for data load preparation are: determine data requirements based on scenario reviews; design programs or reports required to extract data and initiate data cleansing; review data load templates and determine data mapping. Data requirements are specifications that define what data is needed for each scenario and migration object. Data extraction and cleansing are processes that involve extracting data from legacy systems or files and removing errors or inconsistencies. Data load templates and mapping are tools that help you transfer data from source to target systems using predefined formats and rules.
質問 # 74
You are using a single cycle plan with a cycle length of 28 days. You want to schedule the call dates one week before the planned dates. Which settings can you use to achieve this? Note: There are 2 correct answers to this question.
- A. Call horizon = 75%
- B. Call horizon = 25%
- C. Call horizon = 7 days
- D. Call horizon = 21 days
正解:A、C
解説:
According to the SAP document "Asset Management in SAP S/4HANA Cloud" , the call horizon can be defined either as a percentage or as a number of days. A call horizon of 75% means that the call date is 75% of the cycle length before the planned date. A call horizon of 7 days means that the call date is 7 days before the planned date. A call horizon of 21 days or 25% would not achieve the desired result.
質問 # 75
You are assigned to the role of a Maintenance Planner - Resource Scheduling. What actions can you perform using the SAP Fiori app Manage Work Center Utilization? Note: There are 2 correct answers to this question.
- A. Assign production resource tools to maintenance order operations.
- B. View a list of maintenance order operations in your work centers.
- C. Change the control key of maintenance order operations.
- D. Cancel the dispatch of order operations or suboperations.
正解:B、D
解説:
The role of a Maintenance Planner - Resource Scheduling enables you to perform the following actions using the SAP Fiori app Manage Work Center Utilization:
View a list of maintenance order operations in your work centers. This allows you to see the planned start and end dates, duration, status, priority, and assigned resources of each operation.
Cancel the dispatch of order operations or suboperations. This allows you to remove the assignment of resources or work centers from an operation or suboperation and return it to the pool of unassigned operations. Reference: SAP Help Portal - Manage Work Center Utilization
質問 # 76
As a technician, you need to generate a work order with a notification. What app do you use?
- A. Manage orders and Notifications in Information Center
- B. Report Malfunction
- C. Request Maintenance
- D. Manage Notification List
正解:B
解説:
According to the SAP S/4HANA Cloud, public edition Asset Management Learning Journey1, as a technician, you can use the Report Malfunction app to generate a work order with a notification. The Report Malfunction app allows you to create and process malfunction reports for assets or equipment. A malfunction report is a document that provides more details about the cause and effect of an issue or problem with an asset or equipment. A work order is a document that contains the information and activities required for performing maintenance work on an asset or equipment. A notification is a document that describes an issue or problem with an asset or equipment.
質問 # 77
You are assigned to the role of a Maintenance Planner - Resource Scheduling. What actions can you perform using the SAP Fiori app Manage Work Center Utilization? Note: There are 2 correct answers to this question.
- A. Assign production resource tools to maintenance order operations.
- B. View a list of maintenance order operations in your work centers.
- C. Change the control key of maintenance order operations.
- D. Cancel the dispatch of order operations or suboperations.
正解:B、D
質問 # 78
In a preventive maintenance process, a maintenance planner and a maintenance technician are involved. Which process steps are part of the maintenance planner's tasks? Note: There are 3 correct answers to this question.
- A. Confirm the preventive maintenance order.
- B. Technically complete the preventive maintenance order.
- C. Release the preventive maintenance order.
- D. Create the maintenance plan.
- E. Print the job card.
正解:B、C、D
質問 # 79
What are characteristics of the SAP S/4 HANA Migration Cockpit?
- A. Extensibility using the Legacy System Migration Workbench (LSMW)
- B. Combining the staging and file approaches into one migration project
- C. Mapping source values to SAP S/4 HANA target values
- D. Guidance and simulation of the migration process
正解:B、D
質問 # 80
How is the productive system configured?
Note: There are 2 correct answers to this question.
- A. Via the Cloud Application Lifecycle Management (CALM) Implementation Portal
- B. Through the Solution Documentation component of the SAP Solution Manager
- C. Through transports from the quality system
- D. Through Central Business Configuration (CBC) in SAP Business Technology Platform
正解:C、D
解説:
The productive system is configured through transports from the quality system and through Central Business Configuration (CBC) in SAP Business Technology Platform. Transports are used to transfer the configuration settings from the quality system to the productive system. CBC is used to configure additional settings that are specific to the productive system, such as company code, plant, sales organization, etc. Reference: SAP Help Portal - Configuring Your Productive System
質問 # 81
How are business roles, business catalogs and SAP Fiori apps mapped to each other?
- A. A business role is mapped to a business catalog that is mapped to an SAP Fiori app
- B. An SAP Fiori app is mapped to a business catalog that is mapped to a business role
- C. An SAP Fiori app is mapped to a business role that is mapped to a business catalog
- D. A business role is mapped to an SAP Fiori app that is mapped to a business catalog
正解:B
質問 # 82
Which of the following features apply to the new scope items (4HH, 4HL, 4VT and 4WM)? Note:
There are 2 correct answers to this question.
- A. An extended concept for system status management
- B. The scope items released before the 2011-release will expire by December 2025
- C. Introduction of process phases
- D. An enhanced concept for user status management
正解:C、D
質問 # 83
Which process steps are part of the corrective maintenance (BH1) process? Note: There are 3 correct answers to this question.
- A. Approve the maintenance order
- B. Confirm the maintenance order
- C. Show the cost on maintenance orders
- D. Change the maintenance request into a malfunction report
- E. Repair malfunction
正解:B、C、D
解説:
According to the SAP S/4HANA Cloud, public edition Learning Journey1, some process steps that are part of the corrective maintenance (BH1) process are: change the maintenance request into a malfunction report; show the cost on maintenance orders; confirm the maintenance order. A maintenance request is a document that describes an issue or problem with an asset or equipment. A malfunction report is a document that provides more details about the cause and effect of an issue or problem with an asset or equipment. A maintenance order is a document that contains all the information and activities required for performing maintenance work on an asset or equipment. Showing the cost on maintenance orders allows you to view and analyze the planned and actual costs for maintenance work. Confirming the maintenance order allows you to record the completion and results of maintenance work.
質問 # 84
How can business users create new analytics content? Note: There are 3 correct answers to this question.
- A. Change underlying database tables of standard data sources
- B. Create additional key figures in existing data sources
- C. Change existing data sources by adding filters
- D. Create new data sources via joins of standard data sources
- E. Combine current and historical data
正解:B、C、D
質問 # 85
You are using Self-Service Configuration User Interfaces (SSCUIs) to configure a preventive maintenance process for SAP S/4HANA Cloud. Which of the following can you define using SSCUIs? Note: There are 2 correct answers to this question.
- A. Plant sections
- B. Planner groups for task lists
- C. Maintenance plan categories
- D. Sort fields for maintenance plans
正解:B、D
解説:
According to the SAP S/4HANA Cloud, public edition Asset Management Learning Journey1, you can use Self-Service Configuration User Interfaces (SSCUIs) to configure planner groups for task lists or sort fields for maintenance plans in a preventive maintenance process for SAP S/4HANA Cloud. SSCUIs are tools that allow you to customize and adapt standard processes and functionalities in SAP S/4HANA Cloud according to your business needs. Planner groups for task lists are data that group together maintenance planners who are responsible for planning and scheduling maintenance work. Sort fields for maintenance plans are data that define how maintenance plans are sorted in lists or reports.
質問 # 86
In a preventive maintenance process, a maintenance planner and a maintenance technician are involved. Which process steps are part of the maintenance planner's tasks? Note: There are 3 correct answers to this question.
- A. Confirm the preventive maintenance order.
- B. Technically complete the preventive maintenance order.
- C. Release the preventive maintenance order.
- D. Create the maintenance plan.
- E. Print the job card.
正解:B、C、D
解説:
The process steps that are part of the maintenance planner's tasks in a preventive maintenance process are:
Create the maintenance plan. This is the step where the maintenance planner defines the technical object, the maintenance strategy, the maintenance cycle, and the scheduling parameters for the preventive maintenance process.
Release the preventive maintenance order. This is the step where the maintenance planner releases the order that is generated from the maintenance plan according to the schedule. Releasing the order means that it is ready for execution and confirmation.
Technically complete the preventive maintenance order. This is the step where the maintenance planner sets the status of the order to technically completed after all the operations and suboperations have been confirmed. Technically completing the order means that no further work is required and that it can be settled and archived. Reference: [SAP Help Portal - Preventive Maintenance Process]
質問 # 87
Which of the following statements are correct for a Minor Work Notification? Note: There are 3 correct answers to this question.
- A. A work order is not required for such notifications.
- B. Minor work Notification needs separate approval process.
- C. Work Orders are automatically generated for minor work notifications.
- D. Minor Work notification are accepted as soon as these are submitted.
- E. You can record the malfunction details for such notifications.
正解:A、D、E
解説:
According to the SAP S/4HANA Cloud, public edition Learning Journey1, some of the statements that are correct for a Minor Work Notification are: minor work notifications are accepted as soon as these are submitted; you can record malfunction details for such notifications; a work order is not required for such notifications. A minor work notification is a type of notification that describes an issue or problem with an asset or equipment that can be resolved quickly without requiring a work order or approval. A minor work notification is automatically accepted by the system when it is created by a user. You can also record malfunction details such as cause, effect, or damage for such notifications. A work order is a document that contains all the information and activities required for performing maintenance work on an asset or equipment. A work order is not needed for minor work notifications because they can be completed by simple actions such as replacing a part or adjusting a setting.
質問 # 88
What can you use the Query Browser app to do? Note: There are 2 correct answers to this question.
- A. Create your own tags for CDS views
- B. Create and publish a query
- C. Modify an SAP-created analytical query
- D. View authorized published queries
正解:A、D
質問 # 89
......
合格させる保証付き無料クイズ2024年最新の実際に出ると確認されたSAP:https://jp.fast2test.com/C_S4CAM_2308-premium-file.html