質問 # 18
Procurement Knowledge
When is the Notice period visible?
- A. When the contract is published
- B. When there is an agreement date
- C. When there is an expiration role
- D. When there is an effective date
正解:C
質問 # 19
Contract Requests and Contract Workspaces
Why would your customer use a contract request in SAP Ariba Contracts? O To link the pricing from a sourcing event to the contract workspace
- A. To allow external users to work on the contract
- B. To link the pricing from a sourcing event to the contract workspace
- C. To generate a contract approval flow
- D. To allow users, who do not have the permission to create Contract Workspaces, to create Contract Requests instead
正解:D
質問 # 20
Integration
Which of the following documents and designed to capture contract-line item pricing within the SAP Ariba suite of solutions?
Note: There are 3 correct answers to this question
- A. Contract attributes
- B. Main agreement
- C. Contract terms
- D. Contract compliance request
- E. Contract line items
正解:C、D、E
質問 # 21
SAP Ariba Contracts Configuration
Which tabs are available in a Team Member Rules file?
Note: There are 2 correct answers to this question
- A. Team
- B. Field names
- C. Team Member Rules
- D. Users
正解:B、C
質問 # 22
Contract Requests and Contract Workspaces
When reviewing a template in SAP Ariba Contracts, you notice that you are unable to edit. What conditions must be met before you can edit?
Note: There are 2 correct answers to this question
- A. You must manage changes by importing a new version of the template
- B. You must put the template in a Draft state by creating a new version
- C. You must be a member of the Project Owner group on the Team tab of the template
- D. Your administrator must update the Access Control field to include your user account
正解:B、C
質問 # 23
SAP Ariba Contracts Configuration
Which amendment type do you use to change the main agreement?
- A. Renewal amendment
- B. Administrative amendment
- C. Termination amendment
- D. Amendment amendment
正解:D
質問 # 24
Contract Requests and Contract Workspaces
How do you use the Process Status field in a contract workspace or contract request?
Note: There are 2 correct answers to this question
- A. To generate a follow-on task
- B. To indicate task progress
- C. To show users a contract workspace placeholder after contract request approval
- D. As a milestone in tasks tab
正解:B、D
質問 # 25
Contract Authoring
How are multiple causes added to the Clause Library?
- A. Upload the Microsoft Word document containing multiple clauses in a contract workspace and use the
"Publish to Clause Library" option - B. Use the document upload feature in a contract workspace to upload a Microsoft Word document containing multiple clauses
- C. Use the upload feature in the Clause Library to upload a Microsoft Word document containing multiple clauses
- D. Upload the Microsoft Word document containing multiple clauses in a template and use the V U
"Publish to Clause Library" option
正解:D
質問 # 26
SAP Ariba Contracts Configuration
Which actions apply to contract negotiations in SAP Ariba?
Note: There are 2 correct answers to this question
- A. The supplier can modify a received contract document
- B. The project owner can launch only one round of a negotiation task
- C. The initial message must be entered before sending the task
- D. The project owner cannot add observers to a negotiation task
正解:A、C
質問 # 27
Deployment Methodology
Which of the following contract name formats would be acceptable within the zip file that is used to import legacy contracts?
- A. Waste Management Services DD/MM/YYYY-DD/MM/YYYY
- B. Waste Management Services - Jerry's Cleaners
- C. Waste_Management_Services_DDMMYYYY-DDMMYYYY
- D. Waste Management Services (DDMMYYYY-DDMMYYYY)
正解:C
質問 # 28
Integration
Which of the following documents is created in SAP ERP when exporting line-item details from a contract workspace in SAP Ariba Contracts through the Cloud Integration Gateway?
- A. Purchase requisition
- B. Outline agreement
- C. Shopping cart
- D. Purchase order
正解:D
質問 # 29
Contract Requests and Contract Workspaces
Which types of contract requests are provided in SAP Ariba?
Note: There are 2 correct answers to this question
- A. Contract Request (External)
- B. Contract Request (Procurement)
- C. Contract Request (Sales)
- D. Contract Request (Internal)
正解:B、C
質問 # 30
Integration
Which of the following sources can provide line items to use in a Contract Line Items document?
Note: There are 2 correct answers to this question
- A. Clause library
- B. CIF catalog
- C. Material master
- D. Sourcing library
正解:C、D
質問 # 31
Search and Reporting
Where can reports be saved to share with other users?
Note: There are 2 correct answers to this question
- A. Public Reports
- B. Prepackaged Reports
- C. Personal Workspace
- D. Knowledge Projects
正解:A、D
質問 # 32
Contract Authoring
Which clause type indicates that a change was made in a clause in a Microsoft Word document and uploaded back into the system?
- A. Library
- B. Ad Hoc
- C. Nonstandard
- D. d-Hoc Library
正解:B
質問 # 33
......