
[2026年05月]更新のMedical Professional CCM公式認定ガイドPDF
試験CCM Certified Case Manager Certification Exam (CCM)
質問 # 59
When is the Employer obliged to return the Performance Security (PS) under the FIDIC Red Book (edition
1999)?
- A. Within 21 days after the issuance of the Taking-Over Certificate.
- B. Without undue delay after the issuance of the Performance Certificate.
- C. Without undue delay after the issuance of the Taking-Over Certificate.
- D. Within 21 days after the issuance of the Performance Certificate.
正解:D
解説:
Comprehensive and Detailed Explanation:
Under FIDIC Red Book 1999, the Performance Security (or Performance Guarantee) is held to ensure the Contractor's performance during the defects liability period. The security is typically released only after the Employer issues the Performance Certificate, which confirms the completion of defects liability obligations and that the Contractor has fulfilled the contract.
The contract commonly specifies a fixed period (often 21 days) within which the Employer must return the Performance Security after issuance of the Performance Certificate (Option D). The Taking-Over Certificate (Options A and C) marks substantial completion but does not end the Contractor's obligations for defects.
References:
FIDIC Red Book 1999, Sub-Clause 10.2 - Taking-Over Certificate
FIDIC Red Book 1999, Sub-Clause 10.4 - Performance Certificate
FIDIC Red Book 1999, Sub-Clause 10.5 - Release of Performance Security
FIDIC Contract Manager Study Guide, Module on Payment Procedures and Financial Management
質問 # 60
Which two statements are true under the FIDIC Red Book (edition 1999)?
(Choose all of the correct answers - multiple possibilities)
- A. The Performance Certificate is deemed to constitute the acceptance of the Works.
- B. The Performance Certificate is deemed to be issued on fulfilment of certain conditions stated in the respective Sub-Clause.
- C. The Engineer shall issue the Performance Certificate within 28 days at the latest: by the end of the Defects Notification Periods, and once the Contractor has supplied all the Contractor's Documents and completed and tested all Works including remedying any defects in accordance with the Contract.
- D. The Performance Certificate constitutes acceptance of the Works and full performance of all obligations of each Party.
正解:B、C
解説:
Under the FIDIC Red Book 1999, the Performance Certificate marks the end of the Contractor's obligations under the contract (Sub-Clause 11.9). The Engineer must issue this certificate once the Defects Notification Period has ended, all Contractor's Documents are submitted, and all works including defect rectification have been completed and tested.
Option C is correct because the Engineer is required to issue the Performance Certificate within 28 days after these conditions are met.
Option D is correct as the certificate is conditional upon fulfilling specific contract requirements (e.g., completion of works, submission of documents).
Option A is incorrect because acceptance of works usually happens earlier (e.g., taking-over certificate); the Performance Certificate represents completion of all contractual obligations, not just acceptance.
Option B is incorrect as the Performance Certificate confirms contractual completion but does not necessarily imply full mutual performance beyond contract terms.
References:
FIDIC Red Book 1999 Edition, Sub-Clause 11.9 - Performance Certificate
FIDIC Contract Manager Study Guide, Module on Project Close-Out and Final Account
質問 # 61
Upon review of the revised programme, submitted by the Contractor, if the Engineer (under FIDIC Red or Yellow Books) or Employer (under FIDIC Silver Book) does not give a Notice of Non-Compliance within 14 days after receiving a revised programme, then ... [complete the sentence, thereby considering FIDIC Red, Yellow, and Silver Books (edition 2017)]. (1 correct answer applies)
- A. The Contractor cannot proceed in accordance with the Programme.
- B. The Engineer is deemed to have no objection to use the revised programme submitted by the Contractor, for the Works.
- C. The Contractor shall submit a Notice to the Engineer or the Employer reminding him to give its approval on the revised programme.
- D. The Engineer shall be deemed to have given a Consent and the revised programme shall be the Programme.
正解:B
解説:
Comprehensive and Detailed Explanation:
According to the FIDIC 2017 editions (Red, Yellow, and Silver Books), when the Contractor submits a revised programme, the Engineer or Employer has a limited time (typically 14 days) to review and raise any Notice of Non-Compliance if the programme does not meet contract requirements (Sub-Clause 8.3 or equivalent). If no notice is issued within this period, the Engineer or Employer is deemed to have no objection to the revised programme.
This does not imply formal approval or consent, but the programme can be used for the execution and administration of the works in the absence of objections. This avoids unnecessary delay due to inaction.
Option D is correct as it captures this deemed "no objection" position.
Option B is incorrect as "deemed consent" is stronger than FIDIC provisions state; it is more correct to say
"no objection".
Option A is incorrect since the Contractor does not have to remind the Engineer or Employer for consent within this period.
Option C is incorrect because the Contractor may proceed if no non-compliance is notified.
References:
FIDIC Red Book 2017 Edition, Sub-Clause 8.3 - Programme
FIDIC Yellow Book 2017 Edition, Sub-Clause 8.3 - Programme
FIDIC Silver Book 2017 Edition, Sub-Clause 8.3 - Programme
FIDIC Contract Manager Study Guide, Module on Time and Delay Management
質問 # 62
You are the Contract Manager in a highway project using FIDIC Red Book (edition 1999). You work for the Employer- a highway management agency. During the tender period, you are informed of a specific Commencement Date required by the directors of the agency. Which two of the following approaches to inform the tenderers of this date are clearly and unambiguously drafted?
Choose all of the correct answers (multiple possibilities).
- A. Inform the Commencement Date to the tenderers by email, and attach that email in the list of Contract Documents.
- B. Specify Commencement Date in the Particular Conditions.
- C. Specify Commencement Date in the Contract Agreement.
- D. Specify Commencement Date in the Minutes of Meeting of Contract Negotiation.
正解:B、C
解説:
The Commencement Date is a critical contractual milestone that triggers contractual obligations including the start of time for completion. For clarity and enforceability, it must be specified clearly in contract documents forming part of the formal contract. The Contract Agreement (Option B) and the Particular Conditions (Option C) are the standard places to unambiguously specify the Commencement Date.
Minutes of meetings (Option A) or emails (Option D), while useful for informal communication, do not have the legal certainty or binding contractual effect unless expressly incorporated into the contract documents.
Therefore, specifying the Commencement Date solely in meeting minutes or emails is not advised for clarity and risk mitigation.
References:
FIDIC Red Book 1999, Sub-Clause 8.1 - Commencement of Works
FIDIC Contract Manager Study Guide, Module on Contract Formation and Execution
質問 # 63
Which two of the following statements are correct regarding Dispute under the FIDIC Red, Yellow, and Silver Books (edition 2017)?
Choose all of the correct answers (multiple possibilities)
- A. If a Party is dissatisfied with the determination and has given Notice of Dissatisfaction (NOD) to the other party within a strict 28-day time limit, a Dispute arises and either Party may proceed under Sub- Clause 21.4 to obtain a DAAB decision on it.
- B. In case the Engineer refuses to issue a Performance Certificate or to issue one with a correct date under Sub-Clause 11.9, and the Contractor has disagreed with the requested entitlement or relief in connection with this refusal, Dispute shall be deemed to have arisen.
- C. The Dispute must be submitted to the Dispute Avoidance and Adjudication Board (DAAB) within 42 days, otherwise the NOD is deemed to have lapsed and is no longer valid.
- D. Both 'Disagreement' and 'Dispute' are defined terms under the Conditions of Contract.
正解:A、B
解説:
Option A is correct. Under Sub-Clause 11.9 (Performance Certificate) refusal or incorrect issuance by the Engineer, combined with disagreement by the Contractor, may cause a Dispute to arise.
Option B is correct. If a Party is dissatisfied with a determination, it must give a Notice of Dissatisfaction (NOD) within 28 days to escalate the matter to a Dispute, allowing either Party to refer it to the DAAB as per Sub-Clause 21.4.
Option C is incorrect. The contract does not specify a 42-day time limit for submission to DAAB after NOD; timelines vary by contract and stage.
Option D is incorrect. 'Disagreement' is not a formally defined term in FIDIC contracts, whereas 'Dispute' is.
References:
FIDIC Red, Yellow, Silver Books 2017 Edition, Sub-Clause 11.9 and Clause 21 - Claims, Disputes, and Adjudication FIDIC Contract Manager Study Guide, Module on Dispute Resolution
質問 # 64
You are the Contract Manager of the Employer for a Data Centre Project using the FIDIC Yellow Book (edition 2017). As a Contract Manager during the procurement stage, you are to explain the difference between Dispute Avoidance and Adjudication Board (DAAB) and other alternative dispute resolutions for this type of project. Which one of the following statements of its explanation is NOT correct?
- A. Avoidance of Disputes on the project and resolution of Disputes at or soon after the time they arise is a two-part role of the DAAB.
- B. DAAB provided supports for Parties during arbitration, as a witness to give factual evidence on the background for the DAAB's Decision.
- C. The function of the DAAB is to remain in place as part of the Parties' project team to assist both Parties, equally and impartially.
- D. DAAB is to provide for a fair, timely and efficient resolution of Disputes.
正解:B
解説:
Comprehensive and Detailed Explanation:
Option D is NOT correct. The DAAB does not act as a witness or provide support during arbitration. Its role is to avoid and adjudicate disputes early during the project lifecycle impartially and fairly, but it does not serve as witness support in arbitration proceedings.
References:
FIDIC Yellow Book 2017 Edition, Clause 21 - Dispute Avoidance and Adjudication Board FIDIC Contract Manager Study Guide, Module on Dispute Resolution
質問 # 65
During the execution of certain Works under a FIDIC Yellow Book (edition 1999), a Contract in a historical area along the silk route, one of the workers on the excavator shouts out to the supervisor of the Contractor it has discovered something on the Site. The supervisor inspects the finding and concludes this is possibly an ancient treasure in a wooden box. The supervisor sees some golden coins through the cracked lid of the box.
The supervisor immediately stops the execution of the Works, sends the workers away and blocks access to the Site for all persons. Given the sensitive nature of the findings, the supervisor informs you as Engineer.
How do you react?
- A. You thank the supervisor for their action. You make sure the Site is secured and ask the Contractor to make an improvised barrier around the Site. You ask the Contractor to appoint its most trustworthy guards to set a perimeter. You inform the Employer and local authorities and you ask the Contractor to send you a notice in writing whereby it requests for a Variation (as this is needed for you to instruct the Contractor), thereby already including a fixed proposal for the costs of the guards and barrier, all in accordance with Sub-Clause 4.24.
- B. You immediately take action and give the instruction to the supervisor to make sure to cover this finding and till the excavation with material. You then redesign and make a determination (Sub-Clause
3.5) on a change of the Works - if needed - to make sure the execution can restart within days because of the need to finish this project. - C. You compliment the supervisor for their swift and decisive action. However, the Works should advance as soon as possible. You ask the supervisor to excavate the box further, and place it in the back of your truck. You promise the supervisor you will drive the box yourself to the University in the city nearby, because it is very important to preserve found treasures like this. The Contractor is not entitled to an extension of time, as no delay has been incurred.
- D. You inform the supervisor that given the sensitive nature of the findings, you need a formal and written notice as mentioned in Sub-Clause 4.24 second paragraph, otherwise you cannot give further instructions. You ask them to send it to you as soon as possible, because otherwise you are not able to entitle the Contractor to any extension of time and payment of costs.
正解:A
解説:
Comprehensive and Detailed Explanation:
Under FIDIC Yellow Book 1999, Sub-Clause 4.24 ("Unforeseeable Physical Conditions") deals with unexpected discoveries such as archaeological finds. The Engineer's role includes ensuring site safety, notifying the Employer and relevant authorities, and managing the implications through variations.
Option B reflects best practice: securing the site, appointing guards, notifying Employer and authorities, and requesting a formal Variation Notice to cover costs and entitlement to extension of time.
Options A and D are unsafe or legally risky actions that could damage the find and breach legal obligations.
Option C delays the necessary immediate protective actions.
References:
FIDIC Yellow Book 1999 Edition, Sub-Clause 4.24 - Unforeseeable Physical Conditions FIDIC Contract Manager Study Guide, Module on Claims and Variation Management
質問 # 66
You are the new Contract Manager of the Contractor in a bridge project using FIDIC Yellow Book (edition
2017). The project had been suspended due to a material change in the Employer's financial arrangement. You have worked with your team to identify several failures of the Employer in carrying its obligations under the Contract. Which one of the following does NOT allow the Contractor to issue Notice to terminate the Contract?
- A. The Employer failed to comply with a final and binding determination issued by the Engineer, and such failure constitutes a material breach of the Employer's obligations under the Contract.
- B. A prolonged suspension for more than 1 year has affected the whole of the Works.
- C. The Contractor has requested the Employer but has not received any evidence that the financial arrangement is being maintained, despite having sent a notice thereto 4 months earlier.
- D. The Contractor does not receive the amount due under the latest Payment Certificate for more than 4 months after the due date.
正解:C
解説:
Comprehensive and Detailed Explanation:
Option C does NOT, on its own, provide grounds for termination. The Contractor's request for evidence of financial arrangement, without further contractual breach, is insufficient to terminate.
Options A, B, and D are valid grounds for termination under FIDIC Yellow Book 2017 due to prolonged suspension, non-payment beyond allowed period, or failure to comply with binding determinations.
References:
FIDIC Yellow Book 2017 Edition, Sub-Clauses 15.1 (Suspension) and 15.2 (Termination by Contractor) FIDIC Contract Manager Study Guide, Module on Suspension and Termination
質問 # 67
Under the FIDIC Red and Yellow Books (edition 2017), which two of the following elements shall form part of the initial time Programme?
- A. The date on which the right of access to and possession of (each part of) the Site is to be given to the Contractor.
- B. The actual progress to date, any delay to such progress and the effects of such delay on other activities (if any).
- C. The sequence and timing of the remedial work.
- D. All key delivery dates of Plant and Materials.
正解:A、D
解説:
Comprehensive and Detailed Explanation:
Option A is correct: The initial programme must include the date for the Contractor's access to the Site.
Option D is correct: Key delivery dates for Plant and Materials are essential elements of the programme.
Option B relates to updated/revised programmes, not the initial programme.
Option C generally relates to remedial work and is part of revised or detailed programmes.
References:
FIDIC Red and Yellow Books 2017 Edition, Sub-Clause 8.3 - Programme
FIDIC Contract Manager Study Guide, Module on Time and Delay Management
質問 # 68
Regarding the FIDIC Silver Book (both editions), if a part of the Works is to be paid according to quantity supplied or work done, appropriate provisions must be included in the Particular Conditions. Is this statement true or false?
- A. True
- B. False
正解:A
解説:
This statement is true. The Silver Book (EPC/Turnkey contracts) usually involves lump-sum payment, but if part payment is based on quantity or work done, this must be explicitly provided for in the Particular Conditions to avoid ambiguity.
Such provisions ensure clarity on payment terms in line with project specifics.
References:
FIDIC Silver Book 1999 & 2017 Editions, Sub-Clause 14 - Payment Provisions FIDIC Contract Manager Study Guide, Module on Payment Procedures
質問 # 69
Which of the following documents form part of a FIDIC Construction Contract ["Red Book" (1999)], hence, to be drafted and included among the Tender Documents? (2 correct answers apply) Choose all of the correct answers (multiple possibilities).
- A. Schedule of Guarantees
- B. Schedule of Baselines
- C. Bill of Quantities
- D. Specifications
- E. Employer's Requirements
正解:C、D
解説:
Under the FIDIC Red Book (1999), the Tender Documents typically include:
The Bill of Quantities (Option B), which provides detailed quantities for priced items and forms a basis for tender pricing.
The Specifications (Option E), which define the technical requirements for the Works.
The Schedule of Guarantees (Option A) is usually provided later, during contract formation, not as part of tender documents.
Employer's Requirements (Option C) are more commonly referenced in design-build contracts such as the Yellow Book, not the Red Book which is traditionally a design-bid-build contract.
Schedule of Baselines (Option D) is not a standard tender document in FIDIC Red Book contracts.
References:
FIDIC Red Book 1999 Edition - Tender Documents Section
FIDIC Contract Manager Study Guide, Module on Tendering Documents
質問 # 70
Under the FIDIC Red Book (edition 2017), the Engineer has suspended works to come to a change of the design of a part of the Works. After expiry of 84 days of suspension, the Contractor gave notice thereof.
Following this notice, the suspension was not lifted within 28 days. What two statements are correct in such a situation?
- A. The Contractor cannot terminate the Contract.
- B. The Contractor may omit the affected part of Works and deny to carry out such Work going forward, but only after it has given a second notice to the Engineer.
- C. The Contractor may terminate the Contract if it affects the whole Works, but only after it has given a second notice to the Engineer.
- D. Under the Contract the Parties cannot agree on further suspension and the Contractor may immediately terminate the Contract if it affects the whole Works.
正解:C、D
解説:
Under FIDIC Red Book 2017, if the Engineer suspends works for more than 84 days and the Contractor notifies the Engineer, but the suspension is not lifted within 28 days, the Contractor may terminate the contract if the suspension affects the whole of the Works (Option A).
Additionally, the Contractor must give a second notice before termination (Option C). This process ensures proper communication and adherence to contractual procedures.
Option B is incorrect; termination is allowed under specified conditions.
Option D is incorrect; omission of work is not generally permitted without formal termination.
References:
FIDIC Red Book 2017 Edition, Sub-Clause 8.9 - Suspension by Engineer
FIDIC Contract Manager Study Guide, Module on Suspension and Termination
質問 # 71
You are the Contract Manager of the Engineer in a hotel project. In May 2020, the Employer and the Contractor signed a Contract based on the FIDIC Yellow Book (edition 2017), as per which the Contractor will design and build a hotel project with Contract Price of 5,100,000 USD. The Time for Completion for this project is 12 months (May 2021). The Contract also named a nominated Subcontractor (as referred to in Sub- Clause 4.5) who provides mechanical, electrical, and plumbing services for the project (including the fire fighting system), which was accepted by the Contractor without any discussions.
The Project was delayed due to issues with the fire fighting system, and you issued the Taking-Over Certificate in June 2022.
The Employer sent a Notice of Claim to the Contractor on Delay Damages with a maximum value equal to
10% of Contract Price (510,000 USD). The Employer also gave a Notice to the Contractor stating that the Contractor has failed to submit the evidence of payment to the nominated Subcontractor as well as the reason for withholding payment to the nominated Subcontractor. Therefore, the Employer has paid the nominated Subcontractor directly the entire amount due, coming to 100,000 USD. The Employer intends to include this amount as a deduction in the Final Payment to the Contractor.
As Contract Manager of the Engineer, you are tasked to make a fair determination of the Notices of the Employer. In your "Notice of the Engineer's determination", what is your determination for the deduction of the next Interim Payment to the Contractor in relation to the amount directly paid to the nominated Subcontractor?
- A. The Employer is not entitled to deduct the amount directly paid.
- B. The Employer is entitled to deduct the amount directly paid.
正解:B
解説:
Comprehensive and Detailed Explanation:
According to FIDIC Yellow Book 2017, Sub-Clause 4.5, the Employer has the right to pay a nominated Subcontractor directly if the Contractor fails to do so and can deduct the amount from payments due to the Contractor. This provision protects nominated Subcontractors and ensures payment continuity. The Contractor's failure to provide evidence of payment and justification for withholding payment justifies the Employer's direct payment and deduction.
Thus, the Engineer's determination should allow the Employer to deduct the 100,000 USD paid directly to the nominated Subcontractor from the Contractor's next Interim Payment, ensuring fairness and contract compliance.
References:
FIDIC Yellow Book 2017 Edition, Sub-Clause 4.5 - Nominated Subcontractors FIDIC Contract Manager Study Guide, Module on Claims and Payment Procedures
質問 # 72
What are two differences between a notice and other communications under the FIDIC Red Book (edition
2017)? (2 correct answers apply)
Choose all of the correct answers (multiple possibilities).
- A. Both 'Notice' and 'Other Communications' are defined terms under the Conditions of Contract.
- B. Contractually there is no difference between a notice and other communications.
- C. The Parties and Engineer shall be given original or copy of any Notice, Notice of Dissatisfaction (NOD) and Certificates, which is not always the case for other communications.
- D. Notice is a defined term, while other communications are not defined as a term in the General Conditions.
正解:C、D
解説:
Option A is correct: "Notice" is a defined term under FIDIC 2017 Red Book; "Other Communications" is a separate category, also defined but distinct.
Option D is correct: Notices, Notices of Dissatisfaction, and Certificates require delivery to all Parties and the Engineer, whereas other communications may not have such strict requirements.
Option B is incorrect as there are contractual differences.
Option C is partially correct but "Other Communications" and "Notice" are distinct terms, so A is more precise.
References:
FIDIC Red Book 2017 Edition, Sub-Clause 1.1 - Definitions
FIDIC Contract Manager Study Guide, Module on Contract Communication
質問 # 73
In which one of the following circumstances is it recommended to select the Contractor after a two-stage procurement procedure (pre-qualification + tender procedure)?
- A. In case of large scale works, where there are several companies likely to have an interest in submitting an offer.
- B. If there is international financing for the project, it is always necessary to conduct a two-stage procurement procedure.
- C. When the works are simple and of short duration.
- D. When there is a limited number of capable experienced contractors available and ready to take part in the procurement.
正解:A
解説:
Two-stage procurement, involving pre-qualification followed by tender, is typically recommended for large- scale projects where many potential contractors might be interested. This process helps to shortlist qualified contractors, thus streamlining the tender evaluation and increasing the quality and competitiveness of submitted offers.
Option C correctly reflects this approach for complex or large projects where competition needs to be managed.
Option A is incorrect since simple, short-duration projects usually do not require complex procurement.
Option B is incorrect because if only a few capable contractors exist, pre-qualification may be less necessary.
Option D is incorrect as international financing does not always mandate two-stage procurement, although it often influences procurement methods.
References:
FIDIC Contract Manager Study Guide, Module on Contract Formation and Procurement Strategies World Bank Procurement Guidelines and Common Industry Practice
質問 # 74
In a construction project using the FIDIC Silver Book (edition 1999), if the Parties prefer the dispute board to be appointed on an "ad-hoc" basis instead of as a standing Dispute Avoidance and Adjudication Board (DAAB), what is it called? (1 correct answer applies)
- A. DAB
- B. Ad-hoc DB
- C. Ad-hoc arbitration
- D. Ad-hoc DAAB
正解:A
解説:
Under FIDIC terminology, an ad-hoc Dispute Board is known as a DAB (Dispute Adjudication Board), which is appointed for specific disputes as they arise, rather than standing continuously.
The DAAB is a standing board appointed for the project duration, providing continuous dispute avoidance and adjudication.
Option D refers to arbitration, which is a different dispute resolution method.
References:
FIDIC Silver Book 1999 Edition, Clause 20 - Dispute Adjudication Board
FIDIC Contract Manager Study Guide, Module on Dispute Boards and Resolution
質問 # 75
Which one of the following statements best describes the requirements of Time for Completion?
- A. This is one of the Contractor's obligations, namely the completion of most of the Works (except minor outstanding works), within the Time for Completion calculated from the Commencement Date.
- B. This is the Contractor's fundamental time-related obligation, namely the completion of most of the Works (except minor outstanding works), within the Time for Completion calculated from the Commencement Date.
- C. This is one of the Contractor's obligations, namely the completion of most of the Works (except minor outstanding works), within the Time for Completion calculated from the Effective Date.
- D. This is the Contractor's fundamental time-related obligation, namely completion the whole of the Works within the Time for Completion calculated from the Commencement Date.
正解:D
解説:
Option A best describes the Time for Completion as the Contractor's fundamental obligation to complete the entire Works within the contractual Time for Completion, calculated from the Commencement Date.
Options B, C, and D incorrectly limit the scope to "most" of the Works or confuse the reference date.
The Time for Completion sets the critical timeline for contract performance and triggering of delay damages or extensions.
References:
FIDIC Red and Yellow Books 1999 & 2017 Editions, Sub-Clause 8.1 - Time for Completion FIDIC Contract Manager Study Guide, Module on Time and Delay Management
質問 # 76
Which one of the following statements regarding drafting contracts based on FIDIC Books is correct?
- A. The FIDIC Books provide people who draft contracts with great examples on how to draft a good contract model. Furthermore, arrangements from Red, Yellow and Silver Books can be easily mixed to get a good fit for a specific project.
- B. Amending clauses, supposedly in the interest of the Employer, immediately nullifies all the advantages of standardization, and almost invariably introduces conflicting or ambiguous requirements on the parties, and often causes mistrust between them.
- C. People who draft contracts should, when preparing a new contract, always start with the question:where do I want to lay the most risks between Employer and Contractor, and does the Employer has the budget to reward Contractors with a high risk apatite?
- D. The Form of Contract is chosen by the Contractor and imposed by him on the Employer, who tenders on that basis.
正解:C
解説:
Option D is correct because contract drafting should strategically allocate risks between parties based on who can best manage them and the Employer's budget for risk and reward. Understanding risk appetite is key to tailoring FIDIC contracts appropriately.
Option A is exaggerated; while amendments can introduce issues, careful drafting can preserve benefits of standardization.
Option B is partly true but mixing arrangements is complex and not always straightforward.
Option C is incorrect; the Employer usually chooses the contract form.
References:
FIDIC Contract Management Guidelines - Golden Principles
FIDIC Contract Manager Study Guide, Module on Contract Drafting and Risk Allocation
質問 # 77
Which of the following form a Contractor's entitlement, in case the Contractor does not receive an interim payment within the allocated contractual deadline for payment? (2 correct answers apply) Choose all of the correct answers (multiple possibilities).
- A. The Contractor is entitled to suspend the works or reduce the rate of progress of the work, after giving a due Notice (21 days) about this intention.
- B. Right after the expiry of the payment deadline, the Contractor may terminate the contract.
- C. If the payment is not made within the time period required, after the expiry of such period, from the next day onwards, the Contractor is entitled to suspend all his/her activities on Site.
- D. In case the Employer paid the Contractor late, the Contractor becomes entitled to receive financing charges applying the % included in the Contract Data (if this is not stated, then applying the percentage as included under the corresponding Sub-Clause).
- E. Beyond receiving the financing charges, the Contractor has no further entitlements in such a case.
正解:A、D
解説:
Option C is correct: The Contractor is entitled to financing charges (interest) on late payments, calculated as per the percentage specified in the Contract Data or corresponding Sub-Clause.
Option D is correct: The Contractor can suspend works or reduce progress after giving due notice, usually 21 days, if payments are not made on time.
Option A is incorrect; termination is not automatic right after the payment deadline expires.
Option B is incorrect; suspension requires prior notice rather than immediate action.
Option E is incorrect because the Contractor has additional remedies such as suspension, beyond just financing charges.
References:
FIDIC Red, Yellow, Silver Books 1999 & 2017 Editions, Sub-Clause 14.8 - Payment of Retention Money and Financing Charges FIDIC Contract Manager Study Guide, Module on Payment Procedures and Remedies
質問 # 78
......
無料CCM試験問題集試験点数を伸ばそう:https://jp.fast2test.com/CCM-premium-file.html
2026年最新の実際に出るCCM問題集には試験のコツがあるPDF試験材料:https://drive.google.com/open?id=1YLB_5CFJw9uFizuizR3-YfNeWOrqUdb-