[2025年10月]更新のC_TS422_2504試験問題集合格させるのは2025年最新のSAP Certified Associate - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing [Q48-Q69]

Share

[2025年10月]更新のC_TS422_2504試験問題集合格させるのは2025年最新のSAP Certified Associate - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing

無料で使えるC_TS422_2504試験問題集で合格させるお手軽に試験合格

質問 # 48
You use the Finite Scheduling - with Reverse planning strategy and want to allow scheduling in the past.
How can you parameterize this in the strategy profile?

  • A. Specify a negative PP/DS horizon
  • B. Specify a negative opening period
  • C. Specify a negative offset time
  • D. Specify a negative planning horizon

正解:C


質問 # 49
What is the purpose of using a low level code?
Note: There are 2 correct answers to this question.

  • A. To determine the priority of alternative components inside the material BOM (bill of material)
  • B. To determine the use of subitems inside the material BOM (bill of material)
  • C. To determine the sequence in which materials are planned in MRP
  • D. To determine the lowest explosion level at which a material occurs in all the product structures

正解:C、D


質問 # 50
What are the possible results of a production planning run in Advanced Planning (PP/DS)?
Note: There are 2 correct answers to this question.

  • A. Planned order
  • B. Scheduling agreement schedule line
  • C. Purchase order
  • D. Production order

正解:A、B


質問 # 51
What options are available inside a document?
Note: There are 2 correct answers to this question.

  • A. Storage locations
  • B. Versioning
  • C. Plant links
  • D. Object links

正解:B、D


質問 # 52
How are dependent requirements for assemblies created?
Note: There are 2 correct answers to this question.

  • A. They are created on the assembly level during the planning run.
  • B. They are created with exact times in Advanced Planning.
  • C. They are only created for multilevel bill of material (BOM) structures.
  • D. They are created together with the independent requirement for the finished product.

正解:A、B


質問 # 53
Which objects can you change with a change number?
Note: There are 2 correct answers to this question.

  • A. Work center
  • B. Bill of material
  • C. Routings
  • D. Production order

正解:B、C


質問 # 54
Which of the following elements does MRP take into account during net requirement calculation?
Note: There are 2 correct answers to this question.

  • A. Planned orders (unfirmed)
  • B. Production orders
  • C. ATP quantities
  • D. Planned orders (firmed)

正解:B、D


質問 # 55
What are the selection criteria of a bill of material (BOM) alternative?
Note: There are 2 correct answers to this question.

  • A. Date
  • B. Change number
  • C. Material BOM usage
  • D. Lot size

正解:A、D


質問 # 56
When can you maintain the batch characteristic values in SAP S/4HANA?
Note: There are 2 correct answers to this question.

  • A. When you record inspection results
  • B. When you execute batch determination
  • C. When you release the batch
  • D. When you post the goods receipt

正解:A、D


質問 # 57
In the context of the capacity scheduling table, how do you define a pacemaker work center?

  • A. By assigning it to the first operation of a routing
  • B. By assigning it to the capacity scheduling table
  • C. By assigning it to the production version
  • D. By assigning it to the bottleneck operation

正解:C


質問 # 58
Under what circumstances can you change the material type for a material if stocks, reservations, or purchasing documents exist? Note: There are 2 correct answers to this question.

  • A. The quantity and value updates are the same.
  • B. The same batch management level is used.
  • C. The same account category is used.
  • D. The same base unit of measure is used.

正解:A、D


質問 # 59
Which of the following is a scheduling method for a production order?

  • A. Determination of delivery date
  • B. Lead time scheduling
  • C. Determination of basic dates
  • D. Key date scheduling

正解:B


質問 # 60
What happens when you set up detailed scheduling with the finite scheduling mode Insert Operation?

  • A. An operation is scheduled as close as possible to the desired date.
  • B. To create a slot, neighbouring operations are moved in both planning directions.
  • C. Operations on multi-resources are planned finitely in a sequence.
  • D. Sequencing on multi-activity resources is automatically updated during planning.

正解:A


質問 # 61
Why would you use phantom assemblies?
Note: There are 2 correct answers to this question.

  • A. To enable simple structuring of BOMs
  • B. To make the procurement easier
  • C. To reduce the number of material masters
  • D. To make the assignment of components easier

正解:A、D


質問 # 62
You are a consultant on an SAP S/4HANA Cloud greenfield project.
Which of the following aspects should you focus on to achieve and maintain clean core data quality? Note: There are 2 correct answers to this question.

  • A. Accuracy
  • B. Stability
  • C. Timeliness
  • D. Efficiency

正解:B、D


質問 # 63
Which settings can you make in a production scheduling profile?
Note: There are 3 correct answers to this question.

  • A. Default order types
  • B. Automatic goods issue on confirmation
  • C. Automatic goods receipt on confirmation
  • D. Automatic release on order creation
  • E. Automatic print on order creation

正解:A、C、D


質問 # 64
How can a material availability check be triggered automatically for a production order?
Note: There are 2 correct answers to this question.

  • A. By mass processing
  • B. By order confirmation
  • C. By order release
  • D. By capacity planning

正解:A、C


質問 # 65
Which time elements are relevant for lead time scheduling of a production order?
Note: There are 2 correct answers to this question.

  • A. Opening period
  • B. Float after production
  • C. Setup time
  • D. Total replenishment lead time

正解:B、C


質問 # 66
When do you use variant bills of material (BOMs)?

  • A. When multiple materials have similar BOMS
  • B. When a material has a configurable BOM
  • C. When a material has multiple BOMs
  • D. When multiple materials have multiple BOMS

正解:A


質問 # 67
Which of the following questions do you have to answer before you start creating a bill of material (BOM)? Note: There are 2 correct answers to this question.

  • A. In which storage location is the BOM required?
  • B. When does the BOM need to become effective?
  • C. Which base unit of measure must the BOM have?
  • D. For which plant can the BOM be defined?

正解:B、D


質問 # 68
During production order creation, several valid production versions are found.
How does the system choose the production version?

  • A. Planned order or material number
  • B. Validity period or sales order
  • C. Lot size or material cost
  • D. Alphanumeric or quota arrangement

正解:D


質問 # 69
......

C_TS422_2504試験問題集、C_TS422_2504練習テスト問題:https://jp.fast2test.com/C_TS422_2504-premium-file.html

無料C_TS422_2504学習ガイド試験問題と解答:https://drive.google.com/open?id=1vaqmZNzcejL0RLlA0bibQanOkBQa0shz