質問 # 48
You use the Finite Scheduling - with Reverse planning strategy and want to allow scheduling in the past.
How can you parameterize this in the strategy profile?
- A. Specify a negative PP/DS horizon
- B. Specify a negative opening period
- C. Specify a negative offset time
- D. Specify a negative planning horizon
正解:C
質問 # 49
What is the purpose of using a low level code?
Note: There are 2 correct answers to this question.
- A. To determine the priority of alternative components inside the material BOM (bill of material)
- B. To determine the use of subitems inside the material BOM (bill of material)
- C. To determine the sequence in which materials are planned in MRP
- D. To determine the lowest explosion level at which a material occurs in all the product structures
正解:C、D
質問 # 50
What are the possible results of a production planning run in Advanced Planning (PP/DS)?
Note: There are 2 correct answers to this question.
- A. Planned order
- B. Scheduling agreement schedule line
- C. Purchase order
- D. Production order
正解:A、B
質問 # 51
What options are available inside a document?
Note: There are 2 correct answers to this question.
- A. Storage locations
- B. Versioning
- C. Plant links
- D. Object links
正解:B、D
質問 # 52
How are dependent requirements for assemblies created?
Note: There are 2 correct answers to this question.
- A. They are created on the assembly level during the planning run.
- B. They are created with exact times in Advanced Planning.
- C. They are only created for multilevel bill of material (BOM) structures.
- D. They are created together with the independent requirement for the finished product.
正解:A、B
質問 # 53
Which objects can you change with a change number?
Note: There are 2 correct answers to this question.
- A. Work center
- B. Bill of material
- C. Routings
- D. Production order
正解:B、C
質問 # 54
Which of the following elements does MRP take into account during net requirement calculation?
Note: There are 2 correct answers to this question.
- A. Planned orders (unfirmed)
- B. Production orders
- C. ATP quantities
- D. Planned orders (firmed)
正解:B、D
質問 # 55
What are the selection criteria of a bill of material (BOM) alternative?
Note: There are 2 correct answers to this question.
- A. Date
- B. Change number
- C. Material BOM usage
- D. Lot size
正解:A、D
質問 # 56
When can you maintain the batch characteristic values in SAP S/4HANA?
Note: There are 2 correct answers to this question.
- A. When you record inspection results
- B. When you execute batch determination
- C. When you release the batch
- D. When you post the goods receipt
正解:A、D
質問 # 57
In the context of the capacity scheduling table, how do you define a pacemaker work center?
- A. By assigning it to the first operation of a routing
- B. By assigning it to the capacity scheduling table
- C. By assigning it to the production version
- D. By assigning it to the bottleneck operation
正解:C
質問 # 58
Under what circumstances can you change the material type for a material if stocks, reservations, or purchasing documents exist? Note: There are 2 correct answers to this question.
- A. The quantity and value updates are the same.
- B. The same batch management level is used.
- C. The same account category is used.
- D. The same base unit of measure is used.
正解:A、D
質問 # 59
Which of the following is a scheduling method for a production order?
- A. Determination of delivery date
- B. Lead time scheduling
- C. Determination of basic dates
- D. Key date scheduling
正解:B
質問 # 60
What happens when you set up detailed scheduling with the finite scheduling mode Insert Operation?
- A. An operation is scheduled as close as possible to the desired date.
- B. To create a slot, neighbouring operations are moved in both planning directions.
- C. Operations on multi-resources are planned finitely in a sequence.
- D. Sequencing on multi-activity resources is automatically updated during planning.
正解:A
質問 # 61
Why would you use phantom assemblies?
Note: There are 2 correct answers to this question.
- A. To enable simple structuring of BOMs
- B. To make the procurement easier
- C. To reduce the number of material masters
- D. To make the assignment of components easier
正解:A、D
質問 # 62
You are a consultant on an SAP S/4HANA Cloud greenfield project.
Which of the following aspects should you focus on to achieve and maintain clean core data quality? Note: There are 2 correct answers to this question.
- A. Accuracy
- B. Stability
- C. Timeliness
- D. Efficiency
正解:B、D
質問 # 63
Which settings can you make in a production scheduling profile?
Note: There are 3 correct answers to this question.
- A. Default order types
- B. Automatic goods issue on confirmation
- C. Automatic goods receipt on confirmation
- D. Automatic release on order creation
- E. Automatic print on order creation
正解:A、C、D
質問 # 64
How can a material availability check be triggered automatically for a production order?
Note: There are 2 correct answers to this question.
- A. By mass processing
- B. By order confirmation
- C. By order release
- D. By capacity planning
正解:A、C
質問 # 65
Which time elements are relevant for lead time scheduling of a production order?
Note: There are 2 correct answers to this question.
- A. Opening period
- B. Float after production
- C. Setup time
- D. Total replenishment lead time
正解:B、C
質問 # 66
When do you use variant bills of material (BOMs)?
- A. When multiple materials have similar BOMS
- B. When a material has a configurable BOM
- C. When a material has multiple BOMs
- D. When multiple materials have multiple BOMS
正解:A
質問 # 67
Which of the following questions do you have to answer before you start creating a bill of material (BOM)? Note: There are 2 correct answers to this question.
- A. In which storage location is the BOM required?
- B. When does the BOM need to become effective?
- C. Which base unit of measure must the BOM have?
- D. For which plant can the BOM be defined?
正解:B、D
質問 # 68
During production order creation, several valid production versions are found.
How does the system choose the production version?
- A. Planned order or material number
- B. Validity period or sales order
- C. Lot size or material cost
- D. Alphanumeric or quota arrangement
正解:D
質問 # 69
......