質問 # 25
When you define assessment cycles for the period-end closing in overhead cost accounting, which object can you assign to the cycle segment?
Response:
- A. Settlement rule
- B. Allocation structure
- C. Template
- D. Costing sheet
正解:B
質問 # 26
Which criteria do you use to specify the G/L account for the work in process (WIP) settlement?
There are THREE correct answers for this question
Response:
- A. Results analysis cost element
- B. Results analysis profit center
- C. Results analysis method
- D. Results analysis category
- E. Results analysis version
正解:C、D、E
質問 # 27
Where can you adjust the automatic account assignment?
There are TWO correct answers for this question
Response:
- A. Substitution (TA: GGB1)
- B. G/L account (TA: FS00)
- C. Cost center (TA: KS01)
- D. Default account assignment (TA: OKB9)
正解:A、D
質問 # 28
Which parameters can you enter when you create a costing run?
There are THREE correct answers for this question
Response:
- A. Costing version
- B. Production version
- C. Costing variant
- D. Transfer control
- E. Valuation variant
正解:A、C、D
質問 # 29
What does the internal order settlement profile define?
There are THREE correct answers for this question
Response:
- A. The template allocation
- B. Whether commitment management is necessary
- C. The valid receivers
- D. Whether settlement is necessary
- E. The accounting document type
正解:C、D、E
質問 # 30
What is required before you can create a multi-level material cost estimate without quantity structure?
Response:
- A. Material master with costing view
- B. Material master with accounting view and with MRP views
- C. Specific valuation variants for material costings without quantity structure
- D. Specific costing variants for material costings without quantity structure
正解:A
質問 # 31
Which cost objects can only be controlled by period?
There are TWO correct answers for this question
Response:
- A. Product cost collector
- B. Cost object hierarchy
- C. Production order
- D. Process order
正解:A、B
質問 # 32
Which objects are predefined characteristics in SAP S/4HANA?
There are THREE correct answers for this question
Response:
- A. Region
- B. Company code
- C. Controlling area
- D. Product category
- E. Plant
正解:B、C、E
質問 # 33
You use a ledger, an additional standard ledger and an extension ledger. You post a general journal entry without indicating a ledger group.
For which ledger(s) are separate line items posted in the universal journal?
Response:
- A. The leading ledger only
- B. All ledgers
- C. The leading and extension ledgers
- D. The standard ledgers
正解:C
質問 # 34
How can you define a dynamic group for internal orders?
Response:
- A. Assign a selection variant to an end node
- B. Create a substitution rule for mass changes
- C. Use wild cards in the order codes assigned to nodes
- D. Define an order coding mask for order types
正解:C
質問 # 35
What can you define for a user status in the status profile?
Response:
- A. The business user IDs authorized to change the user status
- B. The assigned user status after a business transaction is executed
- C. The order types for which a user status is valid
- D. The versions for which you can enter plan data
正解:B
質問 # 36
Which are levels of internal order planning?
There are TWO correct answers for this question
Response:
- A. Overall planning
- B. Group costing
- C. Integrated planning
- D. Primary and secondary cost and revenue planning
正解:A、C
質問 # 37
What do you use to map the primary cost component split to the production cost component structure?
Response:
- A. Assignment scheme
- B. Cost Component groups
- C. Allocation structure
- D. Transfer structure
正解:B
質問 # 38
What do you need to define in order to report variable costs that refer to the cost component split in account-based CO-PA?
There are TWO correct answers for this question
Response:
- A. A price difference profile
- B. A cost splitting profile
- C. A calculation formula
- D. A variable cost field in ACDOCA
正解:B、D
質問 # 39
Which customizing activity do you perform in overhead cost controlling?
Response:
- A. Define cost centers categories
- B. Maintain costing variant parameters
- C. Define cost center categories
- D. Create value fields
正解:C