質問 # 17
Where can the results of a Time Series Analysis be used?Note: There are 2 correct answers to this question.
- A. In Global (multi-stage) Inventory Optimization to calculate time-phased Recommended Safety Stock Outputs
- B. During XYZ segmentation in the Manage ABC/XYZ Segmentation Rules app
- C. In the Manage Forecast Error Calculations app - Demand Planning app to calculate the Forecast Error CV
- D. In the Microsoft Excel add-in, where you can use them to limit and filter your planning views
正解:A、B
質問 # 18
You create an S&OP operator for heuristics on an SAP IBP project. What must you enable for the S&OP operator that is specifically relevant for subnetworks?
- A. Normalize Quotas parameter
- B. Supply propagation
- C. Compute Expected Supply parameter
- D. Balance Receipts parameter
正解:C
質問 # 19
Which of the following settings can you use in your supply planning background job triggered from Excel? Note: There are 2 correct Answers to this question.
- A. Planning unit
- B. UOM to ID
- C. Target currency
- D. Type of algorithm to use
正解:B、D
質問 # 20
Which of the following checks for master data and key figures does the Check Mode algorithm trigger?Note:
There are 3 correct answers to this question.
- A. It checks whether the sourcing in the Production Source Item Master Data type exists.
- B. It checks whether the required planning level master data exists for a subset of input key figures.
- C. It checks whether the location resource specified in the master data forms a cycle in the supply chain network.
- D. It checks whether the location products specified in the master data are connected by customer sourcing rules within the supply chain network.
- E. It checks whether the heuristic detects cycles formed by nodes (such as location products) in the supply chain network.
正解:B、D、E
質問 # 21
You are working with the inventory optimization process and you want to use a what-if analysis. What parameters are assessed by this analysis? Note: There are 2 correct Answers to this question.
- A. Changed variability
- B. Capacity consumption
- C. Number of planning combinations
- D. Service levels
正解:A、D
質問 # 22
You are working to realign the data due to a recent warehouse closure.What should you be aware of in regards to the realignment steps settings?Note: There are 2 correct answers to this question.
- A. A realignment step can change master data, planning objects and key figures.
- B. You must mark the realignment step as "shared" and assign the steps to users.
- C. The name of the realignment step should be no longer than 20 characters.
- D. The number of steps in the realignment run is limited to 255.
正解:A、B
質問 # 23
What are the ways to achieve rolling aggregation with SAP IBP?
- A. Using a appropriate period weight factor
- B. Using a local member
- C. Using a key figure calculation
- D. Using a attribute as a key figure
正解:A
質問 # 24
Which conditions are prerequisites for key figure disaggregation?
- A. The key figure is set to Not Editable.
- B. The key figure is calculated and aggregation mode is selected.
- C. The key figure is calculated and editable.
- D. The key figure is stored and editable.
正解:D
質問 # 25
Which library is used by the forecasting engine for the demand sensing algorithm?
- A. Supply chain algorithm library
- B. Predictive analytics library
- C. Demand library
- D. Heuristics library
正解:A
質問 # 26
Which of the following modes can you use when creating a constrained plan? Note: There are 2 correct Answers to this question.
- A. Profit maximization
- B. Production maximization
- C. Resource maximization
- D. Delivery maximization
正解:A、D
質問 # 27
You are evaluating criteria for choosing the solver to support planning for a complex supply chain. What are some of the points that should be reviewed? Note: There are 2 correct Answers to this question.
- A. Push and Pull production models are used by the optimizer.
- B. Planning results can be generated faster by the optimizer.
- C. Prioritization of demand elements one by one is achieved by heuristics.
- D. Finite heuristics can achieve demand prioritization and pegging.
正解:A、D
質問 # 28
You are reviewing the master data types for supply planning. Which master data types are compound master data types? Note: There are 2 correct Answers to this question.
- A. SOURCEPRODUCTION
- B. SOURCECUSTOMER
- C. sourcelocation
- D. LOCATIONFR
正解:B、C
質問 # 29
Which of the following are inputs to Demand Sensing with Gradient Boosting (Full) algorithm?Note: There are 2 correct answers to this question.
- A. Recommended Safety Stocks from Multistage Inventory Optimization
- B. Future Consensus Forecasts and Lagged Forecast Snapshots
- C. Forecast Error CV Calculated by Manage Forecast Error Calculations app
- D. Sales Order Quantities (both historical and future open orders)
正解:A、B
質問 # 30
What are some of the prerequisites for configuring a planning area that results in a successful consistency check? Note: There are 2 correct Answers to this question.
- A. Specify a planning horizon in the planning area for each level of the assigned time profile.
- B. Configure at most two input key figures on the same planning level in a key figure calculation.
- C. Configure at least one calculated key figure for the planning area.
- D. Assign the compound master data type and its component master data types.
正解:A、D
質問 # 31
You are starting a new implementation project for SAP IBP and are considering the possible system architecture.What are the possible approaches for setting up the system landscape?Note: There are 2 correct answers to this question.
- A. Set up a two-tier landscape, and have the configuration of the development system regularly updated from the production system.
- B. Create additional test planning areas in the production system to support cutover needs.
- C. Set up a three-tier landscape using transport, starting from the development system to test and production.
- D. Create additional planning areas in the test system to support training needs.
正解:A、C
質問 # 32
You are setting up planing with lot sizes.What are some of the properties of lot sizes that you need to be aware of?Note: There are 2 correct answers to this question.
- A. Lot sizes are applicable for production and handling quantities.
- B. Lot sizes are time-independent master data settings.
- C. Lot sizes are applicable for production and transportation quantities.
- D. Periodic lot size setting overrides the minimum lot size.
正解:A、B
質問 # 33
Which SAP IBP planning operator can be run to delete planning objects in a certain version?
- A. Purge Key Figure Data Outside Planning Area Planning Horizon
- B. Purge Non-Confirming Data
- C. Purge Key Figure Data
- D. Purge Master Data
正解:C
質問 # 34
......
結果を保証するには最新2023年05月無料:https://jp.fast2test.com/C-IBP-2205-premium-file.html
有効な問題最新版を無料で試そうC-IBP-2205試験問題集解答:https://drive.google.com/open?id=1QhlK5CIKCWTBURNcJ1AICtEb3o-DfDJE