質問 47
What are the three pillars of SAP Activate?
- A. Performance tuning
- B. Methodology
- C. SAP Best Practices
- D. Guided configuration
正解: A,B,C
質問 48
What are the effects when the planner release a maintenance order? choose 3 answers
- A. the planner can print the job papers
- B. the technician can record confirmations
- C. the planner CANNOT change planned costs
- D. the planner can estimate costs
- E. the warehouse clerk can post a goods issue
正解: A,B,E
質問 49
The first release of the SAP Asset Manager Mobile application is based on _______________.
- A. O Android only
- B. iOS, Android and Windows
- C. iOS and Android
- D. Windows only
- E. iOS only
正解: E
質問 50
When does the system create the entries in the web app job for the technician? choose 1 answer
- A. when the planner releases the maintenance order
- B. when the planner prints the job card
- C. when the planner performs capacity planning
- D. when the planner creates the maintenance order
正解: B
質問 51
What does a virtual data model provide?
- A. A copy of the database optimized for analytical use
- B. Ready-to-use business reports
- C. Reporting tools for users
- D. Consumption-ready views of data
正解: D
質問 52
What is the function of the print diversion setting?
- A. It tells the system that a shop paper for an order is ready to be printed.
- B. It enables you to define which shop papers are printed as a system default.
- C. It enables you to chose a printer based on certain fields in the order.
- D. It enables you to determine which papers are printed for the technician.
正解: C
質問 53
How SAP offer SAP Asset intelligent network? choose 1 answer
- A. as a cloud-based application
- B. as a license free SAP S4HANA add-on
- C. as a part of S4HANA on premise
- D. as a license-free ERP add-on
正解: A
質問 54
Which of the following pieces of information are available in the production order?
- A. None of the above
- B. Production instructions
- C. Production dates
- D. Order components
- E. Order costs
- F. All of the above
正解: F
質問 55
A piece of equipment cannot be linked to a material. Determine whether this statement is true or false.
- A. True
- B. False
正解: B
質問 56
The maintenance engineer creates a singel cycle plan with the following parameters:
* the call object is maintenance order
* the indicator or seprate completion of maintenance call date is NOT set
* the indicator for completion requirement is NOT activated
* both shift factors are set to 100% .
Which date is relevant for the calculation for further planned dates for all objects? choose 1 answer
- A. planned date of the next call number
- B. basic finish date of the maintenance order
- C. technical completion date of the maintenance order
- D. completion date of maintenance plan
正解: A
質問 57
You plan to use the integration of maintenance order and project system (PS) objects. to which PS objects can you assign a maintenance order? choose 2 answers
- A. project definition
- B. WBS element
- C. network header
- D. network operation
正解: A,B
質問 58
Which information does the usage list for equipement display? choose 1 answer
- A. validity periods
- B. operation hours
- C. material consumption
- D. Failure frequencey
正解: A
質問 59
Which of the following is true about a maintenance planning plant?
- A. The Plant at which the operational systems of a company are installed is called themaintenance plant.
- B. If maintenance work is planned at this plant, the maintenance plant is also themaintenance planning plant.
- C. The maintenance planning plant and the maintenance plant can never be the same.
- D. It is the highest-level element of all the organizational units.
正解: A,B
質問 60
In which object can you change the offset of a maintenance plan strategy? choose 1 answer
- A. maintenance package
- B. maintenance plan header
- C. maintenance plan item
- D. maintenance plan category
正解: A
質問 61
What characterizes the architecture of a simple application?
- A. Reduction in number of tables
- B. Works with any database
- C. Use of dedicated aggregation tables
- D. Push data-intensive tasks to SAP HANA
- E. No data redundancy
正解: A,D,E
質問 62
During the implementation project, you need to define the organizational units. Which of the following objects can you directly assign a maintenance plant?
- A. controlling area
- B. maintenance planner group
- C. maintenance work center
- D. location
正解: D
質問 63
Which order type do you need when you refurbish defective parts? choose 1 answer
- A. order type with investement indicator
- B. order type with refurbishment indicator
- C. order type breakdown maintenance
- D. order type of pereventive maintenance
正解: B