質問 # 13
What are the three key items communicated on the Program Board? (Choose three.)

  • A. Dependencies between teams
  • B. PI Objectives
  • C. Feature delivery dates
  • D. Team velocity
  • E. Milestones
  • F. Program risks

正解:A、C、E


質問 # 14
What is the best way for the Release Train Engineer to show progress of work in the cur-rent Program Increment (PI) to management?

  • A. Generate a velocity trend report
  • B. Conduct a System Demo
  • C. Arrange for a separate meeting with Business Owners
  • D. Conduct a retrospective

正解:B


質問 # 15
Which two actions can be taken immediately during the management review and prob-lem-solving meeting? (Choose two.)

  • A. Hire new people
  • B. Change the scope
  • C. Combine teams to increase velocity
  • D. Change the business priorities
  • E. Recognize the team with the highest velocity

正解:B、D


質問 # 16
Which activity takes place during Team Breakout #2 on the second day of Program In-crement (PI) Planning?

  • A. All Feature delivery and dependencies are visualized on the program board
  • B. Business Owners assign business value without team discussion so they can nor-malize business value across all teams on the Agile Release Train
  • C. The Release Train Engineer (RTE) combines all Team PI Objectives into Program PI Objectives
  • D. The RTE modifies the PI Iteration schedule, if needed, based on the scope of high priority Features

正解:A


質問 # 17
Which tool can the Release Train Engineer use to visualize the flow of value?

  • A. Team burn-down charts
  • B. Weighted shorted job first
  • C. Velocity trend charts
  • D. Kanban systems

正解:D


質問 # 18
What are two examples of team-level events? (Choose two.)

  • A. System Demo
  • B. Daily stand-up
  • C. Program Increment Planning
  • D. Backlog refinement

正解:B


質問 # 19
Which two actions can the Release Train Engineer take to facilitate team growth? (Choose two.)

  • A. Encourage skill specialization
  • B. Facilitate conflict
  • C. Ensure time is allocated for innovation and planning
  • D. Encourage continuous learning
  • E. Provide a team vision

正解:C、D


質問 # 20
What is a primary responsibility of Business Owners in Program Increment (Pl) Planning?

  • A. To ensure that team members plan all of their priorities
  • B. To set the business context
  • C. To establish the Pl budget

正解:B


質問 # 21
What is the primary purpose of PO sync?

  • A. To build objectives for the Program Increment
  • B. To align with the scrum of scrums participants on the status of the Program Increment
  • C. To assess progress of the Program Increment and adjust scope and priority as needed

正解:C


質問 # 22
Product Management is expected to collaborate in planning the amount of upcoming En-abler work by establishing what?

  • A. Capacity allocation
  • B. Completed Epic acceptance criteria
  • C. Team Backlog prioritization

正解:A


質問 # 23
At the end of day two of the Program Increment (PI) Planning event, the team's final plan review covers what information?

  • A. Planned Features, uncommitted objectives, and ROAMed risks
  • B. Changes to capacity and load, final PI objectives, program risks and impediments
  • C. Changes to iteration goals, measured velocity, and dependencies
  • D. Team Features, Stories, and team-level enablers

正解:B


質問 # 24
In SAFe, which activity is a Scrum Master's responsibility?

  • A. Coordinating with other teams
  • B. Owning the daily stand-up
  • C. Facilitating the Scrum of Scrums
  • D. Prioritizing the Team Backlog

正解:A


質問 # 25
In what way is a value stream map different from a process flow?

  • A. A value stream map uncovers local problems in functional organizations
  • B. A value stream map can be operational or developmental; process flows are only operational
  • C. A value stream map measures the flow of value and identifies bottlenecks for improvement
  • D. A value stream map is used to define Solution Context

正解:C


質問 # 26
Which statement is true about the retrospective and problem-solving part of the Inspect and Adapt workshop?

  • A. Key Agile Release Train stakeholders, including Business Owners, Customers, and management can participate along with the teams
  • B. The Release Train Engineer gathers the list of problems to be solved during the fi-nal scrum of scrums of the Program Increment (PI)
  • C. The improvement backlog items resulting from the problem-solving workshop should be items that only leadership can address
  • D. Encourage teams to sit together during the retrospective portion to ensure an ef-fective outcome

正解:A


質問 # 27
What are two purposes of the System Demo? (Choose two.)

  • A. To demonstrate a team's build
  • B. To exercise the performance of the staging area
  • C. To conduct the Inspect and Adapt workshop
  • D. To demonstrate the full solution in a production-like context
  • E. To get feedback from the primary stakeholders

正解:D


質問 # 28
When is the Inspect and Adapt event held?

  • A. At the end of the Program Increment (PI)
  • B. During the Program Increment (PI)
  • C. At the end of every Iteration
  • D. After the System Demo

正解:A


質問 # 29
What does transparency mean in a scrum environment?

  • A. Team members must immediately share any and all feedback with each other
  • B. Development and Operations teams work together
  • C. The process is visible to all stakeholders
  • D. The team is constantly improving its process

正解:C


質問 # 30
What is the most accurate definition of DevOps?

  • A. A set of tools and processes that govern how code is deployed
  • B. A method that ensures Operations works with Development every day to deliver value
  • C. A process that provides visibility to impediments between writing code and deliv-ering value
  • D. A mindset, culture, and set of technical practices that emphasizes close coopera-tion to provide value to the Customer

正解:D


質問 # 31
The Release Train Engineer (RTE) is to attend multiple reviews and status meetings to discuss the Agile Release Train's (ART) progress at the end of each Iteration. What ac-tion could the RTE take to manage expectations?

  • A. Encourage interested parties to attend the System Demo
  • B. Delegate some program reporting and meeting attendance to Scrum Masters on the train
  • C. Make status available at the end of every other Iteration rather than every Itera-tion
  • D. Determine the RTE's capacity for attending meetings and do not exceed it

正解:A


質問 # 32
What are two purposes of a community of practice? (Choose two.)

  • A. To share knowledge and skills
  • B. To align tasks across teams
  • C. To network
  • D. To approve standards
  • E. To refine definitions of done

正解:A、C


質問 # 33
What can occur as a result of not having an Innovation and Planning Iteration?

  • A. Teams can have no time for fixing bugs
  • B. Delivery can be stifled incrementally
  • C. Bottlenecks can be hard to identify and resolve
  • D. Technical debt can grow uncontrollably

正解:D


質問 # 34
What are two benefits of having a well-executed Innovation and Planning (IP) Iteration? (Choose two.)

  • A. Occasional buffer time to deliver more predictably
  • B. Time for teams to plan, demo and improve together
  • C. Shorter lead times before Feature delivery
  • D. Improved dependency management between teams
  • E. Higher flow of program-level business value

正解:B、C


質問 # 35
A group of developers, Scrums Masters, and Product Owners are interested in sharing knowledge and learning more about DevOps concepts. How can the Release Train Engi-neer help them collaborate to gain knowledge about DevOps?

  • A. Help them launch a DevOps community of practice
  • B. Provide Devops training
  • C. Schedule a DevOps bi-weekly synchronization
  • D. Align them with the System Team

正解:A


質問 # 36
What practice can help to identify bottlenecks in the flow of work?

  • A. Comparing transaction costs, holding costs and business value realization
  • B. Visualizing the flow of all work and track progress of individual items
  • C. Modeling overall process flow during value stream identification
  • D. Measuring lead time for all work in progress

正解:C


質問 # 37
......


試験概要:SAFe-RTE試験は、120分以内に60問に答える必要がある多肢選択試験です。試験の合格点は73%であり、試験に合格するとSAFe RTE認定を受け取ります。試験は、アジャイル原則、SAFeフレームワーク、リーダーシップスキル、リリーストレインマネジメントなど、幅広いトピックをカバーしています。

 

検証済み!合格できるSAFe-RTE試験一発合格保証付き:https://jp.fast2test.com/SAFe-RTE-premium-file.html

Scaled Agile SAFe-RTEリアル試験問題保証付き 更新された問題集にはFast2test:https://drive.google.com/open?id=1jg4ULAORgVo7us-he1ybfEoUH1APckyO


弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

我々の働いている時間: ( GMT 0:00-15:00 )
月曜日から土曜日まで

サポート: 現在連絡 

English Deutsch 繁体中文 한국어