質問 # 15
Select all the true statements about Nexus.
- A. There is always one Scrum Master in a Nexus
- B. There is always one Product Owner in a Nexus
- C. There should be separate Product Owner per team
- D. There is always one Product backlog in a Nexus
正解:B、D
質問 # 16
The Nexus Team has failed to meet the Nexus Sprint Goal for two sprints in a row.
What are the possible reasons for this? (Select two best answers)
- A. Definition of Done has too stringent
- B. Nexus Integration Team is not coordinating the work among the developers
- C. Developers are struggling to integrate their work
- D. There is technical debt in the product
正解:C、D
質問 # 17
Definition of Done is always same for Nexus and all individual Scrum Teams. True or False?
- A. FALSE
- B. TRUE
正解:A
質問 # 18
What is the purpose of Nexus Sprint Backlog? Select two best answers
- A. To provide a view of work that is not part of the product backlog
- B. To make the dependencies transparent
- C. To list all the work that is being performed by the Nexus Integration Team
- D. To highlight the flow of work during the Sprint
正解:B、D
質問 # 19
During which event the Definition of Done is most likely to be adjusted?
- A. Nexus Sprint Planning
- B. Nexus Sprint Retrospective
- C. Nexus Daily Scrum
- D. Nexus Sprint Review
正解:B
質問 # 20
Which event is present in Scrum but not in Nexus?
- A. Sprint Review
- B. Daily Scrum
- C. Sprint Planning
- D. Sprint Retrospective
正解:A
質問 # 21
What is true about Nexus Sprint Goal? Select all that apply.
- A. It replaces the Sprint Goal of individual team
- B. It is the sum of all the work and Sprint Goals of the Scrum Teams within the Nexus
- C. Every Nexus member should understand the Nexus Sprint Goal and should work towards achieving it
- D. It is the objective for the Sprint
正解:B、C、D
質問 # 22
During the first 2 Sprints of a product development, Team A's velocity is 10 points whereas Team B's velocity is 20 points.
Which team is performing better?
- A. Team B is performing better
- B. Team A is performing better
- C. Team's performance cannot be determined by comparing the velocity of another team
正解:C
質問 # 23
Who is accountable for managing Product Backlog in Nexus?
- A. Product Owner
- B. Development Teams
- C. Scrum Master
- D. Nexus Integration Team
正解:A
質問 # 24
How much refinement is needed for Product Backlog items?
- A. Until the Stakeholders are satisifed
- B. Until the Product Backlog item is discussed in 3 different sessions
- C. Until the Product Backlog Items are sufficiently independent to be worked on by a single Scrum Team without excessive conflict
正解:C
質問 # 25
In a Nexus, it is agreed that the representatives from each team will participate in the Nexus Sprint Planning to select the Product backlog items for the sprint. They were struggling to find the items with fewer dependencies. There are especially three teams that have a lot of dependent work.
What should the Nexus do to avoid this problem going forward?
- A. Instruct the Nexus Integration Team to perform the product backlog refinement
- B. Reorganize the teams that often have work with a lot of dependencies
- C. Merge the teams that often have work with a lot of dependencies
- D. Increase the Cross-Team refinement activity duration
正解:D
質問 # 26
Changes to the core Scrum framework are needed to be successful with Scrum at large scale. True or False?
- A. FALSE
- B. TRUE
正解:A
質問 # 27
At the end of the 12th Sprint in a Nexus, it is observed that most of the teams are unable to complete the planned work in last 3 Sprints.
What is the most likely reason?
- A. Product Owner is having too much expectation and pushing the teams to deliver more
- B. NIT is not doing the work they are supposed to
- C. Teams are overestimating and selecting too much work during the planning
- D. There is technical debt in the product
正解:D
質問 # 28
Which is not a mandatory event in Scrum but a mandatory event in Nexus?
- A. Daily Scrum
- B. Sprint Retrospective
- C. Sprint Review
- D. Cross-Team Refinement
正解:D
質問 # 29
Nexus requires the overall architecture to be designed and finalized before the Sprints can begin. True or False?
- A. FALSE
- B. TRUE
正解:A
質問 # 30
......