質問 # 29
Which accelerators support the Fit-to-standard workshop in the explore phase? There are 2 correct answers to this question

  • A. Business-Driven configuration Questionnaire
  • B. Quality gate checklist
  • C. Test strategy
  • D. Backing template

正解:A、C


質問 # 30
What activity do you perform during the daily stand-up meeting?

  • A. Negotiate acceptance criteria
  • B. Provide end users with a demo of the new features
  • C. Report showstoppers.
  • D. Re-baseline the release plan

正解:C

解説:
C is correct because reporting showstoppers is one of the activities that you perform during the daily stand-up meeting. A showstopper is an issue or impediment that prevents the team from completing their sprint goal or user story. The scrum master is responsible for resolving or escalating the showstoppers as soon as possible. Verified :


質問 # 31
What accelerator can help you document the configuration definition in the Explore phase?

  • A. Change request template
  • B. Test strategy
  • C. Data definition
  • D. Backlog template

正解:D


質問 # 32
What is the difference between the "New Implementation of SAP S/4HANA Cloud, public edition" and the "New Implementation of SAP S/4HANA, private edition" transition paths? Note: There are 2 correct answers to this question

  • A. Upgrades of SAP S/4HANA Cloud, public edition are based on SAP timelines, and upgrades of SAP S/4HANA Cloud private edition are based on timelines agreed between SAP and the customer
  • B. SAP S/4HANA Cloud, public edition does NOT offer built-in capabilities for extensibility, while SAP S/4HANA Cloud, private edition offers a full development environment
  • C. SAP S/4HANA Cloud, private edition uses the Implementation Guide (IMG) and SAP S/4HANA Cloud, public edition uses SAP Central Business Configuration.
  • D. -I SAP S/4HANA Cloud, private edition is only available through SAP Cloud services and with embedded implementation services from SAP

正解:A、C

解説:
C is correct because upgrades of SAP S/4HANA Cloud, public edition are based on SAP timelines, and upgrades of SAP S/4HANA Cloud, private edition are based on timelines agreed between SAP and the customer. This is one of the differences between the two transition paths. SAP S/4HANA Cloud, public edition has mandatory quarterly upgrades that are performed by SAP, while SAP S/4HANA Cloud, private edition has optional upgrades that are scheduled by the customer in coordination with SAP.
D is correct because SAP S/4HANA Cloud, private edition uses the Implementation Guide (IMG) and SAP S/4HANA Cloud, public edition uses SAP Central Business Configuration. This is another difference between the two transition paths. SAP S/4HANA Cloud, private edition allows more flexibility and customization in the configuration, while SAP S/4HANA Cloud, public edition follows a guided and standardized configuration process. Verified :
: [SAP S/4HANA Cloud Editions]
: [Central Business Configuration Overview]


質問 # 33
In which of the following do you use a work item in Focused Build?

  • A. Epics
  • B. Releases
  • C. Sprints
  • D. Waves

正解:C


質問 # 34
Who determines the tasks that are required to complete the committed backlog items in a Sprint?

  • A. Scrum master
  • B. Product owner
  • C. Scrum team
  • D. Project manager

正解:C


質問 # 35
What is the objective of a sprint retrospective meeting?

  • A. Provide formal feedback to the Project Manager.
  • B. Review and prioritize the backlog.
  • C. Improve the Scrum process.
  • D. Define the stakeholder management approach

正解:C


質問 # 36
Which of the following are benefits of using ready-to-use content?
There are 2 correct answers to this question

  • A. CD Predictable results
  • B. Minimized total cost of ownership
  • C. Run SAP like a factory
  • D. Fast time-to-value

正解:A、D


質問 # 37
In which phase do you collect the main attributes of the product as per the Agile definition?

  • A. Prepare
  • B. Realize
  • C. Deploy
  • D. Explore

正解:D

解説:
According to the SAP Activate methodology for SAP S/4HANA Cloud, the Explore phase is where you collect the main attributes of the product as per the Agile definition. The main attributes of the product are the features, requirements, and user stories that describe what the product should do and how it should deliver value to the customers and stakeholders. The Explore phase involves a fit-to-standard process, where you validate the fit of your business processes to the standard SAP solution and identify any gaps or extensions that need to be addressed. You also prioritize and refine your product backlog, which is a list of user stories that represent the work needed to achieve the product vision1.


質問 # 38
What criterion does the product owner use to sequence the product backlog?

  • A. Relative effort
  • B. Business priority
  • C. Complexity
  • D. Resource availability

正解:B

解説:
A is correct because the product owner is responsible for prioritizing the product backlog based on the business value and urgency of each user story3. Verified :
3: SAP Activate Project Management Certification Guide, page 112


質問 # 39
Your customer is using a non-SAP ERP system and decides to implement SAP S/4HANA. Which of the following options are available to your customer?Note: There are 3 correct answers to this question.

  • A. System Conversion SAP S/4HANA
  • B. New Implementation SAP S/4HANA Cloud, public edition
  • C. New Implementation SAP S/4HANA Cloud, private edition
  • D. System Conversion SAP S/4HANA Cloud, private edition
  • E. New Implementation SAP S/4HANA

正解:B、C、E


質問 # 40
Which of the following capabilities does SAP Solution Manager Test Suite support? Note: There are 2 correct answers to this question.

  • A. Tests for SAP and non-SAP solutions
  • B. Load and volume testing
  • C. Multi-technology change impact analysis
  • D. Manual and automated functional tests

正解:A、D

解説:
B is correct because tests for SAP and non-SAP solutions are one of the capabilities that SAP Solution Manager Test Suite supports. The Test Suite allows customers to create and execute manual and automated tests for both SAP and non-SAP solutions using a single tool. The Test Suite integrates with various testing tools from SAP and partners to support different types of testing scenarios.
C is correct because manual and automated functional tests are one of the capabilities that SAP Solution Manager Test Suite supports. The Test Suite enables customers to perform manual testing based on test case descriptions or automated testing using test scripts. The Test Suite supports various test automation frameworks such as Component Based Test Automation (CBTA), Tricentis Test Automation (TTA), eCATTs, HP QuickTest Professional (QTP), Worksoft Certify, IBM Rational Functional Tester (RFT), Selenium WebDriver, etc. Verified :


質問 # 41
Which activity helps the project team identify and add user stories to the backlog?

  • A. Preparing a project schedule and budget
  • B. Assessing project risks and issues
  • C. Planning the User Acceptance Testing
  • D. Conducting the fit-to-standard workshop

正解:D

解説:
B is correct because conducting the fit-to-standard workshop helps the project team identify and add user stories to the backlog. The fit-to-standard workshop is a process of analyzing the gaps between the customer's business requirements and the standard SAP functionality, and documenting the user stories that describe the desired outcomes and acceptance criteria. Verified :


質問 # 42
What criterion does the product owner use to sequence the product backlog?

  • A. Relative effort
  • B. Business priority
  • C. Complexity
  • D. Resource availability

正解:B


質問 # 43
Which of the following are levels in the structure of an SAP Best Practices for SAP S/4HANA Solution Package?Note: There are 2 correct answers to this question.

  • A. Configuration Guides
  • B. Scope Items
  • C. Business Process Scenarios
  • D. Building Blocks

正解:B、D


質問 # 44
Which tool do you use to configure SAP S/4HANA Cloud, public edition?

  • A. SAP Solution Manager
  • B. SAP Central Business Configuration
  • C. SAP Cloud ALM
  • D. IMG (Implementation Guide)

正解:B


質問 # 45
In which phase do you create "an ordered list of everything that is known to be needed in the Product?

  • A. Realize
  • B. Deploy
  • C. Prepare
  • D. Explore

正解:C


質問 # 46
What is the objective of using scaling Scrum techniques when coordinating large teams in complex projects?

  • A. To ensure alignment in architecture, configuration, and integration
  • B. To reallocate staff to skill-based teams such as developers in one single team
  • C. To bring all specialists, such as the company legal advisors, into the scrum team
  • D. To manage the flow of information between the project and stakeholders

正解:A

解説:
C is correct because ensuring alignment in architecture, configuration, and integration is one of the objectives of using scaling Scrum techniques when coordinating large teams in complex projects. Scaling Scrum techniques are methods that help to apply Scrum principles and practices across multiple teams working on a large-scale product or program. Scaling Scrum techniques aim to ensure alignment in architecture, configuration, and integration by establishing a common vision, backlog, definition of done, and cadence for the teams, and by facilitating cross-team communication and collaboration


質問 # 47
......


SAP C_ACTIVATE22 認定試験の出題範囲:

トピック出題範囲
トピック 1
  • Introduce the SAP Activate solution adoption framework and its content prvisioning tools
  • SAP Activate Methodology Foundation and Tools
トピック 2
  • Describe how the project team prepares release and sprint plans
  • Explain how to transform your existing SAP system into an SAP S
  • 4HANA solution
トピック 3
  • Describe the different activities of an SAP project
  • Explain how to build solutions following a cloud-oriented approach
トピック 4
  • Explain how to transform your existing solution into SAP S
  • 4HANA on premise
  • Transition Path "System Conversion" and "Selective Data Transition"
トピック 5
  • Describe the methodology foundation, its phases, and key activities
  • Explain how to transform your existing solution into SAP S
  • 4HANA Cloud

 

C_ACTIVATE22正真正銘のベスト資料、オンライン練習試験:https://jp.fast2test.com/C_ACTIVATE22-premium-file.html


弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

我々の働いている時間: ( GMT 0:00-15:00 )
月曜日から土曜日まで

サポート: 現在連絡 

English Deutsch 繁体中文 한국어