質問 # 26
アイデア [im_idea_core] はどのテーブルから直接拡張されていますか?
- A. どのテーブルからも拡張されていません
- B. プロジェクト
- C. タスク
- D. アイデア モジュール
正解:A
解説:
According to the ServiceNow documentation1, the Idea [im_idea_core] table is a base table that is not extended from any other table. It stores information about ideas and their categories. The other options are incorrect because:
Task: The Task table is a base table that is extended by many other tables, such as Project, Demand, Incident, etc2.
Idea Modules: The Idea Modules table is a child table of the Idea [im_idea_core] table that defines the idea modules displayed on the Idea Portal3.
Project: The Project table is a child table of the Task table that stores information about projects.
1:
https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/demand-management/refe
https://docs.servicenow.com/bundle/vancouver-platform-administration/page/administer/table-administration/con
https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/demand-management/refe
:
https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/project-management/refer
質問 # 27
サブプロジェクトと親プロジェクトのプロジェクト通貨が異なる場合、コストの積み上げに対してこのプロパティを true に設定する必要があります。
- A. com.snc.project.multicurrency.rollup_if_Difference
- B. com.snc.project.calculate_roi
- C. com.snc.project.rollup_project_start_date
- D. com.snc.project.copy.Additional_attributes
正解:A
質問 # 28
プロジェクト マネージャーがチーム メンバーに代わってタイムシートを承認したり、タイム カードを提出したりする責任がある場合、どのような役割を与える必要がありますか?
- A. タイムカード管理者。
- B. 承認管理者。
- C. activity_admin.
- D. フォーム管理者。
正解:A
解説:
According to the ServiceNow documentation1, the timecard_admin role can approve time sheets or submit time cards on behalf of team members. This role also has the ability to create and modify time sheet policies, time sheet groups, and time sheet periods. The other options are incorrect because:
A: activity_admin: The activity_admin role can create and modify activities, activity sets, and activity plans2.
C: form_admin: The form_admin role can create and modify forms, form sections, and form layouts3.
D: approval_admin: The approval_admin role can create and modify approval rules, approval groups, and approval stages4.
1:
https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/time-card-management/ref
https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/project-management/refer
https://docs.servicenow.com/bundle/vancouver-platform-administration/page/administer/form-administration/con
https://docs.servicenow.com/bundle/vancouver-platform-administration/page/administer/approvals/concept/c_Ap
質問 # 29
リソース計画の作成時に計画コストの計算に使用できるものは次のうちどれですか?
2 つの答えを選択してください
- A. 需要率
- B. 料金表
- C. デフォルトレート
- D. プロジェクトレート
正解:B、D
解説:
According to the ServiceNow documentation1, a rate card is a table that defines the hourly cost of labor for different roles or resources. A project rate is a fixed rate that is applied to all resources assigned to a project, regardless of their roles or individual rates. Both of these can be used to calculate the planned cost of a resource plan by multiplying the hours allocated to each resource by the corresponding rate. The other options are incorrect because:
A: Demand rate: A demand rate is a rate that is applied to a demand, not a resource plan. It is used to estimate the cost of fulfilling a demand before it is converted into a project2.
C: Default rate: A default rate is a rate that is applied to a resource when no other rate is specified. It is not a valid option for calculating the planned cost of a resource plan, as it is only used as a fallback option3.
1:
https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/resource-management/con
https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/demand-management/conc
https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/resource-management/con
質問 # 30
デマンド マネージャーは、デマンドからのアーティファクトを表示できます。デマンドにはどのような成果物が含まれますか?
- A. 意思決定、リスク、要件。
- B. ストーリー、脆弱性タスク、機能強化。
- C. プロジェクト、欠陥、リクエスト。
- D. インシデント、問題、変化。
正解:A
解説:
According to the ServiceNow documentation1, a demand manager can view and edit the following artifacts from a demand:
Decision: A decision that affects the demand or its outcome2.
Risk: A risk that could impact the demand or its outcome3.
Requirement: A requirement that defines the scope or functionality of the demand4.
The other options are not artifacts of a demand, but rather related entities that can be created from a demand or linked to a demand.
1:
https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/demand-management/conc
https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/demand-management/task
https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/demand-management/task
https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/demand-management/task
質問 # 31
ユーザーがリリース管理アプリケーションのテーブルからデータを読み取ってレポートを生成できるようにするには、どのロールをユーザーに割り当てる必要がありますか?
- A. リリース管理者
- B. ビジネス関係者
- C. ユーザーを解放します
- D. プロジェクト マネージャー
正解:B
解説:
According to the Product Documentation for ServiceNow, the business stakeholder role (rm_business_stakeholder) can read and retrieve data from any table of the Release Management application to generate reports. This role can also view the release dashboard, release calendar, and release roadmap. The other roles have different levels of access and permissions for the Release Management application. You can find more information about the roles and responsibilities for Release Management in the Product Documentation for ServiceNow.
質問 # 32
ユーザーの可用性は次のように計算されます。
- A. 割り当てられた時間
- B. 割り当てられた時間を総キャパシティで割った値
- C. 割り当てられた時間と確認された時間の合計を総キャパシティで割ったもの
- D. 容量から割り当てを差し引いた値
正解:B
解説:
According to the ServiceNow documentation1, a user's availability is calculated as the ratio of allocated hours to total capacity, expressed as a percentage. Allocated hours are the hours that a user is assigned to work on a project or demand. Total capacity is the maximum number of hours that a user can work in a given period, based on their schedule and availability profile. A user's availability indicates how much of their time is already allocated and how much is still available for new assignments.
1:
https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/resource-management/con
質問 # 33
ユーザーはタイムカードを記録する際に、自分の仕事に対して複数の料金タイプからいつ選択できますか?
- A. 適用できる料金タイプは 1 つだけです
- B. タイムシート ポリシーで機能が有効になっている場合のみ
- C. この機能がプロジェクト レコードで有効になっている場合のみ
- D. 機能がプロジェクト設定で有効になっている場合のみ
正解:B
解説:
According to the Using rate types and labor rate cards document, a user can choose from multiple rate types for their work, while logging a time card, only if the capability is enabled in the Time Sheet Policies. This capability allows users to select different rate types for different tasks, such as standard, overtime, or travel.
The other options are not correct, as they are not the places where the capability can be enabled. The Project Record is used to create and update project details, such as name, description, and state. The Project Preferences are used to set the default values for project fields, such as number, type, and priority. The option C is not correct, as more than one rate type can apply if the capability is enabled.
質問 # 34
リソース計画の対象となるのはどのような役割を持つユーザーですか?
- A. pps_resource.
- B. it_pps_user.
- C. it_user。
- D. it_project_user。
正解:A
解説:
According to the ServiceNow Resource Management document, users with the pps_resource role can be considered for resource planning, as this role grants access to the Resource Management application and allows the users to view and update their resource allocations. The other options are not correct, as they are not roles that are related to resource planning. The it_project_user role grants access to the Project Portfolio Management application and allows the users to create and update projects. The it_user role grants access to the IT Service Management application and allows the users to manage incidents, problems, and changes. The it_pps_user role grants access to the Project Portfolio Suite application and allows the users to manage portfolios, programs, and projects.
質問 # 35
ソース プロジェクトをターゲット プロジェクトにコピーする場合、デフォルトではどのフィールドがコピーされますか?
3 つの答えを選択してください
- A. 短い説明。
- B. 数値。
- C. 予定されている日付。
- D. 期間フィールド。
- E. 状態
正解:A、C、D
質問 # 36
リソース プランを通じて要求された「ロール」はどこで定義しますか?
- A. リソース管理下のリソースの役割。
- B. スキル管理モジュールの下。
- C. システム ロールと同じなので、別に定義する必要はありません。
- D. システムセキュリティ下の役割。
正解:A
解説:
According to the Assigning Resource Roles document, you define 'Roles' requested via resource plans under resource roles in the Resource Management application. Resource roles are the roles that users can request or allocate for resource plans. The other options are not correct, as they are not the places where you define
'Roles' requested via resource plans. The system roles are the roles that grant access to various applications and modules in the system. The roles under system security are the roles that control the security settings and permissions for the system. The skill management modules are the modules that manage the skills and skill levels of users and groups.
質問 # 37
サブプロジェクトと親プロジェクトのプロジェクト通貨が異なる場合、コストの積み上げに対してこのプロパティを true に設定する必要があります。
- A. com.snc.project.multicurrency.rollup_if_Difference
- B. com.snc.project.calculate_roi
- C. com.snc.project.rollup_project_start_date
- D. com.snc.project.copy.Additional_attributes
正解:A
解説:
According to the ServiceNow documentation1, this property controls whether the cost roll-ups are performed when a sub-project and parent project have different project currencies. If this property is set to true, then the system converts the sub-project currency to the parent project currency using the exchange rate table and performs the cost roll-ups. If this property is set to false, then the system does not perform the cost roll-ups for sub-projects with different currencies.
1:
https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/project-management/refer
質問 # 38
リソース プランの [リクエスト タイプ] フィールドを使用して、リソースをリクエストするためにどのオプションを使用できますか?
3 つの答えを選択してください
- A. 時間
- B. FTE
- C. 日
- D. 月
- E. 人日
正解:A、B、E
解説:
Using the Request type field on a resource plan, you can request a resource by specifying the amount of FTE, person days, or hours that you need for a task or a project. FTE stands for full-time equivalent and represents the percentage of a standard work week that a resource can perform. Person days are the number of days that a resource works on a task or a project. Hours are the number of hours that a resource works on a task or a project. You can find more information about the Request type field in the Product Documentation for ServiceNow.
質問 # 39
デマンドワークベンチは何に使用されますか?
2 つの答えを選択してください
- A. 要求を他の要求と比較して優先順位を付ける
- B. アイデアの承認
- C. 需要とポートフォリオの比較
- D. 要求の承認
正解:A、C
解説:
The demand workbench is a feature of ServiceNow Demand Management that allows you to view and assess business demands in a single place. You can use the demand workbench to compare demands with portfolios and see how they align with your strategic goals and objectives. You can also use the demand workbench to compare and prioritize demands against other demands based on their scores, risks, and benefits. You can find more information about the demand workbench in the Product Documentation for ServiceNow.
質問 # 40
Scenario Planning for PPM がインストールされている場合、ポートフォリオ マネージャーは次のどれに移動してポートフォリオ プランニング ワークベンチにアクセスできますか?
2 つの答えを選択してください
- A. プロジェクトモジュール
- B. ポートフォリオ プランニング ワークベンチ モジュール
- C. ポートフォリオ プランニング関連リンク
- D. プログラム ワークベンチ
正解:B、C
解説:
According to the Scenario Planning for PPM document, a portfolio manager can access the Portfolio Planning Workbench by navigating to either the Portfolio Planning related link on the portfolio form or the Portfolio Planning Workbench module under the Portfolio Planning application menu. The other options are not correct, as they do not lead to the Portfolio Planning Workbench. The Project module is under the Project Portfolio Management application menu and the Program Workbench is under the Program Management application menu.
質問 # 41
「WIP プロジェクトのプロジェクトを移動」プロパティが有効になっている場合、次のどの状態のタスクを除く、プロジェクトに関連付けられているプロジェクト タスクも移動されます。
2 つの答えを選択してください
- A. 保留中
- B. 開く
- C. 進行中の作業
- D. クローズ済み
正解:C、D
解説:
According to the Planning Console document, if the 'Move project for WIP projects' property is enabled, project tasks associated with the project are also moved, except for tasks in the Work in Progress or Closed states. The other options are not correct, as tasks in the Pending or Open states are moved along with the project.
質問 # 42
需要フォームでは、割引率はどのような影響を与えますか?
- A. ROI。
- B. 経済的利益。
- C. 正味現在価値 (NPV)。
- D. 内部収益率 %。
正解:C
解説:
According to the ServiceNow documentation1, the discount rate on the demand form impacts the net present value (NPV) of the demand. The NPV is the difference between the present value of the benefits and the present value of the costs of the demand. The discount rate is the rate used to discount future cash flows to their present value. A higher discount rate means that future cash flows are worth less in the present, and vice versa. The other options are incorrect because:
A: ROI: The ROI (return on investment) is the ratio of the net value to the estimated cost of the demand. The discount rate does not affect the ROI, as both the net value and the estimated cost are based on the present value of the cash flows2.
C: Financial Benefit: The financial benefit is the sum of the present value of the benefits of the demand. The discount rate does not affect the financial benefit directly, but only indirectly through the NPV calculation3.
D: Internal Rate of Return %: The internal rate of return % (IRR) is the discount rate that makes the NPV of the demand equal to zero. The discount rate does not affect the IRR, but rather the IRR is derived from the NPV equation4.
1:
https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/demand-management/refe
https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/demand-management/conc
https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/demand-management/conc
https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/demand-management/conc
質問 # 43
タイムカードから実績工数を更新するプロジェクトプロパティはどのレベルで制御されますか?
- A. プロジェクト レベル。
- B. ポートフォリオ レベル。
- C. プログラム レベル。
- D. アプリケーション レベル (グローバル)。
正解:A
解説:
According to the ServiceNow documentation1, the project property to update actual effort from time card is controlled at the project level. This property is called Update actual effort from time card and it determines if the Actual effort field on the Dates tab should be updated based on the hours entered from time cards for the project. If set to Yes, the Actual effort field is read-only on the Project and Project Task forms. If set to No, the Actual effort field is editable on the Project and Project Task forms.
1:
https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/project-management/refer
質問 # 44
プログラムは、次のものを除くコンテナです。
- A. プログラムタスク
- B. 問題
- C. ポートフォリオ
- D. コスト計画
正解:C
解説:
According to the ServiceNow documentation1, a program is a container for the following:
Program tasks: Tasks that define the scope and deliverables of the program2.
Issues: Problems that affect the program or its outcome3.
Cost plans: Plans that estimate the cost of the program and its components4.
A portfolio is not a part of a program, but rather a collection of programs and projects that are aligned with a strategic goal or objective.
1:
https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/project-portfolio-managem
https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/project-portfolio-managem
https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/project-portfolio-managem
https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/project-portfolio-managem
:
https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/project-portfolio-managem
質問 # 45
後で比較レポートに使用できる、現在のプロジェクトのタスク、スケジュール、または構造のデータ コピーとは何ですか?
- A. 発生額
- B. 予報
- C. コミットメント
- D. ベースライン
正解:D
解説:
A baseline is a data copy of the current project's task, schedule, or structure that can be used for comparison reporting later. A baseline captures the original plan of the project and allows you to track the changes and deviations from the plan over time. You can create multiple baselines for a project and compare them with the current state of the project. You can find more information about baselines in the Product Documentation for ServiceNow.
質問 # 46
アイデアを効率的に収集して評価し、実装するアイデアを迅速に特定するためにアイデア モジュールをアクティブにするプラグインはどれですか?
- A. PPM によるアイデア
- B. リソース管理
- C. テスト管理 2.0
- D. アジャイル開発 2.0
正解:A
解説:
According to the Innovation Management document, the plugin that activates the Ideas module to gather and evaluate ideas efficiently, and quickly identify ideas for implementation is Ideation with PPM. This plugin enables the Innovation Management application, which allows organizations and employees to collect, vote on, manage, and collaborate on ideas from a centralized location. The other options are not correct, as they are not plugins that activate the Ideas module. Test Management 2.0 is a plugin that enables the Test Management
2.0 application, which allows users to create, plan, and execute tests. Agile Development 2.0 is a plugin that enables the Agile Development 2.0 application, which allows users to manage scrum or development work throughout the lifecycle. Resource Management is a plugin that enables the Resource Management application, which allows users to manage resource plans and allocations.
質問 # 47
ユーザーがデマンドワークベンチから新しいデマンドを作成した場合、システムはレコードをどのような状態で保存しますか?
- A. 承認されました
- B. ドラフト
- C. 修飾されています
- D. オープン
正解:C
解説:
According to the Using the Demand Workbench document, if a user creates a new demand from the demand workbench, the system saves the record in the qualified state and displays it on the bubble chart. The other options are not correct, as they are not the default state for a new demand created from the demand workbench.
The approved state is the final state for a demand that has passed all the assessments. The open state is the initial state for a demand that is created from the Service Catalog. The draft state is the state for a demand that is created from the Demand form.
質問 # 48
プロジェクト管理アプリケーションは、2 種類の外部依存関係をサポートします。彼らは何ですか?
2 つの答えを選択してください
- A. ソフト依存関係。
- B. タスクの依存関係。
- C. 依存関係を変更します。
- D. マイルストーンの依存関係。
- E. ハード依存性。
正解:A、E
解説:
The Project Management application supports two types of external dependencies: hard dependency and soft dependency. A hard dependency is a dependency that must be met before a task can start or finish. A soft dependency is a dependency that is preferred but not mandatory for a task to start or finish. You can find more information about these dependency types in the Product Documentation for ServiceNow.
質問 # 49
プロジェクト経費明細は、次の場合を除き、特定のソースに関連付けられたコストです。
- A. 固定資産。
- B. プログラム。
- C. ソフトウェア。
- D. リソース。
正解:B
解説:
According to the Project Expense Lines document, a project expense line is cost associated with a specific source, such as fixed assets, resource, or software. The program field on the project expense line form is not a source of cost, but a reference to the program that the project belongs to. Therefore, the correct answer is B.
Program. The other options are not correct, as they are sources of cost for a project expense line.
質問 # 50
ユーザーがアイデアを送信するときに選択できるアイデア カテゴリを保存するデフォルトのテーブルは何ですか?
- A. im_module
- B. im_idea_core
- C. im_category
- D. dmn_demand
正解:C
解説:
According to the Category Configuration document, the default table that stores the idea categories that a user can select from when submitting an idea is im_category. This table contains the predefined categories for ideas, such as Business Process, Customer Service, or IT Service. The other options are not correct, as they are not the tables that store the idea categories. The dmn_demand table stores the demand records that are created from the approved ideas. The im_module table stores the idea modules that are used to group ideas by different criteria. The im_idea_core table stores the core fields of the idea records.
質問 # 51
......