
あなたを合格させるSAP Certified Application Associate C-TS422-2021試験問題集で2024年05月21日には82問あります
C-TS422-2021無料試験学習ガイド!(更新された82問あります)
質問 # 36
What are the possible results of a production planning run in Advanced Planning (PP/DS)?
- A. Scheduling agreement schedule line
- B. Planned order
- C. Production order
- D. Purchase requistion
- E. Stock transport order
正解:A、B、D
質問 # 37
Which of the following elements does MRP take into account during net requirement calculation?
- A. Lot size
- B. Maximum stock level
- C. Purchase orders
- D. Safety stock
正解:A、D
質問 # 38
Which of the following is valid sequence of the main activities in production order processing?
- A. Creation, printing, release, goods issue, confirmation, goods receipt
- B. Creation, release, settlement, goods issue, confirmation, goods receipt
- C. Creation, availability check, release, material widrawal, confirmation
- D. Creation, release, printing, goods issue, confirmation, goods receipt
正解:C、D
質問 # 39
Which time elements are relevant for lead time scheduling of a production order?
- A. Setup time
- B. Total replenishment lead time
- C. Planned delivery time
- D. Float after production
正解:C、D
質問 # 40
Which materials have a negative quantity in a bill of materials or in a recipe?
- A. By-products
- B. Bulk materials
- C. Waste products
- D. Continuous flow materials
- E. Co-products
正解:A、D、E
質問 # 41
Which times elements does MRP consider in backward scheduling to determine he order dates for components from dependent requirements?
- A. Operation duration
- B. Planed delivery time
- C. Total replenishment lead time
- D. In-house production time
正解:B、D
質問 # 42
What does forecasting in demand planning cycle include?
- A. One-off events
- B. Past sales order quantites
- C. Past quotation quantities
- D. Past procurment quantities
- E. Market intelligence
正解:A、B、E
質問 # 43
What are some uses for the low-level code assigned to each material?
- A. It is used in MRP to determine the sequence in which materials are planned.
- B. It is used by engineering to indentify subitems in an engineering bill of material (BOM).
- C. It is used by product costing to determine how coast are rolled up.
- D. it is used by ATP to determine the priority of alternative components.
正解:A、C
質問 # 44
What are the consequences if the Dispatched operation status is set for a production order operation?
- A. You can reschedule the order using infinite scheduling in a planing table
- B. You can reschedule the operation using lead time scheduling in a planning table
- C. You can reschedule the operation using finite scheduling in planning table
- D. You can reschedule the operation using midpoint scheduling in a planning table.
正解:B、C
質問 # 45
How can you limit the validity of a bill of material (BOM)?
- A. By plant
- B. By period
- C. By material type
- D. By industry
正解:A、B
質問 # 46
What is the difference between co-products and by-products?
- A. Only by-products have a zero inventory valuation.
- B. Only co-products are identified by a special item category in the bill of material (BOM).
- C. Only co-products appear in the process or production order settlement rule.
- D. Only co-products can be manufactured in isolation from the main product.
正解:C
質問 # 47
What could be the reason for multiple commitment of invidula capacities, where several operations have the same scheduled dates on a work center (or resource) after planing?
- A. Alternative work centers are fully occupied.
- B. The work center has several invidula capacities.
- C. The Change Planning Direction indicator is set in strategy profile.
- D. The finite Scheduling indicator is NOT set in the strategy profile.
正解:B、D
質問 # 48
How would you define pegging in the context of Advanced Planning?
- A. An evaluation that is ordered according to the network structure of all related products and represents the coverage of issue elements
- B. An evaluation to verify if there are overstock situations in the balance between receipt and issue elements after the production planning run
- C. An evaluation that is ordered according to the bill-of-material structure of all related products and represents the relationship between the receipt and the issue elements
- D. An evaluation to verify if there are material or capacity shortages in the network after the production planning run.
正解:C
質問 # 49
Why would you use phantom assemblies?
- A. To reduce the number of changes required in bills of materials
- B. To increase the number of planning levels
- C. To reduce the number of material masters
- D. To make the assignment of components easier
- E. To simplify the structure of bills of materials
正解:A、D、E
質問 # 50
You want to schedule an operation finitely, without moving other operations. Which scheduing strategy do you select?
- A. Find slot
- B. Insert operation
- C. Squeeze in
- D. Schedule in working time only
正解:A
質問 # 51
Your proyect team decides to use a make-to-order planning strategy for strategic in discrete manufacturing.
What is the impact of this decision?
- A. A sales-order-specific planning run is required.
- B. Net requirement calcualtion is sales-order specific.
- C. Production orders specific stock is created
- D. Storage location MRP areas are required.
正解:A、B、C
質問 # 52
What detremines whatherthe planned independent requirements in MRP are consumed by other requrements?
- A. Requirements type
- B. Requirements profile
- C. Consumption sequence procedure
- D. Order type
正解:A
質問 # 53
In your plant, MRP is activated.
Which option do you have to exclude a materila from the MRP run?
- A. Use a specific material status
- B. Use a specific material group
- C. Use a specific MRP type
- D. Use specific MRP controller
正解:B、D
質問 # 54
In the Capacity Scheduling Table, which settings can you select for the planning strategy? Note: There are 3 correct answers to this question.
- A. Scheduling control
- B. Planning mode
- C. Direction
- D. Fixed pegging
- E. Finiteness level
正解:A、B、C
質問 # 55
You want to use capacity availability checks for production orders. Which settings have to be made for this?
- A. A checking rule must be assigned in the checking control
- B. The PRT Availability Check must be set in the checking control.
- C. The Relevant for Finite Scheduling indicator must be set
- D. An overall profile must be assigned in the checking control.
正解:C、D
質問 # 56
When working with bouth cross-plant and plant-specific material statuses n the material master, which statuses has the higest priority?
- A. The most restrictive status
- B. The last restrictive status
- C. The plant-specific status
- D. The cross-plant status
正解:A
質問 # 57
Which time elements are part of a routing operation?
- A. Float before production
- B. Pick/pack time
- C. Wait time
- D. Queue time
- E. Move time
正解:B、C、D
質問 # 58
Your production planners must execute planning only for specific resources. How can you achive this in advanced Planning(PP/DS)
- A. Use a resource group.
- B. Use a propagation range.
- C. Use a planning group.
- D. Use heuristic.
正解:D
質問 # 59
Your project used process orders for the production of liquid chemicals.
What can you define to ensure that the production flow happens only in physically connected tanks?
- A. Operation network
- B. Setup matrix
- C. Work center hierarchy
- D. Resource network
正解:C
質問 # 60
......
C-TS422-2021問題集はSAP Certified Application Associate認証済み試験問題と解答:https://jp.fast2test.com/C-TS422-2021-premium-file.html
実際に出ると確認されたC-TS422-2021試験問題集と解答でC-TS422-2021無料更新:https://drive.google.com/open?id=1QqZA4aOost6iUKKaJbFbBEaJaQRtDt35