質問 # 39
Where can you specify a processing sequence during an assignment?

  • A. Constraint Nets
  • B. Constraints
  • C. Pre- and Selection Conditions
  • D. Procedures

正解:D


質問 # 40
Which routing objects can object dependencies be assigned to?Note: There are 3 correct Answers to this question.

  • A. Inspection Characteristics
  • B. Sequences
  • C. Production Resource Tools
  • D. Operations
  • E. Component Allocation

正解:B、C、D


質問 # 41
How can you restrict the search result?Note: There are 2 correct Answers to this question.

  • A. Filters
  • B. Reselect
  • C. Validity
  • D. Change number

正解:A、B


質問 # 42
What do you have to keep in mind when working with value hierarchies?Note: There are 2 correct Answers to this question.

  • A. Value nodes are values.
  • B. Value nodes are not values.
  • C. Only available for characteristics with CHAR or NUM format.
  • D. Only available for characteristics with CHAR format.

正解:B、D


質問 # 43
You connected characteristics inside one class to organizational areas. What are the benefits?Note: There are 2 correct Answers to this question.

  • A. Users can always see all characteristics for all areas.
  • B. A check for the same classification is only possible inside one organizational area.
  • C. A check for the same classification is possible for all organizational areas.
  • D. Users can only work with characteristics depending on the authorization for a particular organizational area.

正解:B、C


質問 # 44
For which objects can you define a status network?Note: There are 2 correct Answers to this question.

  • A. Change record
  • B. Document info record
  • C. Change number record
  • D. Material master record

正解:A、B


質問 # 45
Which configuration process/scenario prevents the display of a BOM explosion in the sales order?Note: There are 2 correct Answers to this question.

  • A. Order BOM with processing mode AVC
  • B. Planned/Production Order without BOM explosion for both processing modes
  • C. Sales Order (SET) for both processing modes
  • D. Order BOM with processing mode classic and standard settings

正解:B、D


質問 # 46
A user releases a document info record with a change number. What effect does this action have on the document info record?Note: There are 2 correct Answers to this question.

  • A. The document displays the release key of the change number.
  • B. The document gets a revision level.
  • C. The document info record uses the validity of a change number.
  • D. All document fields are locked.

正解:B、C


質問 # 47
The value assignment interface for variant configuration can be structured using interface design and characteristic groups.What can be used depending on the processing mode?

  • A. You can only use Interface Design for Processing Mode AVC and Characteristic Groups for Processing Mode Classic.
  • B. You can only use Interface Design for Processing Mode Classic and Characteristic Groups only for Processing Mode AVC.
  • C. You can use interface design and characteristic groups for both processing modes.
  • D. You can use interface design for both processing modes, but characteristic groups only for Processing Mode AVC.

正解:B


質問 # 48
Which configuration process/scenario requires subitems in sales orders?

  • A. Planned/Production Order with BOM explosion
  • B. Planned/Production Order without BOM explosion
  • C. Order BOM
  • D. Sales Order (SET processing)

正解:D


質問 # 49
Why is a Work Center assigned to a Cost Center?

  • A. For capacity to use shift sequences
  • B. For scheduling to determine transportation time and queue time
  • C. For costing to use activity types
  • D. For assignment to find suitable people

正解:C


質問 # 50
What is the significance of the Additional Data tab in class maintenance?

  • A. It only exists for class nodes. It controls the usage in routings.
  • B. It only exists for variant classes. It controls the use in configuration profiles.
  • C. It only exists for class nodes. It controls the usage in BOMs.
  • D. It exists for all class types. It controls the permitted object types.

正解:C


質問 # 51
Why do you need a material BOM header status?

  • A. It controls the usage of the material BOM inside logistic chain.
  • B. It controls the usage of an assembly indicator inside material BOM.
  • C. It controls the usage of the material BOM items inside logistic chain.
  • D. It controls the usage of the material BOM by a certain user.

正解:A


質問 # 52
When or why do you assign production resources and tools to an operation?

  • A. To map the equipment of the Work Center with production resources and tools.
  • B. To provide additional components which cannot be assigned to the BOM.
  • C. To make them available for operation inspection only.
  • D. To make additional production resources and tools available that do not belong to the equipment of the Work Center.

正解:D


質問 # 53
What is the significance of the control key?Note: There are 3 correct Answers to this question.

  • A. It is an optional field in the Work Center.
  • B. It defines the usage of Work Centers in routings.
  • C. It is a value that can be used as a default value in the routing.
  • D. It is a value that can be copied to the routing as a reference.
  • E. It is a mandatory field in the Work Center.

正解:C、D、E


質問 # 54
Which type of object dependencies must contain $self, $parent, or $root at least once?

  • A. All types of object dependencies
  • B. Constraints
  • C. Pre- and Selection Conditions
  • D. Procedures

正解:B


質問 # 55
Which of the following objects can you connect with a revision level?Note: There are 2 correct Answers to this question.

  • A. Classes
  • B. Work Center
  • C. Material Master
  • D. Document

正解:C、D


質問 # 56
You want to use a procedure to set a value in a single-level configuration using a variant table T1.Variant table T1 has only two characteristics C1 and C2. C1 is a key field.The following syntax is incorrect: table T1 (C1 = C1, C2 = C2)Where do you have to insert $self?

  • A. table T1 (C1 = C1, C2 = $self.C2)
  • B. table T1 ($self.C1 = C1, C2 = C2)
  • C. table T1 (C1 = C1, $self.C2 = C2)
  • D. table T1 (C1 = $self.C1, C2 = C2)

正解:A


質問 # 57
Which organizational level is a Work Center assigned to?

  • A. Client
  • B. Storage location
  • C. Plant
  • D. Production supervisor

正解:C


質問 # 58
You use the app Find Objects in Classes. How do you find a class?Note: There are 2 correct Answers to this question.

  • A. Via assigned characteristics
  • B. Via change number
  • C. Via Class BOM
  • D. Via hierarchy

正解:A、D


質問 # 59
What objects can be changed with a change number? Note: There are 2 correct Answers to this question.

  • A. Task Lists
  • B. Work Centers
  • C. Cost Centers
  • D. Bills of Material

正解:A、D


質問 # 60
What controls the material BOM item category?Note: There are 2 correct Answers to this question.

  • A. A work center is required.
  • B. A change number is required.
  • C. A material number is required.
  • D. A negative quantity is allowed.

正解:C、D


質問 # 61
......


SAP C-TS411-2021認定を取得することは、SAP S/4HANA R&Dエンジニアリングと一緒に働く個人にとって価値のある成果です。この認定は、その分野における高い知識と専門知識を証明し、キャリアアップの機会を提供することができます。さらに、認定を維持するには、継続的なプロフェッショナル開発が必要であり、認定された個人がSAP S/4HANA R&Dエンジニアリングの最新の進歩に常に最新の状態になることを保証しています。

 

最新でリアルなC-TS411-2021試験問題集解答:https://drive.google.com/open?id=1toXpbxQsNZ8Rjo6CNkVc6O1zJmYKrbG_

あなたをお手軽に合格させるC-TS411-2021試験正確なPDF問題:https://jp.fast2test.com/C-TS411-2021-premium-file.html


弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

我々の働いている時間: ( GMT 0:00-15:00 )
月曜日から土曜日まで

サポート: 現在連絡 

English Deutsch 繁体中文 한국어